During 2020, Sheridan Company started a construction job with a
contract price of $1,376,000. The job was completed in 2022. The
following information is available. The contract is
non-cancellable.
2020
2021
2022
Costs incurred to date
$344,000
$709,500
$920,200
Estimated costs to complete
516,000
236,500
0
Billings to date (non-refundable)
258,000
774,000
1,376,000
Collections to date
232,200
696,600
1,225,500
Calculate the amount of gross profit to be recognized each year,
assuming the percentage-of-completion method is used.
(Enter negative amounts using...