Question

In: Accounting

Erin Company's inventory at December 1, and the costs charged to Work in Process—Department B during...

Erin Company's inventory at December 1, and the costs charged to Work in Process—Department B during December are as follows:

1,200 units, 40% completed $47,800
From Department A, 26,000 units 845,000
Direct labor 312,000
Factory overhead 176,770

During December, all direct materials are transferred from Department A, the units in process at December 1 were completed, and of the 26,000 units entering the department, all were completed except 1,000 units which were 70% completed as to conversion costs. Inventories are costed by the first-in, first-out method.

Prepare a cost of production report for December.

Round your cost per equivalent unit amounts to two decimal places. Round all other amounts to the nearest dollar. If an amount value is zero enter "0" as answer.

Erin Company
Cost of Production Report--Department B
For the Month Ended December 31
Unit Information
Units charged to production:
Inventory in process, December 1
Received from Department A
Total units accounted for by Department B
Units to be assigned cost:
Equivalent Units
Whole Units Direct Materials Conversion
Inventory in process, December 1 (40% completed)
Started and completed in December
Transferred to finished goods in December
Inventory in process, December 31 (70% complete)
Total units to be assigned costs
Cost Information
COSTS:
Direct Materials Costs Conversion Costs
Costs per equivalent unit:
Total costs for December in Department B $ $
Total equivalent units
Cost per equivalent unit $ $
Costs charged to production:
Direct Materials Costs Conversion Costs Total Costs
Inventory in process, December 1 $
Costs incurred in December
Total costs accounted for by Department B $
Costs allocated to completed and partially completed units:
Inventory in process, December 1, balance $
To complete inventory in process, December 1 $ $
Started and completed in December
Transferred to finished goods in December $
Inventory in process, December 31
Total costs assigned by Department B $

Loading item

There was an error loading this item. If this continues to occur, please contact Technical Support.

Check My Work

Solutions

Expert Solution

Erin Company
Cost of Production Report--Department B
For the Month Ended December 31
Equivalent units
Whole Units Direct material Conversion
Inventory in process, December 1 (40% completed) 1200
Received from Department A 26000
Total units accounted for by Dept. B 27200
Units to be assigned costs:
Inventory in process, Dec 1
(40% completed) 1200*60%=720 1200 0 720
Started and completed in dec 25000 25000 25000
Transferred to finished goods in Dec 26200 25000 25720
Inventory in process, Dec 30 (70% completed) 1000 1000 700
Total units to be assigned costs 27200 26000 26420
Costs
Direct material Conversion Total Costs
Costs
Units Costs
Total costs for Dec in Dept. B 845000 488770 1333770
Total equivalent units 26000 26420
Cost per equivalent unit 32.5 18.50
Costs charged to production:
Inventory in process, Dec1 47800
Costs incurred in Dec (845000+312000+176770) 1333770
Total costs accounted for byDepartment B 1381570
Costs allocated to completed and partially completed units:
Inventory in process, Dec 1, bal. 47800
To complete inventory inprocess, Dec 1 0 13320 13320
Started and completed in April 812500 462500 1275000
Transferred to finishedgoods in Dec 1336120
Inventory in process, Dec 30 32500 12950 45450
Total costs assigned by Dept. B 1381570

Related Solutions

Erin Company's inventory at December 1 and the costs charged to Work in Process—Department B during...
Erin Company's inventory at December 1 and the costs charged to Work in Process—Department B during December are as follows: 1,200 units, 40% completed $47,800 From Department A, 26,000 units 845,000 Direct labor 312,000 Factory overhead 176,770 During December, all direct materials are transferred from Department A, the units in process at December 1 were completed, and of the 26,000 units entering the department, all were completed except 1,000 units that were 70% completed as to conversion costs. Inventories are...
Skittles Company's inventory on March 1 and the costs charged to Work in Process—Dipping Department during...
Skittles Company's inventory on March 1 and the costs charged to Work in Process—Dipping Department during March are as follows: Beginning work in process, 500 units, 60% completed $ 3,460 From Sugar Mixing Department, 10,000 units (direct materials) 36,300 Direct labor incurred 7,960 Factory overhead incurred 12,500 ​ During March, all direct materials were transferred from the Mixing Department, the units in process at March 1 were completed, and of the 10,000 units entering the department, all were completed except...
The inventory at April 1, 2020, and the costs charged to Work in Process--Department B during...
The inventory at April 1, 2020, and the costs charged to Work in Process--Department B during April for Worldwide Company are as follows: 1,200 units, 40% completed $  47,800 From Department A, 26,000 units 845,000 Direct labor 312,000 Factory overhead 176,770 During April, all direct materials are transferred from Department A. In Department B, the units in process at April 1 were completed, and of the 26,000 units entering the department, all were completed except 1,000 units which were 70% completed...
M&M Company's inventory on March 1 and the costs charged to Work in Process—Dipping Department during...
M&M Company's inventory on March 1 and the costs charged to Work in Process—Dipping Department during March are as follows: Beginning work in process, 12,000 units, 60% completed $ 62,400 From Chocolate Mixing Department, 55,000 units (direct materials) 115,500 Direct labor incurred 384,915 Factory overhead incurred 138,000 During March, all direct materials were transferred from the Mixing Department, the units in process at March 1 were completed, and of the 55,000 units entering the department, all were completed except 6,000...
The inventory at May 1 and the costs charged to Work in Process -- Department B...
The inventory at May 1 and the costs charged to Work in Process -- Department B during May for Star Company are as follows: 8,000 Units, 75% Completed ---- $65,600 From Department A, 43,500 Units ---- $78,300 Direct Labor ---- $292,400 Factory Overhead ---- $107,100 During May, all direct materials are transferred from Department A, the units process at May 1 were completed, and of the 43,500 units entering the department, all were completed except 9,000 units which were 2/3...
The Inventory at July 1st and the cost charged to work in process department B during...
The Inventory at July 1st and the cost charged to work in process department B during July for the Parker Corporation are as follows: 32,000 units, 3/4 completed...................................1,312,000 From Department A 174,000 units.........................1,566,000 Direct Labor............................................................5,848,000 Factory Overhead...................................................1,292,000 During July, all direct materials are transferred from Department A, the units in process at July 1st were completed, and of the 174,000 units entering the Department, all were completed except 36,000 units which were 2/3 completed. Inventories are costed by the FIFO...
Work-in-process inventory, January 1, 2011 $ 51,000 Work-in-process inventory, December 31, 2011 $ 56,500 Conversion costs...
Work-in-process inventory, January 1, 2011 $ 51,000 Work-in-process inventory, December 31, 2011 $ 56,500 Conversion costs during the year $ 423,000 1. If direct materials used during the year were $143,000, what was cost of goods manufactured? 2. If the cost of goods manufactured for the year was $575,000, what was the amount of direct materials used during the year?
Question 1 (40 marks) The inventory at April 1, 2020, and the costs charged to Work...
Question 1 The inventory at April 1, 2020, and the costs charged to Work in Process--Department B during April for Worldwide Company are as follows: 1,200 units, 40% completed $  47,800 From Department A, 26,000 units 845,000 Direct labor 312,000 Factory overhead 176,770 During April, all direct materials are transferred from Department A. In Department B, the units in process at April 1 were completed, and of the 26,000 units entering the department, all were completed except 1,000 units which were...
Question 1 (40 marks) The inventory at April 1, 2020, and the costs charged to Work...
Question 1 The inventory at April 1, 2020, and the costs charged to Work in Process--Department B during April for Worldwide Company are as follows: 1,200 units, 40% completed $  47,800 From Department A, 26,000 units 845,000 Direct labor 312,000 Factory overhead 176,770 During April, all direct materials are transferred from Department A. In Department B, the units in process at April 1 were completed, and of the 26,000 units entering the department, all were completed except 1,000 units which were...
The Assembly Department of Power MotorsPower Motors began SeptemberSeptember with no work in process inventory. During...
The Assembly Department of Power MotorsPower Motors began SeptemberSeptember with no work in process inventory. During the month, production that cost $39,860 (direct materials, $9,900 , and conversion costs, $29,960 ) was started on 23,000 units. PowerPower completed and transferred to the Testing Department a total of 15,000 units. The ending work in process inventory was 37.5% complete as to direct materials and 80% complete as to conversion work. --------- 1. Compute the equivalent units for direct materials and conversion...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT