Question

In: Finance

We are evaluating a project that costs $105790, has a seven-year life, and has no salvage...

We are evaluating a project that costs $105790, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4108 units per year. Price per unit is $54, variable cost per unit is $24, and fixed costs are $83887 per year. The tax rate is 31 percent, and we require a 9 percent return on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within +/-11 percent. What is the NPV of the project in worst-case scenario? (Negative amount should be indicated by a minus sign. Round your final answer to the nearest dollar amount. Omit the "$" sign and commas in your response. For example, $123,456.78 should be entered as 123457.)

Solutions

Expert Solution

Time line 0 1 2 3 4 5 6 7
Cost of new machine -105790
=Initial Investment outlay -105790
Unit sales 3656.12 3656.12 3656.12 3656.12 3656.12 3656.12 3656.12
Profits =no. of units sold * (sales price - variable cost) 78314.09 78314.09 78314.09 78314.09 78314.09 78314.09 78314.09
Fixed cost -93114.6 -93114.6 -93114.57 -93114.57 -93114.57 -93114.57 -93114.6
-Depreciation Cost of equipment/no. of years -15112.9 -15112.9 -15112.86 -15112.86 -15112.86 -15112.86 -15112.9
=Pretax cash flows -29913.3 -29913.3 -29913.34 -29913.34 -29913.34 -29913.34 -29913.3
-taxes =(Pretax cash flows)*(1-tax) -20640.2 -20640.2 -20640.2 -20640.2 -20640.2 -20640.2 -20640.2
+Depreciation 15112.86 15112.86 15112.857 15112.857 15112.857 15112.857 15112.86
=after tax operating cash flow -5527.35 -5527.35 -5527.345 -5527.345 -5527.345 -5527.345 -5527.35
+Tax shield on salvage book value =Salvage value * tax rate 0
=Terminal year after tax cash flows 0
Total Cash flow for the period -105790 -5527.35 -5527.35 -5527.345 -5527.345 -5527.345 -5527.345 -5527.35
Discount factor= (1+discount rate)^corresponding period 1 1.09 1.1881 1.295029 1.4115816 1.538624 1.6771001 1.828039
Discounted CF= Cashflow/discount factor -105790 -5070.96 -4652.26 -4268.125 -3915.711 -3592.395 -3295.775 -3023.65
NPV= Sum of discounted CF= -133609

Related Solutions

We are evaluating a project that costs $118,894, has a seven-year life, and has no salvage...
We are evaluating a project that costs $118,894, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4,101 units per year. Price per unit is $47, variable cost per unit is $30, and fixed costs are $82,846 per year. The tax rate is 36 percent, and we require a 12 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $104,299, has a seven-year life, and has no salvage...
We are evaluating a project that costs $104,299, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4,235 units per year. Price per unit is $50, variable cost per unit is $30, and fixed costs are $81,714 per year. The tax rate is 36 percent, and we require a 9 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $827,000, has an seven-year life, and has no salvage...
We are evaluating a project that costs $827,000, has an seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 103,000 units per year. Price per unit is $35, variable cost per unit is $22, and fixed costs are $831,135 per year. The tax rate is 38 percent, and we require a 16 percent return on this project. The projections given for price, quantity, variable costs,...
We are evaluating a project that costs $1,582,000, has a seven-year life, and has no salvage...
We are evaluating a project that costs $1,582,000, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 87,100 units per year. Price per unit is $34.30, variable cost per unit is $20.55, and fixed costs are $751,000 per year. The tax rate is 30 percent, and we require a return of 12 percent on this project. Calculate the base-case operating cash flow and...
We are evaluating a project that costs $1,638,000, has a seven-year life, and has no salvage...
We are evaluating a project that costs $1,638,000, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 87,900 units per year. Price per unit is $34.70, variable cost per unit is $20.95, and fixed costs are $759,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project.    Suppose the projections given for price,...
We are evaluating a project that costs $116335, has a seven-year life, and has no salvage...
We are evaluating a project that costs $116335, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4367 units per year. Price per unit is $55, variable cost per unit is $24, and fixed costs are $80248 per year. The tax rate is 36 percent, and we require a 9 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $100356, has a seven-year life, and has no salvage...
We are evaluating a project that costs $100356, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4229 units per year. Price per unit is $51, variable cost per unit is $30, and fixed costs are $81802 per year. The tax rate is 33 percent, and we require a 11 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $115571, has a seven-year life, and has no salvage...
We are evaluating a project that costs $115571, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4293 units per year. Price per unit is $45, variable cost per unit is $25, and fixed costs are $81427 per year. The tax rate is 35 percent, and we require a 8 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $619,500, has a seven-year life, and has no salvage...
We are evaluating a project that costs $619,500, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,000 units per year. Price per unit is $43, variable cost per unit is $30, and fixed costs are $705,000 per year. The tax rate is 22 percent, and we require a return of 11 percent on this project.     a-1. Calculate the accounting break-even point....
We are evaluating a project that costs $103463, has a seven-year life, and has no salvage...
We are evaluating a project that costs $103463, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4108 units per year. Price per unit is $52, variable cost per unit is $29, and fixed costs are $82337 per year. The tax rate is 36 percent, and we require a 9 percent return on this project. Suppose the projections given for price, quantity, variable...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT