In: Finance
Dog Up! Franks is looking at a new sausage system with an installed cost of $897,000. This cost will be depreciated straight-line to zero over the project's 9-year life, at the end of which the sausage system can be scrapped for $138,000. The sausage system will save the firm $276,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $64,400. Required: If the tax rate is 33 percent and the discount rate is 13 percent, what is the NPV of this project?
Initial Investment for the Project
Initial Investment for the Project = Cost of the asset + Working capital needed
= $897,000 + $64,400
= $961,400
Annual Operating Cash Flow (OCF)
Annual Operating Cash Flow (OCF) = Pretax Savings(1 – Tax Rate) + (Depreciation x Tax Rate)
= [$276,000 x (1 – 0.33)] + [($897,000 / 9 Years) x 0.33]
= [$276,000 x 0.67] + [$99,666.67 x 0.33]
= $184,920 + $32,890
= $217,810
Year 1-8 Cash flow = $217,810
Year 9 Cash flow = Annual operating cash flow + Release of working capital -After-Tax Salvage value
= $217,810 + $64,400 + [$138,000 x (1 – 0.33)]
= $217,810 + $64,400 + [$138,000 x 0.67]
= $217,810 + $64,400 + $92,460
= $374,670
Net Present Value of the Project
| 
 Year  | 
 Annual Cash Flow ($)  | 
 Present Value factor at 13.00%  | 
 Present Value of Cash Flow ($)  | 
| 
 1  | 
 2,17,810  | 
 0.8849558  | 
 1,92,752.21  | 
| 
 2  | 
 2,17,810  | 
 0.7831467  | 
 1,70,577.18  | 
| 
 3  | 
 2,17,810  | 
 0.6930502  | 
 1,50,953.26  | 
| 
 4  | 
 2,17,810  | 
 0.6133187  | 
 1,33,586.95  | 
| 
 5  | 
 2,17,810  | 
 0.5427599  | 
 1,18,218.54  | 
| 
 6  | 
 2,17,810  | 
 0.4803185  | 
 1,04,618.18  | 
| 
 7  | 
 2,17,810  | 
 0.4250606  | 
 92,582.46  | 
| 
 8  | 
 2,17,810  | 
 0.3761599  | 
 81,931.38  | 
| 
 9  | 
 3,74,670  | 
 0.3328848  | 
 1,24,721.96  | 
| 
 TOTAL  | 
 11,69,942.12  | 
||
Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment
= $11,69,942.12 - $961,400
= $208,542.12
“Hence, the NPV for this Project will be $208,542.12”
NOTE
The Formula for calculating the Present Value Factor is [1/(1 + r)n], Where “r” is the Discount/Interest Rate and “n” is the number of years.