Question

In: Statistics and Probability

Explain any difference between the cost per equivalent unit in the Assembly Department under the weighted-average method and the FIFO method.

FIFO method (continuation of 17-30). Do Problem 17-30 using the FIFO method of process costing. Explain any difference between the cost per equivalent unit in the Assembly Department under the weighted-average method and the FIFO method.

Solutions

Expert Solution

FIFO method (continuation of 17-30).

1.         

The equivalent units of work done in the current period in the Assembly Department in October 2009 for direct materials and conversion costs are shown in Solution Exhibit 17-32A.

 

2.         

The cost per equivalent unit of work done in the current period in the Assembly Department in October 2009 for direct materials and conversion costs is calculated in Solution Exhibit 17-32B.

3.         

Solution Exhibit 17-32B summarizes the total Assembly Department costs for October 2009, and assigns these costs to units completed (and transferred out) and units in ending work in process under the FIFO method.

 

The cost per equivalent unit of beginning inventory and of work done in the current period differ:

 

 

Beginning 

Inventory

Work Done in 

Current Period

Direct materials

Conversion costs

Total cost per unit

$250.00 ($1,250,000 ÷ 5,000 equiv. units)

 134.25 ($ 402,750 ÷ 3,000 equiv. units)

$384.25

$225.00

 110.00

$335.00

 

Direct

Materials

Conversion

Costs

Cost per equivalent unit (weighted-average)

$230*

$113*

Cost per equivalent unit (FIFO)

 $225**

 $110**

*from Solution Exhibit 17-30B

**from Solution Exhibit 17-32B

 

The cost per equivalent unit differs between the two methods because each method uses different costs as the numerator of the calculation. FIFO uses only the costs added during the current period whereas weighted-average uses the costs from the beginning work-in-process as well as costs added during the current period. Both methods also use different equivalent units in the denominator.

            

The following table summarizes the costs assigned to units completed and those still in process under the weighted-average and FIFO process-costing methods for our example.

 

 

Weighted Average

(Solution Exhibit 17-30B)

FIFO

(Solution Exhibit 17-32B)

Difference

Cost of units completed and transferred out

Work in process, ending

Total costs accounted for

$7,717,500

772,750

$8,490,250

$7,735,250

755,000

$8,490,250

+ $17,750

- $17,750

                  

The FIFO ending inventory is lower than the weighted-average ending inventory by $17,750. This is because FIFO assumes that all the higher-cost prior-period units in work in process are the first to be completed and transferred out while ending work in process consists of only the lower-cost current-period units. The weighted-average method, however, smoothes out cost per equivalent unit by assuming that more of the lower-cost units are completed and transferred out, while some of the higher-cost units in beginning work in process are placed in ending work in process. So, in this case, the weighted-average method results in a lower cost of units completed and transferred out and a higher ending work-in-process inventory relative to the FIFO method.

SOLUTION EXHIBIT 17-32A

Steps 1 and 2: Summarize Output in Physical Units and Compute Output in Equivalent Units;

FIFO Method of Process Costing, 

Assembly Department of Larsen Company for October 2009.

 

(Step 1)

(Step 2)

Equivalent Units

Flow of Production

Physical

Units

Direct

Materials

Conversion

Costs

 

Work in process, beginning (given)

Started during current period (given)

To account for

 5,000

20,000

 25,000

(work done before current period)

Completed and transferred out during current period:

 From beginning work in process·

 5,000 × (100% - 100%); 5,000 × (100% - 60%)

 

 

 5,000

0

 2,000

 Started and completed

 17,500 ×100%, 17,500 × 100%

 17,000

17,500

 

 17,500

Work in process, ending* (given)

2,500 × 100%; 2,500 × 70%

 2,500

 _____

2,500

 1,750

Accounted for

25,000

                        

   ______

Work done in current period only

 

20,000

21,250

·Degree of completion in this department: direct materials, 100%; conversion costs, 60%.

22,500 physical units completed and transferred out minus 5,000 physical units completed and transferred out from beginning work-in-process inventory.

*Degree of completion in this department: direct materials, 100%; conversion costs, 70%. 

SOLUTION EXHIBIT 17-32B

Steps 3, 4, and 5: Summarize Total Costs to Account For, Compute Cost per Equivalent Unit, and Assign Total Costs to Units Completed and to Units in Ending Work in Process;

FIFO Method of Process Costing, Assembly Department of Larsen Company for October 2009.

 

Total

Production

Costs

Direct

Materials

Conversion

Costs

(Step 3) Work in process, beginning (given)

$1,652,750

$1,250,000

 $ 402,750

Costs added in current period (given)

6,837,500

4,500,000

2,337,500

Total costs to account for

$8,490,250

$5,750,000

$2,740,250

       

(Step 4) Costs added in current period

 

$4,500,000

$2,337,500

             Divide by equivalent units of work done in

             current period (Solution Exhibit 17-32A)

 

÷20,000

÷21,250

 

             Cost per equivalent unit of work done in current period

     

$ 225

$  110

       

(Step 5) Assignment of costs:

             Completed and transferred out (22,500 units):

     

                  Work in process, beginning (5,000 units)

 Costs added to beg. work in process in current period

$1,652,750

220,000

 $1,250,000 + $ 402,750

 (0× $225) + (2,000* × $110)

 

Total from beginning inventory

                  Started and completed (17,500 units)

                         Total costs of units completed & transferred out

             Work in process, ending (2,500 units)

             Total costs accounted for

1,872,750

5,862,500

7,735,250

755,000 

$8,490,250

(17,500† × $225) + (17,500† × $110)

          

(2,500# . $225) + (1,750. $110)

$5,750,000 + $2,740,250

   

 

         
 
*Equivalent units used to complete beginning work in process from Solution Exhibit 17-32A, Step 2.
Equivalent units started and completed from Solution Exhibit 17-32A, Step 2.
#Equivalent units in ending work in process from Solution Exhibit 17-32A, Step 2. 

The equivalent units of work done in the current period in the Assembly Department in October 2009 for direct materials and conversion costs are shown in Solution Exhibit 17-32A.

Related Solutions

explain any difference between the cost of work completed and transferred out and the cost of ending work in process in the Assembly Department under the weighted-average method and the FIF0 method.
FIFO method (continuation of 17-35). Do Problem 17-35 using the FIFO method of process costing. If you did Problem 17-35, explain any difference between the cost of work completed and transferred out and the cost of ending work in process in the Assembly Department under the weighted-average method and the FIF0 method.
Exercise 4-3 Cost Per Equivalent Unit-Weighted-Average Method [LO4-3] Superior Micro Products uses the weighted-average method in...
Exercise 4-3 Cost Per Equivalent Unit-Weighted-Average Method [LO4-3] Superior Micro Products uses the weighted-average method in its process costing system. Data for the Assembly Department for May appear below: Materials Labor Overhead   Work in process, May 1 $ 40,600   $ 68,409   $ 331,872     Cost added during May $ 246,530   $ 45,606   $ 221,248     Equivalent units of production 3,400   3,300   3,200   Required: 1. Compute the cost per equivalent unit for materials, for labor, and for overhead. (Round your answers to 2...
what is the difference between the Average cost method, LIFO method, FIFO method, and Specification Identification...
what is the difference between the Average cost method, LIFO method, FIFO method, and Specification Identification method? why do you recommend the average cost method? what are the consequences they may have on the valuation of the inventory and determination of the net income in case of price fluctuation?
What is the difference between FIFO, LIFO and Average Cost Method? What is the impact of...
What is the difference between FIFO, LIFO and Average Cost Method? What is the impact of FIFO, LIFO and Average cost method amongst income statements and balance sheets? What are the depreciation methods for PPE? What is the impact of each depreciation method on the income statement and balance sheet? What is the asset sale in regards to financial statement impact?
Demonstrate the concept of EUP(equivalent units of production) and its calculation under Weighted Average and FIFO...
Demonstrate the concept of EUP(equivalent units of production) and its calculation under Weighted Average and FIFO method with an illustration. (Use imaginary figures of your own)                                                                           
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes...
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes through two processes: Fabrication and Assembly. The following information was obtained for the Fabrication Department for September: All materials are added at the beginning of the process. Beginning work in process had 70,400 units, 40 percent complete with respect to conversion costs. Ending work in process had 12,200 units, 25 percent complete with respect to conversion costs. Started in process, 96,600 units. Required: 1....
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes...
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes through two processes: Fabrication and Assembly. The following information was obtained for the Fabrication Department for September: All materials are added at the beginning of the process. Beginning work in process had 71,200 units, 40 percent complete with respect to conversion costs. Ending work in process had 13,400 units, 20 percent complete with respect to conversion costs. Started in process, 101,200 units. Required: 1....
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes...
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes through two processes: Fabrication and Assembly. The following information was obtained for the Fabrication Department for September: All materials are added at the beginning of the process. Beginning work in process had 74,900 units, 40 percent complete with respect to conversion costs. Ending work in process had 19,600 units, 35 percent complete with respect to conversion costs. Started in process, 109,100 units. Required: 1....
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes...
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes through two processes: Fabrication and Assembly. The following information was obtained for the Fabrication Department for September: All materials are added at the beginning of the process. Beginning work in process had 73,600 units, 40 percent complete with respect to conversion costs. Ending work in process had 15,700 units, 35 percent complete with respect to conversion costs. Started in process, 90,600 units. Required: 1....
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes...
Weighted Average Method, FIFO Method, Physical Flow, Equivalent Units Heap Company manufactures a product that passes through two processes: Fabrication and Assembly. The following information was obtained for the Fabrication Department for September: All materials are added at the beginning of the process. Beginning work in process had 90,300 units, 20 percent complete with respect to conversion costs. Ending work in process had 12,900 units, 20 percent complete with respect to conversion costs. Started in process, 98,200 units. Required: 1....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT