In: Finance
Year |
Project Alpha |
Project Beta |
1 |
15,000 |
10,200 |
2 |
15,000 |
10,200 |
3 |
15,000 |
10,200 |
4 |
15,000 |
10,200 |
5 |
15,000 |
10,200 |
Required:
Project Alpha
IRR = 20% (IRR is the rate at which NPV = 0)
NPV = $6,636
MIRR = 17.19 %
Present Value = Cash Flow / (1+ Discount Rate) ^ T, where T is the year of cash flow
For example PV of Cash flow for 4th year = 15000 / (1+14%)^4 = 15000/ 1.689 = $8881.20
Similarly other PV are calculated
Future Value is calculated using with the re-investment rate of 14% or the cost of capital = Cash Flow X (1+ Reinvestment Rate) ^(T- t), where T-t is the time for reinvestment
Thus FV of 2nd year cash flow can be calculated as 15000 x (1+14%) ^(5-2) = 15000 x (1.140)^3
= 15000 X 1.481 = 22,223.16
Similarly FV is calculated for other periods as well.
NPV = Sum of present value of all cash flows including investment ( which is taken as -ive sign)
IRR is calculated using excel function IRR and putting all values of cash flows
MIRR = Modified Internal Rate of Return
= (Sum of FV of positive cash flows / Sum of PV of all negative cash flows) ^ (1/n) -1
= (99152 / 44860)^(1/5) -1 = (2.21^0.5) - 1 = 17.14%
Year | Project Alpha Cash Flows | Project Alpha - PV of Cash Flows (Disc rate =14%) | Project Alpha - FV of Positive Cash Flows (Rate =14%) |
0 | (44,860) | (44,860.00) | |
1 | 15,000 | 13,157.89 | $25,334.40 |
2 | 15,000 | 11,542.01 | $22,223.16 |
3 | 15,000 | 10,124.57 | $19,494.00 |
4 | 15,000 | 8,881.20 | $17,100.00 |
5 | 15,000 | 7,790.53 | $15,000.00 |
IRR | 20.00% | ||
NPV | 6,636 | ||
Future Value of Positive Cash flows | 99,152 | ||
MIRR = (FVCF/ PVCF) ^(1/n) -1 |
17% |
Project Beta
IRR = 15% (IRR is the rate at which NPV = 0)
NPV = $ 817
MIRR = 14.54 %
Project Alpha which has higher IRR, NPV and MIRR should be selected
For IRR, accept reject rule is - Projects with IRR higher than minimum required rate are accepted
For NPV, accept reject rule is, Projects with positive NPV are selected