Question

In: Finance

Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital...

  1. Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital budget. The projects are independent. The cash outlay for the Project Alpha is $44,860 and that for the Project Beta is $34,200. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows:

Year

Project Alpha

Project Beta

1

15,000

10,200

2

15,000

10,200

3

15,000

10,200

4

15,000

10,200

5

15,000

10,200

Required:

  1. Calculate the IRR for each project.

  1. Calculate the NPV, for each project

  1. Calculate the MIRR for each project

  1. Indicate the correct accept-reject decision for each.

Solutions

Expert Solution

Project Alpha

IRR = 20% (IRR is the rate at which NPV = 0)

NPV = $6,636

MIRR = 17.19 %

Present Value = Cash Flow / (1+ Discount Rate) ^ T, where T is the year of cash flow

For example PV of Cash flow for 4th year = 15000 / (1+14%)^4 = 15000/ 1.689 = $8881.20

Similarly other PV are calculated

Future Value is calculated using with the re-investment rate of 14% or the cost of capital = Cash Flow X (1+ Reinvestment Rate) ^(T- t), where T-t is the time for reinvestment

Thus FV of 2nd year cash flow can be calculated as 15000 x (1+14%) ^(5-2) = 15000 x (1.140)^3

= 15000 X 1.481 = 22,223.16

Similarly FV is calculated for other periods as well.

NPV = Sum of present value of all cash flows including investment ( which is taken as -ive sign)

IRR is calculated using excel function IRR and putting all values of cash flows

MIRR = Modified Internal Rate of Return

= (Sum of FV of positive cash flows / Sum of PV of all negative cash flows) ^ (1/n) -1

= (99152 / 44860)^(1/5) -1 = (2.21^0.5) - 1 = 17.14%

Year Project Alpha Cash Flows Project Alpha - PV of Cash Flows (Disc rate =14%) Project Alpha - FV of Positive Cash Flows (Rate =14%)
0            (44,860)              (44,860.00)
1             15,000                13,157.89 $25,334.40
2             15,000                11,542.01 $22,223.16
3             15,000                10,124.57 $19,494.00
4             15,000                  8,881.20 $17,100.00
5             15,000                  7,790.53 $15,000.00
IRR 20.00%
NPV                       6,636
Future Value of Positive Cash flows                       99,152
MIRR =
(FVCF/ PVCF) ^(1/n) -1
17%

Project Beta

IRR = 15% (IRR is the rate at which NPV = 0)

NPV = $ 817

MIRR = 14.54 %

Project Alpha which has higher IRR, NPV and MIRR should be selected

For IRR, accept reject rule is - Projects with IRR higher than minimum required rate are accepted

For NPV, accept reject rule is, Projects with positive NPV are selected  


Related Solutions

Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital budget. The projects are independent. The cash outlay for the Project Alpha is $44,860 and that for the Project Beta is $34,200. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Project Alpha Project Beta 1 15,000 10,200 2 15,000 10,200 3 15,000 10,200 4 15,000 10,200 5 15,000 10,200 Required: Calculate the IRR for each project...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital budget. The projects are independent. The cash outlay for the Project Alpha is $44,860 and that for the Project Beta is $34,200. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Project Alpha Project Beta 1 15,000 10,200 2 15,000 10,200 3 15,000 10,200 4 15,000 10,200 5 15,000 10,200 Required: Calculate the IRR for each project....
A company has two projects: Beta and Gamma. Project Beta Project Beta is an investment in...
A company has two projects: Beta and Gamma. Project Beta Project Beta is an investment in machinery. Initial investment paid was £20,000 at the start of the project and it has been estimated there will be nil scrap value at the end. Cost of capital has been estimated as 25%. Year Cash inflows (£) 1 4,000 2 8,000 3 14,000 4 20,000 5 18,000 Project Gamma Project Gamma is another investment in machinery. It has the following information: Yearly cash...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$6,000 $2,000 $2,000 $2,000 $2,000 $2,000 Project N -$18,000 $5,600 $5,600 $5,600 $5,600 $5,600 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$12,000 $4,000 $4,000 $4,000 $4,000 $4,000 Project N -$36,000 $11,200 $11,200 $11,200 $11,200 $11,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...
eBook A firm with a 13% WACC is evaluating two projects for this year's capital budget....
eBook A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$3,000 $1,000 $1,000 $1,000 $1,000 $1,000 Project N -$9,000 $2,800 $2,800 $2,800 $2,800 $2,800 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers...
eBook A firm with a 14% WACC is evaluating two projects for this year's capital budget....
eBook A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$21,000 $7,000 $7,000 $7,000 $7,000 $7,000 Project N -$63,000 $19,600 $19,600 $19,600 $19,600 $19,600 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$3,000 $1,000 $1,000 $1,000 $1,000 $1,000 Project N -$9,000 $2,800 $2,800 $2,800 $2,800 $2,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$12,000 $4,000 $4,000 $4,000 $4,000 $4,000 Project N -$36,000 $11,200 $11,200 $11,200 $11,200 $11,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
Capital budgeting criteria A firm with a 13% WACC is evaluating two projects for this year's...
Capital budgeting criteria A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$15,000 $5,000 $5,000 $5,000 $5,000 $5,000 Project N -$45,000 $14,000 $14,000 $14,000 $14,000 $14,000 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M $ Project N $ Calculate IRR for each project. Round your answers...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT