Question

In: Accounting

Use the following information to answer the questions in this quiz. Please show your work by...

Use the following information to answer the questions in this quiz.

Please show your work by submitting a Word, Excel, or JPEG file in the "Project 2 Drop Box".

INFORMATION OLD MACHINE:

Original Purchase Price

$     550,000.00

Original Life

10 YEARS

Remaining Life

5 YEARS

Straight line depreciation in use

Salvage Value

$      50,000.00

Current Fair Market Value

$     260,000.00

INFORMATION NEW MACHINE A:

Purchase Price

     $895,000.00

Estimated Life

5 YEARS

Use Straight Line Depreciation Method

Estimated Salvage Value

$      10,000.00

Estimated Net Operating Cash Flow Increase/Decrease (Prior to Depreciation and Taxes)

   End of Year 1

$     100,000.00

   End of Year 2

$     150,000.00

   End of Year 3

$     250,000.00

   End of Year 4

$     200,000.00

   End of Year 5

$     200,000.00

ASSUMPTIONS:

   Tax Rate

40%

   WACC Rate

7%

If you keep the old machine, the NPV is:

A.

118,567

B.

117,653

C.

30,489

D.

300,410

40 points

Question 2

If you sell the old machine and buy new machine A, the NPV will be:

10,619

-4,995

-5,859

2,907

40 points

Question 3

What decision do you suggest?

A.

Keep the old machine and do not buy the new machine.

B.

Sell the old machine and buy the new machine.

10 points

Question 4

The cash flow creating the least amount of risk or the cash flow we should be certain of is

A.

The cost of the new machine.

B.

The projected cash flow saving in year 4.

C.

The tax benefit from depreciation

D.

The salvage value on the new machine.

Solutions

Expert Solution


Related Solutions

Use the following information to answer the next three questions. Show ALL your work! Consider the...
Use the following information to answer the next three questions. Show ALL your work! Consider the cash flows from two mutually exclusive projects: Cash Flow Year Project A Project B 0 -$420,000 -$420,000 1 $150,000 $390,000 2 $230,000 $110,000 3 $321,000 $140,000 The appropriate discount rate is 11.7%. -Calculate the net present value (NPV) for both projects, and determine which project should be accepted based on NPV. Round both NPVs to the nearest dollar. -Calculate the internal rate of return...
Please show work and explain. Use the following to answer questions 5 and 6: On January...
Please show work and explain. Use the following to answer questions 5 and 6: On January 1, 2017, Nevada Corporation issued 8% bonds with a face value of $10,000,000. The bonds sold for $11,487,747. They mature in ten years and pay interest semiannually on June 30th and December 31st. The market rate of interest at the time the bonds were issued was 6%. Nevada uses the effective interest method for amortizing bond discounts and premiums. Total interest expense Nevada would...
Please show all work and formulas Please use the following information to answer this question. State    ...
Please show all work and formulas Please use the following information to answer this question. State     Probability       A                     B                      C Boom   .3                     -10%                5%                   0% Normal            .4                     5                      3                      2                      Bust     .3                     10                    -5                     2 Find the expected return and variance of the portfolio if an investor spent $5000 on A, $8000 on B and $7000 on C.
Please show all work and formulas Please use the following information to answer this question. State    ...
Please show all work and formulas Please use the following information to answer this question. State     Probability       A                     B                      C Boom   .3                     -10%                5%                   0% Normal            .4                     5                      3                      2                      Bust     .3                     10                    -5                     2 Find the expected return and variance of the portfolio if an investor spent $5000 on A, $8000 on B and $7000 on C.
Answer the following questions and use Excel to show your work. The mean time required to...
Answer the following questions and use Excel to show your work. The mean time required to complete a certain type of construction project is 52 weeks with a standard deviation of 3 weeks. Answer questions 4–7 using the preceding information and modeling this situation as a normal distribution. 4. What is the probability of the completing the project in no more than 52 weeks? a) 0.25 b) 0.50 c) 0.75 d) 0.05 5. What is the probability of the completing...
Answer the following questions and use Excel to show your work. A student has an important...
Answer the following questions and use Excel to show your work. A student has an important exam coming up and is contemplating not studying for the exam in order to attend a party with his friends. The student must earn a minimum score of 70% on the exam in order to successfully maintain his desired GPA. Suppose the student knows in advance that the exam will consist of 20 multiple-choice questions with 4 possible answers for each question. Answer questions...
Answer the following questions and use Excel to show your work. Customers arrive at a supermarket...
Answer the following questions and use Excel to show your work. Customers arrive at a supermarket check-out counter with an average arrival rate of 9 customers per hour. Answer questions 8–10 using the preceding information and modeling this situation as a Poisson distribution. 8. What is the probability of less than 5 customers arriving at the supermarket check-out counter in a given 1-hour period? a) 0.054 b) 0.446 c) 0.359 d) 0.612 9. What is the probability of exactly 12...
Answer the following questions and use Excel or this document to show your work. 1. Consider...
Answer the following questions and use Excel or this document to show your work. 1. Consider the following results for two samples randomly taken from two normal populations with equal variances. Sample I Sample II Sample Size 28 35 Sample Mean 48 44 Population Standard Deviation 9 10 a. Develop a 95% confidence interval for the difference between the two population means. b. Is there conclusive evidence that one population has a larger mean? Explain.
show your work please Given the following data, answer the following questions: (Assume the second column...
show your work please Given the following data, answer the following questions: (Assume the second column to be the dependent variable) a) Construct the scatter diagram. b) Compute the linear correlation coefficient r and value of r-critical. c) Is r statistically significant at an alpha of 5%?. Explain why or why not d) What is the standard error of regression? e) Identify any outliers (do not remove them). Show your work. If no outliers, indicate N/A f) Compute the equation...
Please show all work and formula: Please use the information on the table below to answer...
Please show all work and formula: Please use the information on the table below to answer this question. Security                       Actual Return             Beta A                                 12%                             1.2 B                                  10%                             1.0 C                                  14%                             1.4 Assume the risk-free interest rate is 1% and the market risk premium is 5.5%. An investor would like to invest $40,000 in Security A, $25,000 in security B and $50,000 in Security C. Find the portfolio’s expected return. Find the portfolio’s actual return. Based on your answers to a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT