Question

In: Finance

Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects...

Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. WACC: 7.75% Year 0 1 2 3 4 CFS -$1,050 $675 $650 CFL -$1,050 $360 $360 $360 $360 I WANT ANSWER BUT NO USE EXCEL THANKS

Solutions

Expert Solution

Computation of IRR using Trial and Error method:

Project S:

Computation of NPV at discount rate of 17 %

Year

PV Factor Computation

PV Factor @ 17 %

(F)

Cash Flow (CS)

PV (CS x F)

0

1/ (1+0.17) ^0

1

-$1,050

-$1,050

1

1/ (1+0.17) ^1

0.85470085470086

675

576.9230769

2

1/ (1+0.17) ^2

0.73051355102637

650

474.8338082

NPV1

     $1.7568851

As NPV is positive, let’s compute NPV at discount rate of 18 %.

Year

PV Factor Computation

PV Factor @ 18 %

(F)

Cash Flow (CS)

PV (CS x F)

0

1/ (1+0.18) ^0

1

-$1,050

-$1,050

1

1/ (1+0.18) ^1

0.84745762711864

675

572.0338983

2

1/ (1+0.18) ^2

0.71818442976156

650

466.8198793

                  NPV2

-$11.1462224

IRRS = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]

= 17 % + [$ 1.7568851 x (18 % - 17%)/ ($ 1.7568851 – (-$ 11.1462224))]

= 17 % + [($ 1.7568851 x 1 %)/ ($ 1.7568851 + $ 11.1462224)]

= 17 % + ($ 0.017568851/ $ 12.9031075)

= 17 % + 0.0013615984

= 17 % + 0.14 % = 17.14 %

Project L:

Computation of NPV at discount rate of 13 %

Year

PV Factor Computation

PV Factor @ 13 %

(F)

Cash Flow (CL)

PV (CL x F)

0

1/ (1+0.13) ^0

1

-$1,050

-$1,050

1

1/ (1+0.13) ^1

0.88495575221239

360

318.5840708

2

1/ (1+0.13) ^2

0.78314668337380

360

281.9328060

3

1/ (1+0.13) ^3

0.69305016227770

360

249.4980584

4

1/ (1+0.13) ^4

0.61331872767938

360

220.7947420

NPV1

$20.8096772

As NPV is positive, let’s compute NPV at discount rate of 14 %.

Year

PV Factor Computation

PV Factor @ 14 % (F)

Cash Flow (CL)

PV (CL x F)

0

1/ (1+0.14) ^0

1

-$1,050

-$1,050

1

1/ (1+0.14) ^1

0.87719298245614

360

315.7894737

2

1/ (1+0.14) ^2

0.76946752847030

360

277.0083102

3

1/ (1+0.14) ^3

0.67497151620202

360

242.9897458

4

1/ (1+0.14) ^4

0.59208027737019

360

213.1488999

                  NPV2

-$1.0635704

IRR L = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]

= 13 % + [$ 20.8096772 x (14 % - 13%)/ ($ 20.8096772 – (-$ 1.0635704))]

= 13 % + [($ 20.8096772 x 1 %)/ ($ 20.8096772 + $ 1.0635704)]

= 13 % + ($ 0.208096772/ $ 21.8732476)

= 13 % + 0.009513757

= 13 % + 0.95 % = 13.95 %

Project S is preferable based on IRR rule decision as it has higher IRR.

Computation of NPV of both projects:

Year

PV Factor Computation

PV Factor @ 7.75 % (F)

Cash Flow (CS)

PV S (CS x F)

Cash Flow (CL)

PV L (CL xF)

0

1/ (1+0.0775)0

1

-$1,050

-$1,050

-$1,050

-$1,050

1

1/ (1+0.0775)1

0.92807424593968

675

626.4501160

360

581.39221903

2

1/ (1+0.0775)2

0.86132180597650

650

559.8591739

360

482.21891474

3

1/ (1+0.0775)3

0.79937058559304

0

0

360

0

4

1/ (1+0.0775)4

0.74187525345061

0

0

360

0

      NPV S

$136.3092899

    NPV L

$13.61113377

NPV of Project S is $136.31 and that of Project L is $13.61

Choosing project on the basis of IRR will cause no value to forgone, as the preferred project S has higher NPV. There is no conflicting result between NPV and IRR decision rule for the two mutually exclusive projects.


Related Solutions

A company is considering Projects S and L, whose cash flows are shown below. These projects...
A company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates other methods. If the decision is made by choosing the project with the higher IRR, how much, if any, value will be forgone, i.e., what's the: NPV and IRR of the chosen project(s). What is the Payback period, discounted payback period, and...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. WACC: 7.75 CFs Y0: $-1050 Y1 $675 $650 CFl Y0 $-1050 Y1 $360 Y2 360 Y3$360...
Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects...
Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. r: 7.75% Year 0 1 2 3 4 CFS −$1,050 $675 $650 CFL −$1,050 $360 $360...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 7.75% 0 1 2 3 4 CF S -$1,025 $380 $380 $380 $380 CF...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? Interest rate: 10.00% Year 0 1 2 3 4 CFS -$1,000 $380 $380 $380 $380...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost WACC 11.75% 0 1 2 3 4 CFs...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT