AlwaysRain Irrigation, Inc., would like to determine capacity requirements for the next four years. Currently two production lines are in place for making bronze and plastic sprinklers. Three types of sprinklers are available in both bronze and plastic: 90-degree nozzle sprinklers, 180-degree nozzle sprinklers, and 360-degree nozzle sprinklers. Management has forecast demand for the next four years as follows:
YEARLY DEMAND | ||||||||
1 (IN 000s) | 2 (IN 000s) | 3 (IN 000s) | 4 (IN 000s) | |||||
Plastic 90 | 31 | 40 | 52 | 53 | ||||
Plastic 180 | 14 | 16 | 17 | 14 | ||||
Plastic 360 | 52 | 52 | 63 | 65 | ||||
Bronze 90 | 6 | 6 | 5 | 15 | ||||
Bronze 180 | 2 | 2 | 5 | 13 | ||||
Bronze 360 | 10 | 12 | 11 | 22 | ||||
Both production lines can produce all the different types of
nozzles. The bronze machines needed for the bronze sprinklers
require three operators and can produce up to 18,000 sprinklers.
The plastic injection molding machine needed for the plastic
sprinklers requires four operators and can produce up to 300,000
sprinklers. Three bronze machines and only one injection molding
machine are available.
What are the capacity requirements for the next four years? (Assume that there is no learning.) (Enter the demand values in thousands. Round your answers to 2 decimal places.)
Year 1 | Year 2 | Year 3 | Year 4 | |||||
Plastic | ||||||||
Demand for plastic sprinklers | ||||||||
Percentage of capacity used | % | % | % | % | ||||
Machine requirements | ||||||||
Labor requirements | ||||||||
Bronze | ||||||||
Demand for bronze sprinklers | ||||||||
Percentage of capacity used | % | % | % | % | ||||
Machine requirements | ||||||||
Labor requirements | ||||||||
(a)
Plastic Machines
Production = 300000
There is just one machine available.
Available capacity per year = 300000
Required operators = 4 per machine
Bronze Machines
Production = 18000
They are 3 machines available
Total production =3 *18000 = 54000
Required operators = 3 per machine
Formulas used:
% of capacity used = (Demand /Capacity) * 100
Machine requirements = (Demand/Capacity of a single machine)
Labor requirements = Machine requirements * No of operators required per machine
Plastic | Year 1 | Year 2 | Year 3 | Year 4 |
Demand (000's) | 97 | 108 | 132 | 132 |
Capacity (000's) | 300 | 300 | 300 | 300 |
% of capacity used | 32.33% | 36.00% | 44.00% | 44.00% |
Machine requirement | 0.323 | 0.360 | 0.440 | 0.440 |
Labor requirements | 1.293 | 1.440 | 1.760 | 1.760 |
Bronze | Year 1 | Year 2 | Year 3 | Year 4 |
Demand (000's) | 18 | 20 | 21 | 50 |
Capacity (000's) | 54 | 54 | 54 | 54 |
% of capacity used | 33.33% | 37.04% | 38.89% | 92.59% |
Machine requirement | 0.333 | 0.370 | 0.389 | 0.926 |
Labor requirements | 1.000 | 1.111 | 1.167 | 2.778 |
(b) There is sufficient capacity to meet the demand over the next 4 years.