Question

In: Finance

We are evaluating a project that costs $100356, has a seven-year life, and has no salvage...

We are evaluating a project that costs $100356, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4229 units per year. Price per unit is $51, variable cost per unit is $30, and fixed costs are $81802 per year. The tax rate is 33 percent, and we require a 11 percent return on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within +/-12 percent. What is the NPV of the project in worst-case scenario? (Negative amount should be indicated by a minus sign. Round your final answer to the nearest dollar amount. Omit the "$" sign and commas in your response. For example, $123,456.78 should be entered as 123457.)

Solutions

Expert Solution

Time line 0 1 2 3 4 5 6 7
Cost of new machine -100356
=Initial Investment outlay -100356
Unit sales 3721.52 3721.52 3721.52 3721.52 3721.52 3721.52 3721.52
Profits =no. of units sold * (sales price - variable cost) 41978.75 41978.75 41978.746 41978.746 41978.746 41978.746 41978.75
Fixed cost -91618.2 -91618.2 -91618.24 -91618.24 -91618.24 -91618.24 -91618.2
-Depreciation Cost of equipment/no. of years -14336.6 -14336.6 -14336.57 -14336.57 -14336.57 -14336.57 -14336.6
=Pretax cash flows -63976.1 -63976.1 -63976.07 -63976.07 -63976.07 -63976.07 -63976.1
-taxes =(Pretax cash flows)*(1-tax) -42864 -42864 -42863.96 -42863.96 -42863.96 -42863.96 -42864
+Depreciation 14336.57 14336.57 14336.571 14336.571 14336.571 14336.571 14336.57
=after tax operating cash flow -28527.4 -28527.4 -28527.39 -28527.39 -28527.39 -28527.39 -28527.4
+Tax shield on salvage book value =Salvage value * tax rate -4.8E-12
=Terminal year after tax cash flows -4.8E-12
Total Cash flow for the period -100356 -28527.4 -28527.4 -28527.39 -28527.39 -28527.39 -28527.39 -28527.4
Discount factor= (1+discount rate)^corresponding period 1 1.11 1.2321 1.367631 1.5180704 1.6850582 1.8704146 2.07616
Discounted CF= Cashflow/discount factor -100356 -25700.4 -23153.5 -20858.98 -18791.88 -16929.62 -15251.91 -13740.5
NPV= Sum of discounted CF= -234783
IRR is discount rate at which NPV = 0 = 11.00%

Related Solutions

We are evaluating a project that costs $118,894, has a seven-year life, and has no salvage...
We are evaluating a project that costs $118,894, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4,101 units per year. Price per unit is $47, variable cost per unit is $30, and fixed costs are $82,846 per year. The tax rate is 36 percent, and we require a 12 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $104,299, has a seven-year life, and has no salvage...
We are evaluating a project that costs $104,299, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4,235 units per year. Price per unit is $50, variable cost per unit is $30, and fixed costs are $81,714 per year. The tax rate is 36 percent, and we require a 9 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $827,000, has an seven-year life, and has no salvage...
We are evaluating a project that costs $827,000, has an seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 103,000 units per year. Price per unit is $35, variable cost per unit is $22, and fixed costs are $831,135 per year. The tax rate is 38 percent, and we require a 16 percent return on this project. The projections given for price, quantity, variable costs,...
We are evaluating a project that costs $1,582,000, has a seven-year life, and has no salvage...
We are evaluating a project that costs $1,582,000, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 87,100 units per year. Price per unit is $34.30, variable cost per unit is $20.55, and fixed costs are $751,000 per year. The tax rate is 30 percent, and we require a return of 12 percent on this project. Calculate the base-case operating cash flow and...
We are evaluating a project that costs $1,638,000, has a seven-year life, and has no salvage...
We are evaluating a project that costs $1,638,000, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 87,900 units per year. Price per unit is $34.70, variable cost per unit is $20.95, and fixed costs are $759,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project.    Suppose the projections given for price,...
We are evaluating a project that costs $116335, has a seven-year life, and has no salvage...
We are evaluating a project that costs $116335, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4367 units per year. Price per unit is $55, variable cost per unit is $24, and fixed costs are $80248 per year. The tax rate is 36 percent, and we require a 9 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $115571, has a seven-year life, and has no salvage...
We are evaluating a project that costs $115571, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4293 units per year. Price per unit is $45, variable cost per unit is $25, and fixed costs are $81427 per year. The tax rate is 35 percent, and we require a 8 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $619,500, has a seven-year life, and has no salvage...
We are evaluating a project that costs $619,500, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 90,000 units per year. Price per unit is $43, variable cost per unit is $30, and fixed costs are $705,000 per year. The tax rate is 22 percent, and we require a return of 11 percent on this project.     a-1. Calculate the accounting break-even point....
We are evaluating a project that costs $105790, has a seven-year life, and has no salvage...
We are evaluating a project that costs $105790, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4108 units per year. Price per unit is $54, variable cost per unit is $24, and fixed costs are $83887 per year. The tax rate is 31 percent, and we require a 9 percent return on this project. Suppose the projections given for price, quantity, variable...
We are evaluating a project that costs $103463, has a seven-year life, and has no salvage...
We are evaluating a project that costs $103463, has a seven-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 4108 units per year. Price per unit is $52, variable cost per unit is $29, and fixed costs are $82337 per year. The tax rate is 36 percent, and we require a 9 percent return on this project. Suppose the projections given for price, quantity, variable...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT