Question

In: Finance

Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects...

Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost.

r: 7.75%
Year 0 1 2 3 4
CFS −$1,050 $675 $650
CFL −$1,050 $360 $360 $360 $360

Solutions

Expert Solution

Solution:- Given in Question-

WACC (r) = 7.75%

First to calculate IRR of the Project-

Cross Over Rate = 9%.

Hence, Interest Rate is lower then Crossover rate. So Conflict Exists.

Then, We need to calculate IRR of Individual project-

IRR of CFS = 17.13%

IRR of CFL = 13.95%

Calculate NPV of the Project-

NPV of CFS = $136.31

NPV of CFL = $149.03

Value Lost if use the IRR Criterion = NPV of CFL - NPV of CFS

Value Lost if use the IRR Criterion = $149.03 - $136.31

Value Lost if use the IRR Criterion = $12.72

If you have any query related to question then feel free to ask me in a comment. Thanks. Please rate.


Related Solutions

A company is considering Projects S and L, whose cash flows are shown below. These projects...
A company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates other methods. If the decision is made by choosing the project with the higher IRR, how much, if any, value will be forgone, i.e., what's the: NPV and IRR of the chosen project(s). What is the Payback period, discounted payback period, and...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. WACC: 7.75 CFs Y0: $-1050 Y1 $675 $650 CFl Y0 $-1050 Y1 $360 Y2 360 Y3$360...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. WACC: 7.75% Year 0 1 2 3 4 CFS -$1,050 $675 $650 CFL -$1,050 $360 $360...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 7.75% 0 1 2 3 4 CF S -$1,025 $380 $380 $380 $380 CF...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? Interest rate: 10.00% Year 0 1 2 3 4 CFS -$1,000 $380 $380 $380 $380...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost WACC 11.75% 0 1 2 3 4 CFs...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT