Question

In: Finance

A two-year project has been evaluated and has an NPV on an after tax basis of...

A two-year project has been evaluated and has an NPV on an after tax basis of -$2000. On reviewing the analysis the Finance Manager found that depreciation had been omitted from the tax analysis. The allowable depreciation for tax purposes is $5000 for each year. Using a tax rate of 30% and and a discount rate after tax of 12% pa, determine the correct NPV for the project (to the nearest dollar).

Can someone help me to solve this and explain the method to me?

Thanks!

Solutions

Expert Solution

We are already given the NPV of the project without adjustments. What we will do now is calculate the Present Value of the depreciation expense for both years and add the value to the given NPV to arrive at the correct NPV.

Now, the depreciation expense is 5000, which is tax deductible. So after factoring in the tax shield provided by the depreciation expense, the depreciation is 5000 x (1-Tax Rate) = 5000(1-0.3) = 3500

This will be the depreciation expense for both the years. Since it an expense, it will have a negative impact on the NPV of the project. We will take the Present Value of this expense for each year using the following formula:

, where

FV = Expense in the future

r = Discount Rate

t = Time

Plugging in the values we get:

For Year 1, PV = 3500/(1+0.12)1

= 3125

For Year2, PV = 3500/(1+0.12)2

= 2800

So the Total Present Value of depreciation is 3125+2800 = $5925

Therefore the correct NPV = -2000-5925 = -$7925


Related Solutions

caclulate the NPV for the project that has an initial investment of $20,000 with expected after-tax...
caclulate the NPV for the project that has an initial investment of $20,000 with expected after-tax operating cash flows of $125,000 per year for each of the next 3 years. However, in preparation for its termination at the end of year 3, an additional investment of $350,000 must be made at the end of Year 2. What is the NPV? the cost of capital is 12%. Please show all calculations in excel!
What is the NPV of a project that costs $200,000, provides $43,000 in after-tax cash flows...
What is the NPV of a project that costs $200,000, provides $43,000 in after-tax cash flows (excluding the CCA tax shield) annually for six years , requires a $5,000 increase in net working capital, and depreciates the asset at 15 percent declining balance over six years and sold at zero salvage value? The discount rate is 14 percent. The tax rate is 40 percent.(Assume the half-year rule applies and working capital is recovered at the end of the project) Select...
What is the NPV of a project that costs $200,000, provides $43,000 in after-tax cash flows...
What is the NPV of a project that costs $200,000, provides $43,000 in after-tax cash flows (excluding the CCA tax shield) annually for six years , requires a $5,000 increase in net working capital, and depreciates the asset at 15 percent declining balance over six years and sold at zero salvage value? The discount rate is 14 percent. The tax rate is 40 percent.(Assume the half-year rule applies and working capital is recovered at the end of the project)
What is the NPV of this project? (in 000s) Bogle is considering a two-year project to...
What is the NPV of this project? (in 000s) Bogle is considering a two-year project to manufacture microchips. Bogle purchases equipment for $750K. This two-year project will require additional inventory of $125K and accounts payable of $150K, which reverse at the end of the project. Bogle’s tax rate is 50%, and its cost of capital is 12%. Bogle estimates incremental revenue of $600K in years 1 and 2, and operating expenses equal to 15% of revenues. The machine is depreciated...
Tamarisk Inc. now has the following two projects available: Project Initial CF After-tax CF1 After-tax CF2...
Tamarisk Inc. now has the following two projects available: Project Initial CF After-tax CF1 After-tax CF2 After-tax CF3 1 -11,119 5,050 5,825 9,100 2 -3,104 3,550 2,950 Assume that RF = 4.6%, market risk premium = 10.1%, and beta = 1.3. Use the EANPV approach to determine which project(s) Tamarisk Inc. should choose if they are mutually exclusive. (Round cost of capital to 2 decimal places, e.g.17.35% and the final answers to 0 decimal places, e.g. 2,513.) PMT1 $   ...
A project has the following total (or net) after-tax cash flows.                ____________________________________________________         Year&nbs
A project has the following total (or net) after-tax cash flows.                ____________________________________________________         Year             Total (or net) after-tax cash flow                ____________________________________________________                   1 $1,000,000 2 1,500,000 3 2,000,000 4 2,500,000                   _______________________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $4,000,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project. c) Find...
1. Me Online, Inc. is considering a project that has an initial after-tax outlay or after-tax...
1. Me Online, Inc. is considering a project that has an initial after-tax outlay or after-tax cost of $220,000. The respective future cash inflows from its four-year project for years 1 through 4 are: $50,000, $60,000, $70,000 and $80,000. Sportswear Online uses the net present value method and has a discount rate of 11%. Will Sportswear Online accept the project? a. Me Online rejects the project because the NPV is about -$22,375.73 b. Me Online accepts the project because the...
Assume the high-tech version is an acceptable project if evaluated on an individual basis. How will...
Assume the high-tech version is an acceptable project if evaluated on an individual basis. How will you decide what to recommend for the proposed new leash? A. Accept the project if the incremental IRR > required return B. Reject the project if the incremental IRR < IRR for the high-tech version C. Accept both projects if both versions have IRR > required return D. Reject the project if the incremental IRR > required return
The tax rate on the product group chocolate and confectionery has been determined on the basis...
The tax rate on the product group chocolate and confectionery has been determined on the basis of fiscal considerations. The tax includes goods that are considered typical sweets, such as chocolate, candies, caramels, and some types of biscuits. Ice cream, baked goods, and some types of biscuits are exempt from the tax. e) Briefly explain in words what we mean by fiscal taxes. Discuss and illustrate graphically how the tax on chocolate and confectionery affects the quantity sold in the...
After the problem has been set up, the calculator should be used to compute NPV and...
After the problem has been set up, the calculator should be used to compute NPV and IRR.   Show calculator inputs. Chunky Monkey Ice Cream has a 12% cost of capital, and has generated the following information on two mutually exclusive projects.   Project A will require an investment of $100,000 while the initial outlay for Project B is 2 ½ times greater:              Year Project A Project B 1 30,000 75,000 2 30,000 75,000 3 30,000 75,000 4 30,000 75,000 5 50,000 100,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT