In: Finance
Answer: -
NPV of the project is $3736
Explanation: -
Step 1: - calculation of equivalent cash flows from years 5 and 6
We know that the IRR is the discount rate at which NPV is equal to zero.
Therefore,
[Cash flow of years 1 to 4 * (PVIFA 16.15%, 4)] + [equal Cash flow of years 5 and 6 * ((PVIF 16.15%, 5) + (PVIF 16.15, 6))] - initial cost = 0
By substituting values, we get
[$2094 * 2.7898] + [equal Cash flow of years 5 and 6 * (.473 +.407)] - $9175 = 0
$5842 + [equal Cash flow of years 5 and 6 * .88] = $9175
equal Cash flow of years 5 and 6 * .88 = $9175 - $5842
equal Cash flow of years 5 and 6 = $3333 / .88
equal Cash flow of years 5 and 6 = $3787.5
Step 2: - calculation of NPV
NPV = [Cash flow of years 1 to 4 * (PVIFA 5.66%, 4)] + [equal Cash flow of years 5 and 6 * ((PVIF 5.66%, 5) + (PVIF 5.66%, 6))] - initial cost
NPV = [$2094 * 3.4926] + [$3787.5 * (.759 +.719)] - $9175
NPV = $7313.5 + $5598 - $9175
NPV = $3736