Using everything you know about capital budgeting, if the two projects are mutually exclusive, which project...

Using everything you know about capital budgeting, if the two projects are mutually exclusive, which project or projects should the firm undertake? Explain in full. The answer must be complete (mini paragraph). Substantiate with numbers.

Solutions

Expert Solution

MUTUALLY EXCLUSIVE PROJECTS MEANS ONLY ONE OF THE PROJECT IS TO BE SELECTED.

SO IT IMPLIES CAPITAL RATIONING.

SO WE HAVE TO SELECT THE BEST PROJECT & NPV IS THE BEST METHOD FOR SELECTING THE PROJECT.

WHY NPV ?

BECAUSE THIS IS THE ONLY PROJECT WHICH USES TIME VALUE CONCEPT. SO OUT OF ALL METHODS AVAILABLE, NPV IS THE ONLY BEST.

EXAMPLE : SEE EXCEL SHEET


Related Solutions

As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for Bissett Corporation, you are evaluating two mutually exclusive projects (you can only choose one) with the following cash flows. The discount rate is 15%. Year Project X Project Y 0 - 100,000 - 100,000 1 50,000 10,000 2 40,000 30,000 3 10,000 40,000 4 10,000 30,000 Which project would you choose? Project X since it has higher IRR Project Y since it has higher NPV Project X since it has higher NPV Neither...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows: Project E Project F Year Cash Flow Cash Flow 0 -$100,000 -$100,000 1 50,000 10,000 2 40,000 30,000 3 30,000 40,000 4 10,000 60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects...
As the director of capital budgeting for EFG Corporation, you are evaluating two mutually exclusive projects with the following net cash flows:                                Project E Project F                   Year     Cash Flow     Cash Flow                    0       -$100,000        -$100,000                    1          50,000            10,000                    2          40,000            30,000                    3          30,000            40,000                    4          10,000            60,000 If EFG’s cost of capital is 15 percent, What is the NPV and IRR of the better project, respectively??
Company A is considering the following two mutually exclusive projects. Company A bases their capital budgeting...
Company A is considering the following two mutually exclusive projects. Company A bases their capital budgeting decisions solely on the NPV criteria. (Do not round intermediate calculations. Round your final answer to two decimal places.) Year Project 1 Project 2 0 -$75,000 -$75,000 1 $50,000 $20,000 2 $30,000 $21,000 3 $15,000 $59,000 1. At what required rate of return (%) is Company A indifferent between the two projects? 2. If the required rate of return is less than the crossover...
Capital Budgeting Question: You are considering two mutually exclusive projects for potential investment. The cash flows...
Capital Budgeting Question: You are considering two mutually exclusive projects for potential investment. The cash flows for the two projects are given. For both projects, the required rate of return is 12%. Year Project A Project B 0 ($40,000) ($40,000) 1 $14,400 $0 2 $14,400 $0 3 $14,400 $0 4 $14,400 $70,000 Find the following: 1. The Net Present Value (NPV) . 2. The Internal Rate of Return (IRR) . 3. Use Excel to draw a graph of the NPV...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project A -$250 $50 $50 $50 $200 $200 Project B -$600 $300 $300 $70 $70 $70 Which project would you recommend? Select the correct answer. I. Both Projects A and B, since both projects have IRR's > 0. II. Project A, since the NPVA > NPVB. III. Both Projects A and B, since both...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: Project A -$300 $75 $75 $75 $220 $220 Project B -$550 $250 $250 $80 $80 $80 Which project would you recommend? Select the correct answer. I. Both Projects A and B, since both projects have IRR's > 0. II. Project A, since the NPVA > NPVB. III. Project B, since the NPVB > NPVA. IV. Neither A or B, since...
A company is evaluating two mutually exclusive projects in which to invest. Project A needs an...
A company is evaluating two mutually exclusive projects in which to invest. Project A needs an investment of $300,000 and will deliver $160,000 in annual profits during its 8 years life. Project B needs an investment of $400,000 and will deliver $210,000 in annual profits during its 6 years life. Considering a Study Period of 6 years, and that project A can be sold for $200,000 at the end of the 6th year (because it will still have 2 years...
Capital budgeting criteria: mutually exclusive projects Project S costs $17,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $17,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $15,000 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Neither S or L, since each project's NPV < 0. III. Both...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT