Question

In: Computer Science

WEEK 9 ASSIGNMENT Answer the following questions: With IT projects – what are some of the...

WEEK 9 ASSIGNMENT

Answer the following questions:

  1. With IT projects – what are some of the common risks associated with managing an IT project?
  2. What are the potential consequences of not assessing the technical risks associated with an information systems development project? In what ways could you identify an information systems project that was technically riskier than another?

Solutions

Expert Solution

1)The common risks associated with managing an IT project?
⦁   They are mostly complex projects with many mutually connected activities and participants,
⦁   Risk immanency and uncertainty,
⦁   They should be realized in the given time and within the framework of anticipated
⦁   costs,
⦁   They are determined by goals and tasks that should be attained, defined by the manager, i.e. the user.
⦁   Necessity of competent experts, as well as sufficient material and financial resources, and so on
Thus, the projects of information systems development are very complex; therefore they are liable to the influence of many risks.

Phase of of the project life cycle Possible risk factors

1)All phases Insufficient time period for one or more phases
All information not included
Transition to the next phase without finishing one or more

2)previous ohases
Plan Unwritten information and plans
Badly done cost-benefit analysis

3)Defining Plan carrying out by the team members who
have not yet worked in the same or simillar
projects
Plan not in written form
Plan not completely carried out


4)Start The project team members have not taken
part in the plan carrying out
Plan is not assessed and verified by the
team members participating in its carrying out
Absence of procedures for conflic t solving
and maintaing high-quality information


5)Carrying out Changes of clients’ needs
Incomplete or wrong information relating to
the schedule of carrying out and necessary resources
Absence of reporting on project advancement
Leaving of the team members
Change of market conditions
Changes managment without consistent
analysis of consequences which can
influence the whole project
6)End Project results not formally acknowledged
by the project manager
New project is assigned to the team
members before finishing the current one


Failure to attain expected benefits from the project
•Inaccurate project cost estimates
•Inaccurate project duration estimates
•Failure to achieve adequate system performance levels
•Failure to adequately integrate the new system with existing hardware, software, or organizational procedures.

In what ways could you identify that one IS project is riskier than another?

There are many ways to identify that one IS project is riskier than another. The factors used to assess a project’s risk are as follows.
⦁   Project size
⦁   Number of members on the project team
⦁   Project duration time
⦁   Number of organizational departments involved in project
⦁   Size of programming effort (Example: hours, function points)
⦁   Number of outsourcing partners.
⦁   Project structure –oNew system or renovation of existing system(s)
⦁   Organizational, procedural, structural, or personnel changes resulting form system
⦁   User perceptions and willingness to participate in effort
⦁   Management commitment to system

  • Amount of user information systems development effort.

⦁   Development group
⦁   Familiarity with target hardware, software development environment,
⦁   tools, and operating systems
⦁   Familiarity with proposed application area
⦁   Familiarity with building similar systems of similar size.
⦁   User Group
⦁   Familiarity with information systems development process
⦁   Familiarity with proposed application area
⦁   Familiarity with using similar project


Related Solutions

ASSIGNMENT: Answer the following questions: What are the reasons that IT projects fail after listening to...
ASSIGNMENT: Answer the following questions: What are the reasons that IT projects fail after listening to the podcast? Describe the reasons and impact. What experiences have you had? List and describe “soft skills” needed in managing projects. Why is each important?
WEEK 1 HOMEWORK (based on your week 1 assignment) Please answer the following questions in complete...
WEEK 1 HOMEWORK (based on your week 1 assignment) Please answer the following questions in complete sentences. Identify and define at least 5 fallacies about racism. What areas of life does racism affect? Define the two types of racism (institutional and interpersonal). What is symbolic violence when it comes to race? At one time Jews dominated basketball; now it is a game almost exclusively for African Americans. The text authors identify at least two reasons why both of these groups...
WEEK 9 DISCUSSION Answer any three of the questions below: What does the level of "uncertainty"...
WEEK 9 DISCUSSION Answer any three of the questions below: What does the level of "uncertainty" have to do with risk? If a risk, no longer has a level of uncertainty, is it still a risk - why or why not? Although risk can have both negative and positive consequences, why do you think many project teams tend to focus on negative risks? What is "risk management," and why is it important in the project environment? Does it make sense...
9. Answer the following questions for #9 with 50 - 100 words. What is the key...
9. Answer the following questions for #9 with 50 - 100 words. What is the key tax characteristic for investors associated with state and local (municipal) securities? How would you define efficient security markets?
WEEK 9 ASSIGNMENT#7 DISCUSS THE FOLLOWING IN YOUR OWN WORDS. 1: What are the Risk Assessment...
WEEK 9 ASSIGNMENT#7 DISCUSS THE FOLLOWING IN YOUR OWN WORDS. 1: What are the Risk Assessment and Evaluation of Samsung Galaxy Note 7? 2: What are the mitigation of Samsung Galaxy Note 7?
________________________Directions: Answer the questions and submit to Week #6 assignment 1.) Pre-Operative Phase – List 3...
________________________Directions: Answer the questions and submit to Week #6 assignment 1.) Pre-Operative Phase – List 3 criteria a pre-operative surgical RN would assess in a patient who is having upcoming surgery. Explain what the Pre-Anesthesia Care Unit (PACU) is .2.) Intra-Operative Phase – Discuss role of “Circulating RN” during a surgical procedure. Discuss role of Scrub Tech/Scrub RN during a surgical procedure. 3.) Post-Operative Phase – Explain what occurs during PACU Phase I and Recovery Phase II after a surgery...
Research and answer the following questions: What are some of the communication channels in use today?...
Research and answer the following questions: What are some of the communication channels in use today? Name some of the advantages and disadvantages of communication channels. How has technology influenced the way we communicate? In your own organization, what channels are in place? How effectively are they used?   Your Discussion posts should be a minimum of 250 words in length and not more than 750 words. Use APA citations and references for the textbook and any other sources used.
WEEK 9 DISCUSSION Answer any two of the questions below: Discuss any approaches, tools, or techniques...
WEEK 9 DISCUSSION Answer any two of the questions below: Discuss any approaches, tools, or techniques that may be helpful in assessing and identifying risks in IS projects. How can communication help in identifying AND managing risk? Give an example from your personal or professional experience. When looking at risks in the project environment, why are we concerned with the impact and probability of a potential risk event? When is the best time to assess potential risks in an IS...
For your homework assignment for week 1 prepare an essay that answers the following questions: 1....
For your homework assignment for week 1 prepare an essay that answers the following questions: 1. A decade ago the idea that medical procedures might move offshore was unthinkable. Today it is a reality. What trends have facilitated this process? Is the globalization of health care good or bad for the American economy? 2. Is the globalization of health care good or bad for patients? Who might benefit from the globalization of health care? Who might lose? 3. How might...
To kill a mockingbird chapter 9 : answer the following questions in complete sentences: 1.What advice...
To kill a mockingbird chapter 9 : answer the following questions in complete sentences: 1.What advice does Atticus have for Scout? 2. Scout and Jem have “mixed feelings” about Christmas. What are these feelings and why? 3. Why is Aunt Alexandra critical of the way Atticus is raising Scout? In light of this criticism, what is ironic about the fact that Francis is learning to cook? 4. How does Scout respond to Aunt Alexandra’s vision of what it means to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT