Question

In: Accounting

Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...

Required information

[The following information applies to the questions displayed below.]
  

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018 2019 2020
Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400
Estimated costs to complete as of year-end 5,396,000 2,204,000 0
Billings during the year 2,140,000 3,256,000 4,604,000
Cash collections during the year 1,870,000 3,200,000 4,930,000


Westgate recognizes revenue over time according to percentage of completion.

3. Complete the information required below to prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. (Do not round intermediate calculations.)

Solutions

Expert Solution

Balance Sheet (Partial) 2018 2019
Current Assets:
Accounts receivable $       2,70,000 $       3,26,000
Construction in progress $     29,00,000 $      71,00,000
Less: Billings $   -21,40,000 $     -53,96,000
Cost in excess of billings $       7,60,000 $     17,04,000
Current Liabilities:
Working Notes: 2018 2019
Cost incurred during the year $     22,04,000 $     31,92,000
Add: Cost incurred in previous year $     22,04,000
Cost incurred till date (i) $     22,04,000 $     53,96,000
Add: Estimated cost to complete $     53,96,000 $     22,04,000
Total cost (ii) $     76,00,000 $     76,00,000
Percentage Completed [(iii) = (i) / (ii)] 29% 71%
Construction in progress [$10000000 X (iii)] $     29,00,000 $     71,00,000
Billings during the year $     21,40,000 $     32,56,000
Less: Cash collections during the year 1870000 3200000
Accounts Receivable $       2,70,000 $           56,000
Add: Previous year balance $       2,70,000
Total Accounts receivables $       2,70,000 $       3,26,000

Related Solutions

Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,550,000 $ 4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during the year 2,050,000 4,750,000 3,200,000 Cash collections during...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT