Question

In: Accounting

The smelting department of Company X has the following production and cost data for September: •...

The smelting department of Company X has the following production and cost data for September:

• Production: Beginning work in process 200 units that are 100% complete as to materials and 82% complete as to conversion costs; units started into production 1,000 units; units transferred out to next department 950 units; ending work in process are 100% complete as to materials and 42% complete as to conversion costs.

• Manufacturing costs: Beginning work in process TL8,200 materials, TL9,270 labor, and TL2,200 manufacturing overhead costs. In the current period, TL50,500 worth of materials, TL25,700 worth of labor and TL32,000 worth of manufacturing overhead costs are incurred.

Question: Compute the conversion cost portion of the ending inventory if the company uses FIFO method to compute equivalent units. method to compute equivalent units.

Solutions

Expert Solution

Under FIFO method units started first are transferred out first.So of the units completed and transferred out ,200 units is from beginning work in process inventory and remaining is those 950 -200 = 750 units started in current period .

Ending work in process inventory =Beginning +started -transferred out

                     = 200+1000 -950

                    = 250 units

Conversion cost
Units completed and transferred out
Beginning work in process 200(1-.82 already completed)=36
current period production 750*100%=750
Ending work in process inventory 250*42%= 105
Equivalent units of production 891
Conversion cost per equivalent unit
Labor cost 25700
Manufacturing overhead 32000
Total conversion cost for current period 57700`
Equivalent units of production 891
cost per equivalent unit 57700/891 =$ 64.75870

Conversion cost portion of ending inventory = Conversion cost per equivalent unit * Equivalent unit for Ending work in process inventory -conversion

                    = 64.7587 * 105

                   = $ 6800


Related Solutions

The smelting department of Company X has the following production and cost data for September: •...
The smelting department of Company X has the following production and cost data for September: • Production: Beginning work in process 200 units that are 100% complete as to materials and 82% complete as to conversion costs; units started into production 1,000 units; units transferred out to next department 950 units; ending work in process are 100% complete as to materials and 42% complete as to conversion costs. • Manufacturing costs: Beginning work in process TL8,200 materials, TL9,270 labor, and...
The smelting department of Company X has following production and cost data for September: Production: No...
The smelting department of Company X has following production and cost data for September: Production: No beginning work in process; units started into production 1,000 units; units transferred out to next department 900 units; ending work in process 100 units that are 100% complete as to materials and 4z% complete as to conversion costs. Manufacturing costs: In current period, TL50,x00 worth of materials, TL25,y00 worth of labor and TL3t,000 worth of manufacturing overhead costs are incurred. (a) (15 points) Assuming...
Q-2) The smelting department of Company X has following production and cost data for September: Production:...
Q-2) The smelting department of Company X has following production and cost data for September: Production: Beginning work in process 200 units that are 100% complete as to materials and 85% complete as to conversion costs; units started into production 1,000 units; units transferred out to next department 900 units; ending work in process 300 units that are 100% complete as to materials and 46% complete as to conversion costs. Manufacturing costs: Beginning work in process TL8,600 materials, TL9,230 labor...
The Smelting Department of Kiner Company has the following production data for November. Production: Beginning work...
The Smelting Department of Kiner Company has the following production data for November. Production: Beginning work in process 3,800 units that are 100% complete as to materials and 25% complete as to conversion costs; units transferred out 9,700 units; and ending work in process 8,300 units that are 100% complete as to materials and 46% complete as to conversion costs. Compute the equivalent units of production for (a) materials and (b) conversion costs for the month of November.
The Polishing Department of Sunland Company has the following production and manufacturing cost data for September....
The Polishing Department of Sunland Company has the following production and manufacturing cost data for September. Materials are entered at the beginning of the process. Production: Beginning inventory 1,800 units that are 100% complete as to materials and 30% complete as to conversion costs; units started during the period are 43,600; ending inventory of 5,600 units 10% complete as to conversion costs. Manufacturing costs: Beginning inventory costs, comprised of $21,500 of materials and $33,186 of conversion costs; materials costs added...
The Polishing Department of Major Company has the following production and manufacturing cost data for September....
The Polishing Department of Major Company has the following production and manufacturing cost data for September. Materials are entered at the beginning of the process. Production: Beginning inventory 1,620 units that are 100% complete as to materials and 30% complete as to conversion costs; units started during the period are 44,700; ending inventory of 6,800 units 10% complete as to conversion costs. Manufacturing costs: Beginning inventory costs, comprised of $21,300 of materials and $19,580 of conversion costs; materials costs added...
The Polishing Department of Coronado Company has the following production and manufacturing cost data for September....
The Polishing Department of Coronado Company has the following production and manufacturing cost data for September. Materials are entered at the beginning of the process. Production: Beginning inventory 1,520 units that are 100% complete as to materials and 30% complete as to conversion costs; units started during the period are 46,300; ending inventory of 6,800 units 10% complete as to conversion costs. Manufacturing costs: Beginning inventory costs, comprised of $20,500 of materials and $34,645 of conversion costs; materials costs added...
The Polishing Department of Waterway Company has the following production and manufacturing cost data for September....
The Polishing Department of Waterway Company has the following production and manufacturing cost data for September. Materials are entered at the beginning of the process. Production: Beginning inventory 1,880 units that are 100% complete as to materials and 30% complete as to conversion costs; units started during the period are 41,300; ending inventory of 5,400 units 10% complete as to conversion costs. Manufacturing costs: Beginning inventory costs, comprised of $20,800 of materials and $9,756 of conversion costs; materials costs added...
The Polishing Department of Major Company has the following production and manufacturing cost data for September....
The Polishing Department of Major Company has the following production and manufacturing cost data for September. Materials are entered at the beginning of the process. Production: Beginning inventory 1,520 units that are 100% complete as to materials and 30% complete as to conversion costs; units started during the period are 41,300; ending inventory of 7,400 units 10% complete as to conversion costs. Manufacturing costs: Beginning inventory costs, comprised of $21,600 of materials and $12,320 of conversion costs; materials costs added...
Use below information for Questions 10 to 13: The smelting department of Company X has following...
Use below information for Questions 10 to 13: The smelting department of Company X has following production and cost data for September: Production: Beginning work in process 200 units that are 100% complete as to materials and 71% complete as to conversion costs; units started into production 1,000 units; ending work in process 250 in units that are 100% complete as to materials and 57% complete to conversion costs. Manufacturing costs: Beginning work in process TL8,100 materials, TL9,270 labor and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT