In: Finance
Investment Timing Option: Option Analysis
The Karns Oil Company is deciding whether to drill for oil on a tract of land that the company owns. The company estimates the project would cost $8 million today. Karns estimates that, once drilled, the oil will generate positive net cash flows of $4 million a year at the end of each of the next 4 years. Although the company is fairly confident about its cash flow forecast, in 2 years it will have more information about the local geology and about the price of oil. Karns estimates that if it waits 2 years then the project would cost $9 million. Moreover, if it waits 2 years, then there is a 90% chance that the net cash flows would be $4.2 million a year for 4 years and a 10% chance that they would be $2.2 million a year for 4 years. Assume all cash flows are discounted at 10%. Use the Black-Scholes model to estimate the value of the option. Assume the variance of the project's rate of return is 0.111 and that the risk-free rate is 8%. Do not round intermediate calculations. Enter your answers in millions. For example, an answer of $10,550,000 should be entered as 10.55. Round your answer to three decimal places.
Option 1 (start project now):
Option 1: | |
Initial investment (II) | (80,00,000.00) |
Annual cash flow (CF) | 4,000,0000.00 |
PV of CF | 1,26,79,461.79 |
NPV (II + PV of CF) | 46,79,461.79 |
Option 2 (start project 2 years from now):
Formula | Option 2: | |
Initial investment (II) | (90,00,000.00) | |
Annual cash flow (with 90% prob.) | 42,00,000.00 | |
PV of annual cash flow (pv1) | 1,33,13,434.87 | |
90%*pv1 | Prob. Weight PV (PV1) | 1,19,82,091.39 |
Annual cash flow (with 10% prob.) | 22,00,000.00 | |
PV of annual cash flow (pv2) | 69,73,703.98 | |
10%*pv2 | Prob. Weight PV (PV2) | 6,97,370.40 |
(II+PV1+PV2) | NPV | 36,79,461.785 |
For the Black-Scholes Model:
Spot price = NPV of choice 1 = 4,679,461.785
Strike price = NPV of choice 2 = 3,679,461.785
Time to expiry = 2 years (the time between the two options)
Variance = 0.111 or 11.1%, so volatility (or standard deviation) = 0.111^0.5 = 33.32%
Risk-free rate = 8%
Using a Black-Scholes calculator, the value of the option to wait is: $1,739,328.91 or $1.739 million.