Question

In: Accounting

Teledex Company manufactures product to customers’ specification and uses a job-order costing system. The company uses...

Teledex Company manufactures product to customers’ specification and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead(assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year. Department Fabricating Machining Assembly Total Plant Manufacturing overhead 350,000 400,000 90,000 840,000 Direct Labor 200,000 100,000 300,000 600,000 Jobs require varying amounts of work in the three departments. The coopers job, for example, would have required manufacturing costs in the three departments as follows: Department Fabricating Machining Assembly Total Plant Direct Materials 3,000 200 1,400 4,500 Direct Labor 2,800 500 9,500 Manufacturing overhead ? ? ? ? Required: 1. Using the company’s plantwide approach: a. Compute the plantwide predetermined overhead rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the coopers job 2. Suppose that instead od using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 3. Explain the difference between the manufacturing overhead that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs 150% of total manufacturing cost (direct materials, direct labor and applied overhead). What was the company’s bid price on the Koopers Job using a plantwide predetermined overhead rate? What would the bid price have been if departmental predetermined overhead rate had been used to apply overhead cost?

Solutions

Expert Solution

Thank you for your patience. Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Teledex
Answer 1 a
Calculation of Plant wide OH Rate Fabricating Machining Assembly Total Note
Manufacturing overhead    350,000.00 400,000.00     90,000.00 840,000.00 A
Direct Labor    200,000.00 100,000.00 300,000.00 600,000.00 B
Predetermined OH Rate                1.40 C=A/B
Answer 1 b
Allocated OH for Koopers Job Fabricating Machining Assembly Total
Direct Labor        2,800.00           500.00       9,500.00     12,800.00 D
Predetermined OH Rate                1.40               1.40               1.40 See C
Allocated OH        3,920.00           700.00     13,300.00     17,920.00 E=C*D
Answer 2 a
Calculation of Departmental OH Rate Fabricating Machining Assembly Note
Manufacturing overhead    350,000.00 400,000.00     90,000.00 F
Direct Labor    200,000.00 100,000.00 300,000.00 G
Predetermined OH Rate                1.75               4.00               0.30 H=F/G
Answer 2 b
Allocated OH for Koopers Job Fabricating Machining Assembly Total
Direct Labor        2,800.00           500.00       9,500.00     12,800.00 I
Predetermined OH Rate                1.75               4.00               0.30 See H
Allocated OH        4,900.00       2,000.00       2,850.00        9,750.00 J=H*I
Answer 3 OH allocated
Single rate      17,920.00
Departmental rate        9,750.00
Difference        8,170.00
Answer 4 a
Bid price under plant wide OH rate Fabricating Machining Assembly Total
Direct Materials        3,000.00           200.00       1,400.00        4,600.00 K
Direct Labor        2,800.00           500.00       9,500.00     12,800.00 See I
Allocated OH        3,920.00           700.00     13,300.00     17,920.00 See E
Total manufacturing cost        9,720.00       1,400.00     24,200.00     35,320.00 L=K+E+I
Bid price     52,980.00 M= L*150%
Answer 4 b
Bid price under departmental OH rate Amount $
Direct Materials        4,600.00 See K
Direct Labor      12,800.00 See I
Allocated OH        9,750.00 See J
Total manufacturing cost      27,150.00 N=K+I+J
Bid price      40,725.00 O=N*150%

Related Solutions

McDuff Company uses a job-order costing system to compute product costs. There are two producing departments...
McDuff Company uses a job-order costing system to compute product costs. There are two producing departments (P1 and P2) and two support departments (S1 and S2). The costs incurred in S1 and S2 are allocated to Departments A and B and included in their factory overhead rates for costing products. S1 costs are allocated based on the number of employees, S2 costs are allocated based on direct labor hours, and the production departmental overhead rates are also based on direct...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,151,400 in manufacturing overhead cost at an activity level of 561,000 machine-hours. The company spent the entire month of January working on a large order for 12,500 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,290,000 in manufacturing overhead cost at an activity level of 572,000 machine-hours. The company spent the entire month of January working on a large order for 12,800 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,158,800 in manufacturing overhead cost at an activity level of 562,000 machine-hours. The company spent the entire month of January working on a large order for 12,500 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,215,000 in manufacturing overhead cost at an activity level of 562,000 machine-hours. The company spent the entire month of January working on a large order for 12,900 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,232,800 in manufacturing overhead cost at an activity level of 572,000 machine-hours. The company spent the entire month of January working on a large order for 12,300 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,320,000 in manufacturing overhead cost at an activity level of 576,000 machine-hours. The company spent the entire month of January working on a large order for 12,900 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,354,800 in manufacturing overhead cost at an activity level of 573,000 machine-hours. The company spent the entire month of January working on a large order for 13,000 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,215,000 in manufacturing overhead cost at an activity level of 562,000 machine-hours. The company spent the entire month of January working on a large order for 12,900 custom-made machined parts. The company had no work...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system...
Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead costs to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,327,500 in manufacturing overhead cost at an activity level of 577,000 machine-hours.       The company spent the entire month of January working on a large order for 9,000 custom made machined parts. The company had no...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT