Exercise 17-8 Using the plantwide overhead rate to assess prices LO P1

Way Cool produces two different models of air conditioners. The company produces the mechanical systems in its components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and round "Cost per unit and OH rate" answers to 2 decimal places.)

Process Activity Overhead Cost Driver Quantity
Components Changeover $ 451,000 Number of batches 730
Machining 301,600 Machine hours 7,580
Setups 227,000 Number of setups 60
$ 979,600
Finishing Welding $ 182,700 Welding hours 4,000
Inspecting 223,000 Number of inspections 805
Rework 60,700 Rework orders 240
$ 466,400
Support Purchasing $ 137,500 Purchase orders 473
Providing space 30,200 Number of units 6,600
Providing utilities 60,300 Number of units 6,600
$ 228,000

   
Additional production information concerning its two product lines follows.

Model 145 Model 212
Units produced 2,200 4,400
Welding hours 1,800 2,200
Batches 365 365
Number of inspections 470 335
Machine hours 2,330 5,250
Setups 30 30
Rework orders 140 100
Purchase orders 315 158

  
Required:

1. Using a plantwide overhead rate based on machine hours, compute the overhead cost per unit for each product line.
0
2. Determine the total cost per unit for each product line if the direct labor and direct materials costs per unit are $290 for Model 145 and $130 for Model 212.
Overhead Assigned Activity Driver Plantwide OH rate Total Overhead Cost Units Produced OH Cost per unit
Model 145 $0
Model 212 $0
Model 145 Model 212
0
3. If the market price for Model 145 is $748 and the market price for Model 212 is $480, determine the profit or loss per unit for each model.
Model 145 Model 212
Market price

Solutions

Expert Solution

Solution:

1.)

Total overhead costs (Components overhead costs + Finishing overhead costs + Support overhead costs) $1,674,000($979,600 + $466,400 + $228,000)
Total machine hours 7,580 hours

Predetermined overhead rate = Overhead costs / Machine Hours

= $1674000 / 7580 hours

= $220.84 per machine hour

2.)

Overhead Assigned Activity Driver Plantwide OH Rate Total Overhead Cost Units Produced OH Cost Per Unit
Model 145 2,330hours $220.84 per hour $514,557 2,200 $233.89
Model 212 5,250hours $220.84 per hour $1,159,410 4,400 $263.50
Total manufacturing cost per unit: Model 145 Model 212
Material and Labor $290.00 $130.00
Overhead $233.89 $263.50
Total manufacturing cost $523.89 $393.50

3.)

Model 145 Model 212
Market price $748.00 $480.00
Manufacturing cost per unit -$523.89 -$393.50
Profit (loss) per unit $224.11 $86.50

If you have any query regarding this question please ask me. If you satisfy please like.


Related Solutions

Exercise 4-7 Using the plantwide overhead rate to assess prices LO P1 Way Cool produces two...
Exercise 4-7 Using the plantwide overhead rate to assess prices LO P1 Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. (Loss amounts should be indicated with a minus sign. Round your intermediate calculations and round "Cost per unit and...
Exercise 17-8 Using departmental overhead rates to assess prices LO P2 Way Cool produces two different...
Exercise 17-8 Using departmental overhead rates to assess prices LO P2 Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 452,000 Number of batches 790 Machining 313,000 Machine hours 7,920 Setups...
A) Exercise 4-8 Using departmental overhead rates to assess prices LO P2 Way Cool produces two...
A) Exercise 4-8 Using departmental overhead rates to assess prices LO P2 Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 458,000 Number of batches 870 Machining 313,000 Machine hours 8,320...
Exercise 4-8 Using departmental overhead rates to assess prices LO P2 Way Cool produces two different...
Exercise 4-8 Using departmental overhead rates to assess prices LO P2 Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 458,000 Number of batches 870 Machining 313,000 Machine hours 8,320 Setups...
Exercise 4-9 Using ABC to assess prices LO P3 Way Cool produces two different models of...
Exercise 4-9 Using ABC to assess prices LO P3 Way Cool produces two different models of air conditioners. The company produces the mechanical systems in their components department. The mechanical systems are combined with the housing assembly in its finishing department. The activities, costs, and drivers associated with these two manufacturing processes and the production support process follow. Process Activity Overhead Cost Driver Quantity Components Changeover $ 485,050 Number of batches 890 Machining 366,275 Machine hours 8,050 Setups 334,800 Number...
Exercise 4-6 Assigning overhead costs using the plantwide rate and departmental rate methods LO P1, P2...
Exercise 4-6 Assigning overhead costs using the plantwide rate and departmental rate methods LO P1, P2 Laval produces lamps and home lighting fixtures. Its most popular product is a brushed aluminum desk lamp. This lamp is made from components shaped in the fabricating department and assembled in the assembly department. Information related to the 33,000 desk lamps produced annually follows. Direct materials $ 270,000 Direct labor Fabricating department (6,000 DLH × $28 per DLH) $ 168,000 Assembly department (16,000 DLH...
Problem 17-1A Comparing costs using ABC with the plantwide overhead rate LO P1, P3, A1, A2...
Problem 17-1A Comparing costs using ABC with the plantwide overhead rate LO P1, P3, A1, A2 The following data are for the two products produced by Tadros Company. Product A Product B Direct materials $ 13 per unit $ 25 per unit Direct labor hours 0.6 DLH per unit 1.5 DLH per unit Machine hours 0.5 MH per unit 1.1 MH per unit Batches 120 batches 240 batches Volume 10,000 units 2,000 units Engineering modifications 9 modifications 45 modifications Number...
Problem 17-1A Comparing costs using ABC with the plantwide overhead rate LO P1, P3, A1, A2...
Problem 17-1A Comparing costs using ABC with the plantwide overhead rate LO P1, P3, A1, A2 The following data are for the two products produced by Tadros Company. Product A Product B Direct materials $ 14 per unit $ 27 per unit Direct labor hours 0.5 DLH per unit 1.5 DLH per unit Machine hours 0.4 MH per unit 1.1 MH per unit Batches 105 batches 210 batches Volume 10,000 units 2,000 units Engineering modifications 9 modifications 45 modifications Number...
Problem 17-1A Comparing costs using ABC with the plantwide overhead rate LO P1, P3, A1, A2...
Problem 17-1A Comparing costs using ABC with the plantwide overhead rate LO P1, P3, A1, A2 The following data are for the two products produced by Tadros Company. Product A Product B Direct materials $ 14 per unit $ 25 per unit Direct labor hours 0.6 DLH per unit 1.5 DLH per unit Machine hours 0.5 MH per unit 1.1 MH per unit Batches 110 batches 220 batches Volume 10,000 units 2,000 units Engineering modifications 8 modifications 40 modifications Number...
Problem 17-5A Pricing analysis with ABC and a plantwide overhead rate LO A1, A2, P1, P3...
Problem 17-5A Pricing analysis with ABC and a plantwide overhead rate LO A1, A2, P1, P3 [The following information applies to the questions displayed below.] Sara’s Salsa Company produces its condiments in two types: Extra Fine for restaurant customers and Family Style for home use. Salsa is prepared in department 1 and packaged in department 2. The activities, overhead costs, and drivers associated with these two manufacturing processes and the company’s production support activities follow. Process Activity Overhead cost Driver...
ADVERTISEMENT