1- write Commissioning, Startup, Operation, and Shutdown procedure of a pump
2- What is the function of shaft sleeve for a centrifugal pump?
3: Discuss the types of pipe reducers for a centrifugal pumping system
4: Write a gate valve mounting procedure
5: Write assembly and dismantling procedure of a
rising stem gate valve
1) Pre start up checks needs to be done before starting up the
pump to detect any failures and deal with them. Pump should be
checked for proper placement and must be secured properly. All the
fasteners must be tightened. The rotation of the pump shaft must be
checked. Shaft seals, alignment and bearing lube must all be taken
care of.
Details such as pump data sheet, pump curve, installation operation
booklet , general tools, instruments such as vibrometer etc must be
checked with.
After pre check the pump startup begins and suction valve is opened
to full open position. Discharge valve is also opened slightly.
Pump must be primed and regulation of all heating, cooling sections
must be done. Then the motor is started and discharge is adjusted
and desired flow is reached.
Shutdown should be done in the reverse direction of startup and
driver is also shutdown. Dischareg valve for small pumps ae closed
along with the suction valve.