Question

In: Accounting

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,156,000 $ 3,388,000 $ 2,371,600 Estimated costs to complete as of year-end 5,544,000 2,156,000 0 Billings during the year 2,130,000 3,414,000 4,456,000 Cash collections during the year 1,865,000 3,300,000 4,835,000 Westgate recognizes revenue over time according to percentage of completion.

1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).

Solutions

Expert Solution

  • Requirements 2

Requirement 2A

Date

Accounts title

Debit

Credit

2021

Construction in Progress

$2,156,000

   Various accounts

$2,156,000

(construction cost incurred)

2021

Accounts receivables

$2,130,000

Billing on Construction contracts

$2,130,000

(amount billed during the year)

2021

Cash

$1,865,000

Accounts receivables

$1,865,000

(cash received)

2021

Construction in Progress

$644,000

Cost of construction

$2,156,000

Revenue from Long Term contract

$2,800,000

(revenue recognised)

Requirement 2B

Date

Accounts title

Debit

Credit

2022

Construction in Progress

$3,388,000

   Various accounts

$3,388,000

(construction cost incurred)

2022

Accounts receivables

$3,414,000

Billing on Construction contracts

$3,414,000

(amount billed during the year)

2022

Cash

$3,300,000

Accounts receivables

$3,300,000

(cash received)

2022

Construction in Progress

$1,012,000

Cost of construction

$3,388,000

Revenue from Long Term contract

$4,400,000

(revenue recognised)

Requirement 2C

Date

Accounts title

Debit

Credit

2023

Construction in Progress

$2,371,600

   Various accounts

$2,371,600

(construction cost incurred)

2023

Accounts receivables

$4,456,000

Billing on Construction contracts

$4,456,000

(amount billed during the year)

2023

Cash

$4,835,000

Accounts receivables

$4,835,000

(cash received)

2023

Construction in Progress

$428,400

Cost of construction

$2,371,600

Revenue from Long Term contract

$2,800,000

(revenue recognised)

2023

Billing on Construction contracts

$10,000,000

   Construction in Progress

$10,000,000

(to record completion of contract)

  • Working

Working

2021

2022

2023

A

Contract Price

$10,000,000

$10,000,000

$10,000,000

B

Cost Incurred to Date

$2,156,000

$5,544,000

$7,915,600

C

Estimated cost yet to be incurred to complete the contract

$5,544,000

$2,156,000

$0

D = B+C

Total Cost

$7,700,000

$7,700,000

$7,915,600

E = (B/D) x 100

% of Completion

28.00%

72.00%

100.00%

F = A x E

Revenue to date

$2,800,000

$7,200,000

$10,000,000

G

Revenue of Previous year

$0

$2,800,000

$7,200,000

H = F - G

Net Revenue this year

$2,800,000

$4,400,000

$2,800,000

I (=B)

Cost to date

$2,156,000

$5,544,000

$7,915,600

J

Cost to date of previous year

$0

$2,156,000

$5,544,000

K = I - J

Net Cost for the year

$2,156,000

$3,388,000

$2,371,600

L = H - K

Gross Profits

$644,000

$1,012,000

$428,400


Related Solutions

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 5. Calculate the amount of revenue and...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 3. Complete the information required below to...
in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
in 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT