Question

In: Accounting

Problem 3-18B Cost flows and Unit Product Costs in Activity-Based Costing [LO2, LO3, LO4] [The following...

Problem 3-18B Cost flows and Unit Product Costs in Activity-Based Costing [LO2, LO3, LO4]

[The following information applies to the questions displayed below.]

Fisher Company uses activity-based costing to determine product costs for external financial reports. At the beginning of the year, management made the following estimates of cost and activity in the company’s five activity cost pools:

  Activity Cost Pool

Activity
Measure

Expected
Overhead Cost

Expected
Activity

  Labor-related

  Direct labor-hours

$

382,800

23,200

DLHs

  Purchase orders

  Number of orders

$

131,560

5,720

orders

  Material receipts

  Number of receipts

$

137,280

2,080

receipts

  Relay assembly

  Number of relays

$

1,195,200

14,400

relays

  General factory

  Machine-hours

$

1,207,800

73,200

MHs

References

Section BreakProblem 3-18B Cost flows and Unit Product Costs in Activity-Based Costing [LO2, LO3, LO4]

38.

value:
5.00 points

Required information

Problem 3-18B Part 1

Required:
1.

Compute the activity rate for each of the activity cost pools. (Round your answers to 2 decimal places.)

References

eBook & Resources

WorksheetDifficulty: 3 HardLearning Objective: 03-03 Compute product costs using activity-based costing.

Problem 3-18B Part 1Learning Objective: 03-02 Compute activity rates for an activity-based costing system.Learning Objective: 03-04 Contrast the product costs computed under activity-based costing and conventional costing methods.


39.

value:
5.00 points

Required information

Problem 3-18B Part 2

2.

The expected activity for the year was distributed among the company’s four products as follows:

   

Expected Activity
  Activity Cost Pool Product A Product B Product C Product D
  Labor related (DLHs) 7,800     1,800 8,800 4,800
  Production orders (orders) 1,000     1,060 1,300 2,360
  Materials receipts (receipts) 480     840 340 420
  Relay assembly (relays) 4,300     2,400 3,400 4,300
  General factory (MHs) 16,800     26,800 17,800 11,800

   

Using the ABC data, determine the total amount of overhead cost applied to each product.

Solutions

Expert Solution

Activity Cost pool Expected O/H cost Expected Activity(No`s) Activity Rate
Labor related 382800 23200 16.5 per direct labor hour (282500/23200)
Purchase orders 131560 5720 23 per order (131560/5720)
Material Receipts 137280 2080 66 per receipt (137280/2080)
Relay Assembly 1195200 14400 83 per relays (1195200/14400)
General factory 1207800 73200 16.5 per machine hour (1207800/73200)
Product A Product B Product C Product D
Activity cost pool Per activity rate Activity(Nos) Total Cost(per activity rate* Nos) Activity(Nos) Total Cost(per activity rate* Nos) Activity(Nos) Total Cost(per activity rate* Nos) Activity(Nos) Total Cost(per activity rate* Nos)
Labor related 16.5 7800 128700 1800 29700 8800 145200 4800 79200
Purchase orders 23 1000 23000 1060 24380 1300 29900 2360 54280
Material Receipts 66 480 31680 840 55440 340 22440 420 27720
Relay Assembly 83 4300 356900 2400 199200 3400 282200 4300 356900
General factory 16.5 16800 277200 26800 442200 17800 293700 11800 194700
Total Cost $817,480.00 $750,920.00 $773,440.00 $712,800.00

Related Solutions

Problem 6-18B Variable and Absorption Costing Unit Product Costs and Income Statements; Explanation of Difference in...
Problem 6-18B Variable and Absorption Costing Unit Product Costs and Income Statements; Explanation of Difference in Net Operating Income [LO6-1, LO6-2, LO6-3] McCracken Aerial, Inc., produces and sells a unique type of TV antenna. The company has just opened a new plant to manufacture the antenna, and the following cost and revenue data have been provided for the first month of the plant’s operation:   Beginning inventory 0      Units produced 51,750      Units sold 45,000      Selling price per unit...
PROBLEM 2–24 Schedule of Cost of Goods Manufactured; Income Statement; Cost Behaviour [LO1, LO2, LO3, LO4,...
PROBLEM 2–24 Schedule of Cost of Goods Manufactured; Income Statement; Cost Behaviour [LO1, LO2, LO3, LO4, LO5] Carlton Manufacturing Company provided the following details about operations in February Purchases of raw materials. . . . . . . ........................................... 130 000 Maintenance, factory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ....
Problem 4-16 Contrasting ABC and Conventional Product Costs [LO4-2, LO4-3, LO4-4] [The following information applies to...
Problem 4-16 Contrasting ABC and Conventional Product Costs [LO4-2, LO4-3, LO4-4] [The following information applies to the questions displayed below.] For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.60 hours of direct labor time per unit to manufacture...
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing....
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $462,400. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information...
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing....
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $462,400. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information...
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing....
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $462,400. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information...
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing....
Activity-Based Costing and Product Cost Distortion Handbrain Inc. is considering a change to activity-based product costing. The company produces two products, cell phones and tablet PCs, in a single production department. The production department is estimated to require 4,000 direct labor hours. The total indirect labor is budgeted to be $462,400. Time records from indirect labor employees revealed that they spent 40% of their time setting up production runs and 60% of their time supporting actual production. The following information...
Problem 3-14B Compute and Use Activity Rates to Determine the Costs of Serving Customers [LO3-2, LO3-3,...
Problem 3-14B Compute and Use Activity Rates to Determine the Costs of Serving Customers [LO3-2, LO3-3, LO3-4] The Tavern is a popular restaurant located in State College. The owner of the restaurant has been trying to better understand costs at the restaurant and has hired a student intern to conduct an activity-based costing study. The intern, in consultation with the owner, identified the following major activities:   Activity Cost Pool Activity Measure   Serving a party of diners      Number of parties served...
Problem 3-14A Compute and Use Activity Rates to Determine the Costs of Serving Customers [LO3-2, LO3-3,...
Problem 3-14A Compute and Use Activity Rates to Determine the Costs of Serving Customers [LO3-2, LO3-3, LO3-4] Gino’s Restaurant is a popular restaurant in Boston, Massachusetts. The owner of the restaurant has been trying to better understand costs at the restaurant and has hired a student intern to conduct an activity-based costing study. The intern, in consultation with the owner, identified the following major activities:   Activity Cost Pool Activity Measure   Serving a party of diners      Number of parties served   Serving...
Problem 10-19 Comprehensive Variance Analysis in a Hospital [LO2, LO3, LO4, LO5, LO6] Marc Goudreau, administrator...
Problem 10-19 Comprehensive Variance Analysis in a Hospital [LO2, LO3, LO4, LO5, LO6] Marc Goudreau, administrator of Clearwater Hospital, was puzzled by the prior month ’s reports. “Every month, it’s anyone’s guess whether the lab will show a profit or a loss. Perhaps the only answer is to increase our lab fees again.” “We can’t,” replied Rhoda Groves, the controller. “There are still a lot of complaints about the last increase, particularly from the insurance companies and government health units....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT