In: Accounting
Barnville applies overhead at a rate of $6.00 per direct labor hour. The direct labor rate is $10.00 per hour. During June, Jobs B, C, and D were started. The following is information on costs incurred in June:
Job Direct materials Direct labor hours
A $200 5
B $380 18
C $500 40
D
$150
8
Jobs A, B and C have been completed. At June 30, only Job D is
still is process.
Question 1: Required: Calculate the cost of the completed
jobs.
Question 2: Required: What is the balance in Work in process
inventory on June 30 (cost of the unfinished job)?
Solution
Barnville
Jobs |
Direct materials cost |
Direct labor at $10 per hour |
Overhead at $6 per direct labor hour |
Total cost |
A |
$200 |
$50 |
$30 |
$280 |
B |
$380 |
$180 |
$108 |
$668 |
C |
$500 |
$400 |
$240 |
$1,140 |
Given direct labor hours for the jobs are as follows,
Direct labor cost is calculated as follows,
A $10 x 5 hrs = $50
B $10 x 18 hrs = $180
C $10 x 40 hrs = $400
Overhead cost is calculated as follows,
A $6 x 5 hrs = $30
B $6 x 18 hrs = $108
C $6 x 40 hrs = $240
Job D is unfinished, hence cost of job D represents the balance in work in process inventory as at June 30.
Cost of Job D is computed as follows,
Direct materials$150
Direct labor ($10 x 8 hours)$80
Overhead cost ($6 x 8 hours)$48
Total cost$278
Hence, the balance in work in process inventory on June 30 is $278.
Since the percentage of completion is not provided, the entire cost of Job D is shown as work in process inventory.