In: Finance
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. WACC: 7.75% Year 0 1 2 3 4 CFS -$1,050 $675 $650 CFL -$1,050 $360 $360 $360 $360 I WANT ANSWER BUT NO USE EXCEL THANKS
Computation of IRR using Trial and Error method:
Project S:
Computation of NPV at discount rate of 17 %
Year |
PV Factor Computation |
PV Factor @ 17 % (F) |
Cash Flow (CS) |
PV (CS x F) |
0 |
1/ (1+0.17) ^0 |
1 |
-$1,050 |
-$1,050 |
1 |
1/ (1+0.17) ^1 |
0.85470085470086 |
675 |
576.9230769 |
2 |
1/ (1+0.17) ^2 |
0.73051355102637 |
650 |
474.8338082 |
NPV1 |
$1.7568851 |
As NPV is positive, let’s compute NPV at discount rate of 18 %.
Year |
PV Factor Computation |
PV Factor @ 18 % (F) |
Cash Flow (CS) |
PV (CS x F) |
0 |
1/ (1+0.18) ^0 |
1 |
-$1,050 |
-$1,050 |
1 |
1/ (1+0.18) ^1 |
0.84745762711864 |
675 |
572.0338983 |
2 |
1/ (1+0.18) ^2 |
0.71818442976156 |
650 |
466.8198793 |
NPV2 |
-$11.1462224 |
IRRS = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]
= 17 % + [$ 1.7568851 x (18 % - 17%)/ ($ 1.7568851 – (-$ 11.1462224))]
= 17 % + [($ 1.7568851 x 1 %)/ ($ 1.7568851 + $ 11.1462224)]
= 17 % + ($ 0.017568851/ $ 12.9031075)
= 17 % + 0.0013615984
= 17 % + 0.14 % = 17.14 %
Project L:
Computation of NPV at discount rate of 13 %
Year |
PV Factor Computation |
PV Factor @ 13 % (F) |
Cash Flow (CL) |
PV (CL x F) |
0 |
1/ (1+0.13) ^0 |
1 |
-$1,050 |
-$1,050 |
1 |
1/ (1+0.13) ^1 |
0.88495575221239 |
360 |
318.5840708 |
2 |
1/ (1+0.13) ^2 |
0.78314668337380 |
360 |
281.9328060 |
3 |
1/ (1+0.13) ^3 |
0.69305016227770 |
360 |
249.4980584 |
4 |
1/ (1+0.13) ^4 |
0.61331872767938 |
360 |
220.7947420 |
NPV1 |
$20.8096772 |
As NPV is positive, let’s compute NPV at discount rate of 14 %.
Year |
PV Factor Computation |
PV Factor @ 14 % (F) |
Cash Flow (CL) |
PV (CL x F) |
0 |
1/ (1+0.14) ^0 |
1 |
-$1,050 |
-$1,050 |
1 |
1/ (1+0.14) ^1 |
0.87719298245614 |
360 |
315.7894737 |
2 |
1/ (1+0.14) ^2 |
0.76946752847030 |
360 |
277.0083102 |
3 |
1/ (1+0.14) ^3 |
0.67497151620202 |
360 |
242.9897458 |
4 |
1/ (1+0.14) ^4 |
0.59208027737019 |
360 |
213.1488999 |
NPV2 |
-$1.0635704 |
IRR L = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]
= 13 % + [$ 20.8096772 x (14 % - 13%)/ ($ 20.8096772 – (-$ 1.0635704))]
= 13 % + [($ 20.8096772 x 1 %)/ ($ 20.8096772 + $ 1.0635704)]
= 13 % + ($ 0.208096772/ $ 21.8732476)
= 13 % + 0.009513757
= 13 % + 0.95 % = 13.95 %
Project S is preferable based on IRR rule decision as it has higher IRR.
Computation of NPV of both projects:
Year |
PV Factor Computation |
PV Factor @ 7.75 % (F) |
Cash Flow (CS) |
PV S (CS x F) |
Cash Flow (CL) |
PV L (CL xF) |
0 |
1/ (1+0.0775)0 |
1 |
-$1,050 |
-$1,050 |
-$1,050 |
-$1,050 |
1 |
1/ (1+0.0775)1 |
0.92807424593968 |
675 |
626.4501160 |
360 |
581.39221903 |
2 |
1/ (1+0.0775)2 |
0.86132180597650 |
650 |
559.8591739 |
360 |
482.21891474 |
3 |
1/ (1+0.0775)3 |
0.79937058559304 |
0 |
0 |
360 |
0 |
4 |
1/ (1+0.0775)4 |
0.74187525345061 |
0 |
0 |
360 |
0 |
NPV S |
$136.3092899 |
NPV L |
$13.61113377 |
NPV of Project S is $136.31 and that of Project L is $13.61
Choosing project on the basis of IRR will cause no value to forgone, as the preferred project S has higher NPV. There is no conflicting result between NPV and IRR decision rule for the two mutually exclusive projects.