Question

In: Finance

Sandhill Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...

Sandhill Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 10 percent discount rate for production systems. Year System 1 System 2 0 -$12,590 -$48,783 1 12,731 33,490 2 12,731 33,490 3 12,731 33,490 Compute the IRR for both production system 1 and production system 2. (Do not round intermediate calculations. Round answers to 2 decimal places, e.g. 15.25%.) IRR of system 1 is % and IRR of system 2 is %. Which has the higher IRR? has higher IRR. Compute the NPV for both production system 1 and production system 2. (Do not round intermediate calculations. Round answers to 2 decimal places, e.g. 15.25.) NPV of system 1 is $ and NPV of system 2 $ . Which production system has the higher NPV? has higher NPV.

Solutions

Expert Solution

Computation of IRR using trial and error method:

System 1:

Computation of NPV using discount rate of 85 %:

Year

Cash Flow S1

Computation of PV Factor

PV Factor @ 85 % (F)

PV (S1 x F)

0

-$12,590

1/(1+0.85)^0

1

-$12,590

1

12731

1/(1+0.85)^1

0.54054054054054

6881.62162

2

12731

1/(1+0.85)^2

0.29218407596786

3719.79547

3

12731

1/(1+0.85)^3

0.15793733836101

2010.70025

                     NPV1

  $22.11734

As NPV is positive, let’s compute NPV at discount rate of 86 %.

Year

Cash Flow S1

Computation of PV Factor

PV Factor @ 86 % (F)

PV (S1 x F)

0

-$12,590

1/(1+0.86)^0

1

-$12,590

1

12731

1/(1+0.86)^1

0.53763440860215

6844.62366

2

12731

1/(1+0.86)^2

0.28905075731298

3679.90519

3

12731

1/(1+0.86)^3

0.15540363296397

1978.44365

                        NPV2

-$ 87.02750

IRR = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]

= 85 % + [$ 22.11734 x (86% - 85%)/ ($ 22.11734 – (-$ 87.02750))]

= 85 % + [($ 22.11734 x 1 %)/ ($ 22.11734 +$ 87.02750)]

= 85 % + ($ 22.11734/ $ 109.14485)

= 85 % + 0.002026422

= 85 % + 0.20 % = 85.20 %

System 2:

Computation of NPV using discount rate of 47 %:

Year

Cash Flow S2

Computation of PV Factor

PV Factor @ 47 % (F)

PV (S2 x F)

0

-$48,783

1/(1+0.47)^0

1

-$48,783

1

33490

1/(1+0.47)^1

0.68027210884354

22782.31293

2

33490

1/(1+0.47)^2

0.46277014207043

15498.17206

3

33490

1/(1+0.47)^3

0.31480962045608

10542.97419

                            NPV1

    $40.45918

As NPV is positive, let’s compute NPV at discount rate of 48 %.

Year

Cash Flow S2

Computation of PV Factor

PV Factor @ 48 % (F)

PV (S2 x F)

0

-$48,783

1/(1+0.48)^0

1

-$48,783

1

33490

1/(1+0.48)^1

0.67567567567568

22628.37838

2

33490

1/(1+0.48)^2

0.45653761869978

15289.44485

3

33490

1/(1+0.48)^3

0.30847136398634

10330.70598

                           NPV 2

-$ 534.47079

IRR = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]

= 47 % + [$ 40.45918 x (48% - 47%)/ ($ 40.45918 – (-$ 534.47079))]

= 47 % + [($ 40.45918 x 1 %)/ ($ 40.45918 +$ 534.47079)]

= 47 % + ($ 0.4045918/ $ 574.92996)

= 47 % + 0.000703723

= 47 % + 0.07 % = 47.07 %

IRR of System 1 is 85.20 %

IRR of System 2 is 47.07 %

System 1 has higher IRR.

Computation of NPV:

System 1:

Year

Cash Flow S1

Computation of PV Factor

PV Factor @ 10 % (F)

PV (S1 x F)

0

-$12,590

1/(1+0.1)^0

1

-$12,590

1

12731

1/(1+0.1)^1

0.90909090909091

11573.63636

2

12731

1/(1+0.1)^2

0.82644628099174

10521.48760

3

12731

1/(1+0.1)^3

0.75131480090158

9564.98873

                        NPV S1

$19,070.11269

System 2:

Year

Cash Flow S2

Computation of PV Factor

PV Factor @ 10 % (F)

PV (S2 x F)

0

-$48,783

1/(1+0.1)^0

1

-$48,783

1

33490

1/(1+0.1)^1

0.90909090909091

30445.45455

2

33490

1/(1+0.1)^2

0.82644628099174

27677.68595

3

33490

1/(1+0.1)^3

0.75131480090158

25161.53268

                         NPV S2

$34,501.67318

NPV of System 1 is $ 19,070.11

NPV of System 2 is $ 34,501.67

System 2 has higher NPV.


Related Solutions

Blossom Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Blossom Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 9 percent discount rate for production system projects. Year System 1 System 2 0 -$15,900 -$43,400 1 15,900 31,700 2 15,900 31,700 3 15,900 31,700 Calculate NPV. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round answers...
Blossom Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Blossom Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 7 percent discount rate for production system projects. Year System 1 System 2 0 -$12,000 -$42,000 1 12,000 30,000 2 12,000 30,000 3 12,000 30,000 Calculate NPV. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round answers...
Wildhorse Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Wildhorse Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 7 percent discount rate for production systems. Year System 1 System 2 0 -$15,080 -$47,448 1 15,294 33,300 2 15,294 33,300 3 15,294 33,300 Compute the IRR for both production system 1 and production system 2. (Do not round intermediate calculations. Round...
Wildhorse Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Wildhorse Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 10 percent discount rate for production system projects. Year System 1 System 2 0 -$14,200 -$44,000 1 14,200 34,400 2 14,200 34,400 3 14,200 34,400 1) Calculate NPV. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round...
Crane Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive,...
Crane Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 8 percent discount rate for production system projects. YearSystem 1System 2 0 -$12,900-$43,800 1 12,900 32,500 2 12,900 32,500 3 12,900 32,500
Cullumber Incorporated management is considering investing in two alternative production systems.
Cullumber Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 9 percent discount rate for production system projects.YearSystem 1System 20-$13,000-$42,600113,00033,900213,00033,900313,00033,900Calculate NPV. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round answers to 2 decimal places, e.g. 15.25.)In which system should the firm invest?
Problem 10.25 Carla Vista Incorporated management is considering investing in two alternative production systems. The systems...
Problem 10.25 Carla Vista Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. The firm uses a 9 percent discount rate for production systems. Year System 1 System 2 0 -$12,010 -$49,910 1 12,080 33,930 2 12,080 33,930 3 12,080 33,930 Compute the IRR for both production system 1 and production system 2. (Do not round...
[EXCEL] Net present value: Blanda Incorporated management is considering investing in two alternative production systems. The...
[EXCEL] Net present value: Blanda Incorporated management is considering investing in two alternative production systems. The systems are mutually exclusive, and the cost of the new equipment and the resulting cash flows are shown in the accompanying table. If the firm uses a 9 percent discount rate for production system projects, in which system should the firm invest? Year    System 1         System 2 0          −$15,000        −$45,000 1          15,000            32,000 2          15,000            32,000 3          15,000            32,000 [EXCEL] Payback: Refer to Problem...
KORONA Manufacturing is considering investing in either of two mutually exclusive projects, A and B. The...
KORONA Manufacturing is considering investing in either of two mutually exclusive projects, A and B. The firm has a 14 percent cost of capital, and the risk-free rate is currently 9 percent. The initial investment, expected cash inflows, and certainty equivalent factors associated with each of the projects are shown in the following table. Project A Project B Initial investment (II) $ 40,000 $ 56,000 Year (t) Cash inflows (CFt) Certainty equivalent factors (αt) Cash inflows (CFt) Certainty equivalent factors...
ABC Company is considering investing in two mutually exclusive projects, L and S. The two projects’...
ABC Company is considering investing in two mutually exclusive projects, L and S. The two projects’ forecasted cash flows are shown as below. WACC is 10%. Year 0 1 2 3 4 Project L CF ($) -1,000    700 500 200 0 Project S CF ($) -1,200 100 300 800 1,000 a. Calculate the NPVs for both projects. b. Calculate the IRRs for both projects. c. Calculate the Discounted Paybacks for both projects. [Draw a timeline] d. Based on your...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT