Question

In: Accounting

2. The completed contract method of accounting for long-term construction-type contracts is preferable when: Select one:...

2. The completed contract method of accounting for long-term construction-type contracts is preferable when: Select one: a. Estimates of costs to complete and extent of progress toward completion are reasonably dependable. b. The contracts are of a relatively long duration. c. Lack of dependable estimates or inherent hazards cause forecasts to be doubtful d. A contractor is involved in numerous projects.

3. In preparing the adjusting journal entries for Year 4, the accountant for a large local law firm discovered that depreciation on furniture, fixtures and office equipment was understated by $40,000 for Year 3. The previous accountant had not depreciated a leasehold improvement because she believed that the improvement would revert to the office owner at the end of the lease term. The present accountant, knowing better, prepared the journal entry to make the correction. That entry, assuming a tax rate of 30%, would include which of the following: Select one: a. dr. accumulated depreciation $28,000. b. cr. retained earnings $28,000. c. dr. depreciation expense $28,000 d. dr. retained earnings $28,000.

4. King Corporation decided to sell its sporting goods business segment for $900,000, on September 1, Year 1, which is also the disposal date. The book value of the segment's net assets is $700,000 on this date. The pre-tax income for the segment for the period January 1 - September 1, Year 1, was $20,000. Assuming a tax rate of 40%, choose the correct reporting for discontinued operations in the income statement of King Corporation, for the year ended December 31, Year 1. Select one: a. Choice 1 b. Choice 2 c. Choice 3 d. Choice 4

Solutions

Expert Solution

answer to Question 2- Correct Option is c)

The completed contract method of accounting for long-term construction-type contracts is preferable when (c) Lack of dependable estimates or inherent hazards cause forecasts to be doubtful

Becuase The completed contract method is used to recognize all of the revenue and profit associated with a project only after the project has been completed. This method is used when there is uncertainty about the collection of funds due from a customer under the terms of a contract.

Answer to Q3 -

In preparing the adjusting journal entries for Year 4, the accountant for a large local law firm discovered that depreciation on furniture, fixtures and office equipment was understated by $40,000 for Year 3. The previous accountant had not depreciated a leasehold improvement because she believed that the improvement would revert to the office owner at the end of the lease term. The present accountant, knowing better, prepared the journal entry to make the correction. That entry, assuming a tax rate of 30%, would include which of the following: d). dr. retained earnings $28,000.

This is becuase we should charge the short-depreciation net of taxes and this will have the effect of reducing profits as expenses in the PY should have been more by $28000

Answer to Q4 - Question does not elaborate/present  the choices 1,2,3,4


Related Solutions

Widjaja Compay is accounting for a long term construction contract using the percentage of completion method....
Widjaja Compay is accounting for a long term construction contract using the percentage of completion method. It is a 4 year contract that is currently in its second year. The latest estimates of contact costs indicate that the contact will be completed at a profit to the company. Based on this information please answer the following: 1 What theoretical justification is there or the Widjaja Company's use of the percentage-of-completion method 2 Discuss how the progress billings will be accounted...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
What are the two basic methods of accounting for long-term construction contracts? Indicate the circumstances that...
What are the two basic methods of accounting for long-term construction contracts? Indicate the circumstances that determine when one or the other of these methods should be used.
Two undergraduate accounting learners discussed the timing of revenue recognition for long-term construction contracts in their...
Two undergraduate accounting learners discussed the timing of revenue recognition for long-term construction contracts in their online course discussion area. The discussion focused on which method was most like the typical revenue recognition method of recognizing revenue at the point of product delivery. William argued that recognizing revenue upon project completion was preferable because it was analogous to recognizing revenue at the point of delivery. Sarah disagreed and supported recognizing revenue over time, stating that it was analogous to accruing...
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which...
Long‐term contract based on percentage of completion method Jim’s Construction Co. has a $6,800,000 contract which began on January 1, 2015 to build a new football stadium with an expected completion date of October 31, 2017. The following table provides information gathered during the construction period. Jim uses the percentage completion method to account for this contract.                                                                                                                                  2015 2016 2017 Construction costs incurred during the year 2,040,000 2,932,500 1,657,500 Estimated costs to complete 3,060,000 1,657,500 0 Billings during the...
Two first year accounting associates are discussing the timing of revenue recognition for long-term construction contracts,...
Two first year accounting associates are discussing the timing of revenue recognition for long-term construction contracts, and more specifically, discussing which method best reflects the point-of-sale/delivery. One associate, Taylor, believes recognizing revenue at the time of completion is the preferred method and most like point-of-sale/delivery revenue recognition. The other associate, Alex, believes recognizing the revenue over time is the preferred method because revenue is recognized as time progresses (as portions of the contract are completed), and the revenue can be...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 50 $ 150 $ 45 Estimated costs to complete as of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT