Question

In: Operations Management

Remedies for Breach. Reefpoint Brewhouse in Racine, Wisconsin, contracted with Forman Awnings and Construction, LLC, for...

Remedies for Breach. Reefpoint Brewhouse in Racine, Wisconsin, contracted with Forman Awnings and Construction, LLC, for the fabrication and installation of an awning system over an outdoor seating area. After the system was complete, Reefpoint expressed concerns about the workmanship but did not give Forman a chance to make repairs. The brewhouse used the awning for two months and then had it removed so that siding on the building could be replaced. The parties disagreed about whether cracked and broken welds observed after the removal of the system were due to shoddy workmanship. Reefpoint paid only $400 on the contract price of $8,161. Can Reefpoint rescind the contract and obtain a return of its $400? Is Forman entitled to recover the difference between Reefpoint’s payment and the contract price? Discuss.

Solutions

Expert Solution

Though Reefpoint had concerns about the awning system, they still accepted it from Forman. Also Reefpoint did not give Forman a chance to make repairs in the awning and got it replaced because of some other construction issue.

Reefpoint had taken the delivery of the product, though having concerns with the quality. The product was installed and used for a particular period of time. Reefpoint clearly had the benefit of its bargain. The reason to remove the awning system owned to an external factor, not at all concerned with Forman. The law states that at the time of delivery, if the buyer is not satisfied with the quality of the product, the buyer can repudiate or can accept the product, seeking some reduction in its price. But once the buyer accepts and uses the product, remedy of rescission is not available.

So Reefpoint cannot rescind the contract and opt for the refund. Instead Forman is entitled to recover the difference after reducing the quality deteroriment price


Related Solutions

What are some of the remedies of the seller if there is a breach of a...
What are some of the remedies of the seller if there is a breach of a sales contract? Provide an example. Do some Internet research and find a case that involves a UCC contract and that discusses a UCC remedy available to the seller. Provide a brief summary of the facts and an explanation of the court's decision. Do you agree with the decision? What are some of the remedies of the buyer if there is a breach of a...
CHECKLIST FOR CHAPTER # 13 --- BREACH AND REMEDIES MNGT 262 900 1. Be familiar with...
CHECKLIST FOR CHAPTER # 13 --- BREACH AND REMEDIES MNGT 262 900 1. Be familiar with the four basic categories of damages. 2. Distinguish compensatory damages in breach of contracts for the sale of goods from contracts from the sale of land, and from construction contracts. 3. In breach of contracts situations, what duty is the injured party held to? Explain what is meant by mitigation of damages. 4. Distinguish liquidated damages from penalties. 5. What two questions must a...
Define, explain and give a case study example of the following terms: • Remedies of Breach...
Define, explain and give a case study example of the following terms: • Remedies of Breach • Implied Warranties • Intangible Property
Offer and Acceptance), 7 (Consideration), 10 (Writing) and 13 (Breach of Contract and Remedies). Your written...
Offer and Acceptance), 7 (Consideration), 10 (Writing) and 13 (Breach of Contract and Remedies). Your written answer should be between 1000 and 1200 words. 20 marks
Dalton Construction Co. contracted to build a bridge for $8,000,000. Construction began in 2018 and was...
Dalton Construction Co. contracted to build a bridge for $8,000,000. Construction began in 2018 and was completed in 2019. Data relating to the construction are: 2018 2019 Costs incurred during the year $2,105,600 $2,408,400 Estimated costs to complete 2,374,400 ― Dalton uses the percentage-of-completion method. Part 1 How much revenue should be reported for 2018? Part 2 Make the entry to record progress billings of $2,905,600 during 2018. (Credit account titles are automatically indented when amount is entered. Do not...
Rajbir Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2018 and was...
Rajbir Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2018 and was completed in 2019. Data relating to the construction are: 2018 2019 Costs incurred during the year $3,300,000 $2,750,000 Estimated costs to complete 2,700,000 — Raj uses the percentage-of-completion method. Instructions (a) How much revenue should be reported for 2018? Show your computation. (b) Make the entry to record progress billings of $4,100,000 during 2018. (c) Make the entry to record the revenue and gross...
In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in...
In January 2010, Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in early 2010 and was completed in 2011. The following additional information is available:                                                                                                    2010                       2011        Costs incurred............................................................. $ 2,430,000            $ 2,700,000        Estimated costs to complete............................................. 2,600,000                         —        Collections during the year.............................................. 2,400,000               3,600,000          Billings for the year …………………………………………..     2,800,000                3,200,000 Used the percentage-of-completion method. Instructions Under the contract-based approach, a)     How much revenue should be reported...
Titania Inc. is issuing bonds to finance the construction of anew plant in Wisconsin. These...
Titania Inc. is issuing bonds to finance the construction of a new plant in Wisconsin. These bonds are being offered with a face value of $1000, a coupon rate of 9% (paid annually), and a maturity of 18 years. The current market interest rate for similar financial assets is 7% per year (compounded annually). a. Find the pure/fair price of each bond at the time of issuance. b. Find the fair price of each bond if purchase ends up being...
Advise when a contractor will not be in breach of a construction contract as defined under...
Advise when a contractor will not be in breach of a construction contract as defined under the Housing Grants Construction and Regeneration Act 1996, if he wants to stop work on a project due to non-payment.
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in...
In January 2019, Miller Construction Corp. contracted to construct a building for $3,600,000. Construction started in early 2019 and was completed in 2020. The following additional information is available: 2019 2020 Cost Incurred $1,458,000 $1,620,000 Estimated costs to complete 1,560,000 - Billed 1,700,000 1,900,000 Collections during the year 1,440,000 2,160,000 Miller uses the percentage-of-completion method. Under the contract-based approach for percentage completion, a) How much revenue should Miller report for 2019 and 2020? b) Prepare all journal entries for 2019...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT