In: Finance
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$356,000 –$40,000 1 31,000 23,000 2 42,000 15,200 3 50,000 14,100 4 445,000 11,200 The required return on these investments is 13 percent. Required: (a) What is the payback period for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) Payback period Project A years Project B years (b) What is the NPV for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g.,32.16).) Net present value Project A $ Project B $ (c) What is the IRR for each project? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).) Internal rate of return Project A % Project B % (d) What is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 3 decimal places (e.g., 32.161).) Profitability index Project A Project B (e) Based on your answers in (a) through (d), which project will you finally choose?
a
| Project A | ||
| Year | Cash flow stream | Cumulative cash flow |
| 0 | -356000 | -356000 |
| 1 | 31000 | -325000 |
| 2 | 42000 | -283000 |
| 3 | 50000 | -233000 |
| 4 | 445000 | 212000 |
| Payback period is the time by which undiscounted cashflow cover the intial investment outlay | |||||
| this is happening between year 3 and 4 | |||||
| therefore by interpolation payback period = 3 + (0-(-233000))/(212000-(-233000)) | |||||
| 3.52 Years |
| Project B | ||
| Year | Cash flow stream | Cumulative cash flow |
| 0 | -40000 | -40000 |
| 1 | 23000 | -17000 |
| 2 | 15200 | -1800 |
| 3 | 14100 | 12300 |
| 4 | 11200 | 23500 |
| Payback period is the time by which undiscounted cashflow cover the intial investment outlay | |||||
| this is happening between year 2 and 3 | |||||
| therefore by interpolation payback period = 2 + (0-(-1800))/(12300-(-1800)) | |||||
| 2.13 Years |
b
| Project A | |||||
| Discount rate | 13.000% | ||||
| Year | 0 | 1 | 2 | 3 | 4 |
| Cash flow stream | -356000 | 31000 | 42000 | 50000 | 445000 |
| Discounting factor | 1.000 | 1.130 | 1.277 | 1.443 | 1.630 |
| Discounted cash flows project | -356000.000 | 27433.628 | 32892.161 | 34652.508 | 272926.834 |
| NPV = Sum of discounted cash flows | |||||
| NPV Project A = | 11905.13 | ||||
| Where | |||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
| Discounted Cashflow= | Cash flow stream/discounting factor | ||||
| Project B | |||||
| Discount rate | 13.000% | ||||
| Year | 0 | 1 | 2 | 3 | 4 |
| Cash flow stream | -40000 | 23000 | 15200 | 14100 | 11200 |
| Discounting factor | 1.000 | 1.130 | 1.277 | 1.443 | 1.630 |
| Discounted cash flows project | -40000.000 | 20353.982 | 11903.830 | 9772.007 | 6869.170 |
| NPV = Sum of discounted cash flows | |||||
| NPV Project B = | 8898.99 | ||||
| Where | |||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
| Discounted Cashflow= | Cash flow stream/discounting factor | ||||
c
| Project A | |||||
| IRR is the rate at which NPV =0 | |||||
| IRR | 14.07% | ||||
| Year | 0 | 1 | 2 | 3 | 4 |
| Cash flow stream | -356000.000 | 31000.000 | 42000.000 | 50000.000 | 445000.000 |
| Discounting factor | 1.000 | 1.141 | 1.301 | 1.484 | 1.693 |
| Discounted cash flows project | -356000.000 | 27176.943 | 32279.523 | 33688.892 | 262854.641 |
| NPV = Sum of discounted cash flows | |||||
| NPV Project A = | 0.000 | ||||
| Where | |||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
| Discounted Cashflow= | Cash flow stream/discounting factor | ||||
| Project B | |||||
| IRR is the rate at which NPV =0 | |||||
| IRR | 24.90% | ||||
| Year | 0 | 1 | 2 | 3 | 4 |
| Cash flow stream | -40000.000 | 23000.000 | 15200.000 | 14100.000 | 11200.000 |
| Discounting factor | 1.000 | 1.249 | 1.560 | 1.948 | 2.433 |
| Discounted cash flows project | -40000.000 | 18415.417 | 9744.308 | 7237.361 | 4602.914 |
| NPV = Sum of discounted cash flows | |||||
| NPV Project B = | 0.001 | ||||
| Where | |||||
| Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
| Discounted Cashflow= | Cash flow stream/discounting factor | ||||
d
Project A
| PI= (NPV+initial inv.)/initial inv. |
| =(11905.13+356000)/356000 |
| 1.03 |
Project B
| PI= (NPV+initial inv.)/initial inv. |
| =(8898.99+40000)/40000 |
| 1.22 |
e
Accept project B as it has higher IRR and profitability index