In: Finance
| Consider the following two mutually exclusive projects: | 
| Year | Cash Flow (A) | Cash Flow (B) | 
| 0 | –$258,138 | –$15,249 | 
| 1 | 26,800 | 4,065 | 
| 2 | 54,000 | 8,853 | 
| 3 | 54,000 | 13,513 | 
| 4 | 426,000 | 9,112 | 
| Whichever project you choose, if any, you require a 6 percent return on your investment. | 
| a. What is the payback period for Project A? | 
| Multiple Choice | 
  | 
| b. What is the payback period for Project B? | 
| Multiple Choice | 
  | 
| c. What is the discounted payback period for Project A? | 
| Multiple Choice | 
  | 
| d. What is the discounted payback period for Project B? | 
| Multiple Choice | 
  | 
| e. What is the NPV for Project A? | 
| Multiple Choice | 
  | 
| f. What is the NPV for Project B ? | 
| Multiple Choice | 
  | 
| g. What is the IRR for Project A? | 
| Multiple Choice | 
  | 
| h. What is the IRR for Project B? | 
| Multiple Choice | 
  | 
| i. What is the profitability index for Project A? | 
| Multiple Choice | 
  | 
| j. What is the profitability index for Project B? | 
| Multiple Choice | 
  | 
| Answer a | |||||||||
| Calculation of Payback period | |||||||||
| Year | Project A | Project B | |||||||
| Cash flow | Cumulative Cash flows | Cash flow | Cumulative Cash flows | ||||||
| 0 | -$258,138.00 | -$258,138.00 | -$15,249.00 | -$15,249.00 | |||||
| 1 | $26,800.00 | -$231,338.00 | $4,065.00 | -$11,184.00 | |||||
| 2 | $54,000.00 | -$177,338.00 | $8,853.00 | -$2,331.00 | |||||
| 3 | $54,000.00 | -$123,338.00 | $13,513.00 | $11,182.00 | |||||
| 4 | $426,000.00 | $302,662.00 | $9,112.00 | $20,294.00 | |||||
| Payback period of Project A = 3 Years + [$123338 / $426000] = 3.29 years | |||||||||
| Answer b | |||||||||
| Payback period of Project B = 2 Years + [$2331/$13513] = 2.17 years | |||||||||
| Answer c | |||||||||
| Calculation of discounted payback period | |||||||||
| Year | Project A | Project B | |||||||
| Discount Factor @ 6% | Cash flow | Present Value | Cumulative Cash flows | Cash flow | Present Value | Cumulative Cash flows | |||
| 0 | 1.00000 | -$258,138.00 | -$258,138.00 | -$258,138.00 | -$15,249.00 | -$15,249.00 | -$15,249.00 | ||
| 1 | 0.94340 | $26,800.00 | $25,283.02 | -$232,854.98 | $4,065.00 | $3,834.91 | -$11,414.09 | ||
| 2 | 0.89000 | $54,000.00 | $48,059.81 | -$184,795.17 | $8,853.00 | $7,879.14 | -$3,534.96 | ||
| 3 | 0.83962 | $54,000.00 | $45,339.44 | -$139,455.73 | $13,513.00 | $11,345.78 | $7,810.82 | ||
| 4 | 0.79209 | $426,000.00 | $337,431.90 | $197,976.17 | $9,112.00 | $7,217.56 | $15,028.38 | ||
| Discounted Payback period of Project A = 3 Years + [$139455.73 / $337431.90] = 3.41 years | |||||||||
| Answer d | |||||||||
| Discounted Payback period of Project B = 2 Years + [$3534.96/$11345.78] = 2.31 years | |||||||||
| Answer e | |||||||||
| Calculation of NPV of project | |||||||||
| Project A | |||||||||
| Year | Discount Factor @ 6% | Cash flow | Present Value | ||||||
| 0 | 1.00000 | -$258,138.00 | -$258,138.00 | ||||||
| 1 | 0.94340 | $26,800.00 | $25,283.02 | ||||||
| 2 | 0.89000 | $54,000.00 | $48,059.81 | ||||||
| 3 | 0.83962 | $54,000.00 | $45,339.44 | ||||||
| 4 | 0.79209 | $426,000.00 | $337,431.90 | ||||||
| NPV of Project A | $197,976.17 | ||||||||
| Answer f | |||||||||
| Project B | |||||||||
| Year | Discount Factor @ 6% | Cash flow | Present Value | ||||||
| 0 | 1.00000 | -$15,249.00 | -$15,249.00 | ||||||
| 1 | 0.94340 | $4,065.00 | $3,834.91 | ||||||
| 2 | 0.89000 | $8,853.00 | $7,879.14 | ||||||
| 3 | 0.83962 | $13,513.00 | $11,345.78 | ||||||
| 4 | 0.79209 | $9,112.00 | $7,217.56 | ||||||
| NPV of Project B | $15,028.38 | ||||||||
| Answer g | Answer h | ||||||||
| Calculation of IRR of project | Calculation of IRR of project | ||||||||
| Year | Project A Cash flows | Year | Project B Cash flows | ||||||
| 0 | -$258,138.00 | 0 | -$15,249.00 | ||||||
| 1 | $26,800.00 | 1 | $4,065.00 | ||||||
| 2 | $54,000.00 | 2 | $8,853.00 | ||||||
| 3 | $54,000.00 | 3 | $13,513.00 | ||||||
| 4 | $426,000.00 | 4 | $9,112.00 | ||||||
| IRR of Project A = | 25.00% | IRR of Project A = | 38.00% | ||||||
| Answer I | |||||||||
| Profitability index for Project A = Present Value of future cash inflows / Initial Investment = $456,114.17 / $258,138 = 1.767 | |||||||||
| Answer J | |||||||||
| Profitability index for Project B = Present Value of future cash inflows / Initial Investment = $30,277.38 / $15,249 = 1.986 | |||||||||