In: Accounting
Owen Company manufactures bicycles and tricycles. For both products, materials are added at the beginning of the production process, and conversion costs are incurred uniformly. Owen Company uses the FIFO method to compute equivalent units. Production and cost data for the month of March are as follows.
|
|
Percentage |
|||
Work in process units, March 1 | 190 | 80 | % | ||
Units started into production | 1,380 | ||||
Work in process units, March 31 | 300 | 40 | % |
|
||
Work in process units, March 1 | $19,070 | |
Direct materials | 49,680 | |
Direct labor | 25,900 | |
Manufacturing overhead | 29,810 |
|
|
Percentage |
|||
Work in process units, March 1 | 140 | 75 | % | ||
Units started into production | 990 | ||||
Work in process units, March 31 | 60 | 25 | % |
|
||
Work in process units, March 1 | $6,460 | |
Direct materials | 30,690 | |
Direct labor | 14,300 | |
Manufacturing overhead | 20,000 |
Calculate the equivalent units of production for materials and conversion costs for both the bicycles and the tricycles.
Materials |
Conversion Costs |
|||
Equivalent Units of bicycles | ||||
Equivalent Units of tricycles |
eTextbook and Media
Calculate the unit costs of production for materials and conversion costs for both the bicycles and the tricycles.
Materials |
Conversion Costs |
|||
Unit costs of bicycles | ||||
Unit costs of tricycles |
eTextbook and Media
Calculate the assignment of costs to units transferred out and
in process at the end of the accounting period for both the
bicycles and the tricycles.
Bicycles
Costs accounted for: |
||
Transferred out |
$ |
|
Work in process, March 31 |
||
Materials |
$ |
|
Conversion costs |
||
Total costs |
$ |
Tricycles
Costs accounted for: |
||
Transferred out |
$ |
|
Work in process, March 31 |
||
Materials |
$ |
|
Conversion costs |
||
Total costs |
$ |
eTextbook and Media
Prepare a production cost report for the month of March for the bicycles only.
OWEN COMPANY |
||||||
Equivalent Units |
||||||
Quantities |
Physical |
|
Conversion |
|||
Units to be accounted for |
||||||
Work in process, March 1 |
||||||
Started into production |
||||||
Total units |
||||||
Units accounted for |
||||||
Completed and transferred out |
||||||
Work in process, March 1 |
||||||
Started and completed |
||||||
Work in process, March 31 |
||||||
Total units |
||||||
|
|
Conversion |
|
|||
Unit costs |
||||||
Costs in March |
$ |
$ |
$ |
|||
Equivalent units |
||||||
Unit costs |
$ |
$ |
$ |
|||
Costs to be accounted for |
||||||
Work in process, March 1 |
$ |
|||||
Started into production |
||||||
Total costs |
$ |
|||||
Cost Reconciliation Schedule |
||||||
Costs accounted for |
||||||
Transferred out |
||||||
Work in process, March 1 |
$ |
|||||
Conversion costs to complete beginning inventory |
||||||
Started and completed |
$ |
|||||
Work in process, March 31 |
||||||
Materials |
||||||
Conversion costs |
||||||
Total costs |
$ |
PART 1 | ||||||||||||
Material | Conversion | |||||||||||
Equivalent Units Of Bicycles | 1380 | 1238 | ||||||||||
Equivalent Units of Tricycles | 990 | 980 | ||||||||||
PART 2 | ||||||||||||
Material | Conversion | |||||||||||
Unit CostOf Bicycles | $36 | $45 | ||||||||||
Unit cost of Tricycles | $31 | $35 | ||||||||||
PART 3 | ||||||||||||
Costs Accounted For - Bicycles | Costs Accounted For - Tricycles | |||||||||||
Transferred out | $1,08,260 | Transferred out | $69,065 | |||||||||
Work-In-Process March 31 | Work-In-Process March 31 | |||||||||||
Materials | $10,800 | Materials | $1,860 | |||||||||
Conversion Cost | $5,400 | Conversion Cost | $525 | |||||||||
Total Costs | $1,24,460 | Total Costs | $71,450 | |||||||||
PART 4 | ||||||||||||
Bicycles | Tricycles | |||||||||||
Quantities | Physical Units | % Completed | Materials | % Completed | Conversion Costs | Quantities | Physical Units | % Completed | Materials | % Completed | Conversion Costs | |
Units to be Accounted For: | Units to be Accounted For: | |||||||||||
Work-In-Process March 1 | 190 | Work-In-Process March 1 | 140 | |||||||||
Started into Production | 1380 | Started into Production | 990 | |||||||||
Total Units to Account For | 1570 | Total Units to Account For | 1130 | |||||||||
Units Accounted For | Units Accounted For | |||||||||||
Completed & Transferred Out | Completed & Transferred Out | |||||||||||
Work-In-Process March 1 | 190 | 0% | 0 | 20% | 38 | Work-In-Process March 1 | 140 | 0% | 0 | 25% | 35 | |
Started & Completed | 1080 | 100% | 1080 | 100% | 1080 | Started & Completed | 930 | 100% | 930 | 100% | 930 | |
Work-In-Process March 31 | 300 | 100% | 300 | 40% | 120 | Work-In-Process March 31 | 60 | 100% | 60 | 25% | 15 | |
Total Units Accounted For | 1570 | 1380 | 1238 | Total Units Accounted For | 1130 | 990 | 980 | |||||
Unit Cost Analysis Schedule - FIFO | Unit Cost Analysis Schedule - FIFO | |||||||||||
Materials | Conversion Costs | Total Costs | Materials | Conversion Costs | Total Costs | |||||||
Unit Costs | Unit Costs | |||||||||||
Costs in March | $49,680 | $55,710 | $1,05,390 | Costs in March | $30,690 | $34,300 | $64,990 | |||||
Equivalent Units | 1380 | 1238 | Equivalent Units | 990 | 980 | |||||||
Cost per Equivalant Unit | $36 | $45 | $81 | Cost per Equivalant Unit | $31 | $35 | $66 | |||||
Costs to be Accounted For | Costs to be Accounted For | |||||||||||
Work-In-Process March 1 | $19,070 | Work-In-Process March 1 | $6,460 | |||||||||
Started into Production | $1,05,390 | Started into Production | $64,990 | |||||||||
Total Costs | $1,24,460 | Total Costs | $71,450 | |||||||||
NOTE: IN FIFO Method only current period cost is divided by equivalent units to arrive at cost per equivalent unit. | NOTE: IN FIFO Method only current period cost is divided by equivalent units to arrive at cost per equivalent unit. | |||||||||||
Cost Reconcillation Schedule | Cost Reconcillation Schedule | |||||||||||
Costs Accounted For | Costs Accounted For | |||||||||||
Transferred out | Transferred out | |||||||||||
Work-In-Process March 1 | $19,070 | Work-In-Process March 1 | $6,460 | |||||||||
Conversion Costs to complete Beginning Inventory (38*45) | $1,710 | Conversion Costs to complete Beginning Inventory (35 * $35) | $1,225 | |||||||||
Started & Completed (1080 * $81) | $87,480 | $1,08,260 | Started & Completed (930 * $66) | $61,380 | $69,065 | |||||||
Work In Process Inventory March 31 | Work In Process Inventory March 31 | |||||||||||
Materials (300 * $36) | $10,800 | Materials (60 * $31) | $1,860 | |||||||||
Conversion Costs (120 * $45) | $5,400 | $16,200 | Conversion Costs (15 * $35) | $525 | $2,385 | |||||||
Total Cost Accounted For | $1,24,460 | Total Cost Accounted For | $71,450 | |||||||||