Question

In: Statistics and Probability

Review, analyze, and complete the Chase Manhattan Bank Case Study below. The workload in many areas...

Review, analyze, and complete the Chase Manhattan Bank Case Study below. The workload in many areas of bank operations has the characteristics of a nonuniform distribution with respect to time of day. For example, at Chase Manhattan Bank in New York, the number of domestic money transfer requests received from customers, if plotted against time of day, would appear to have the shape of an inverted U curve with the peak around 1 P.M. For efficient use of resources, the personnel available should, therefore, vary correspondingly. A variable capacity can be achieved effectively by employing part-time personnel. Because part-timers are not entitled to all the fringe benefits, they are often more economical than full-time employees. Other considerations, however, may limit the extent to which part-time people can be hired in a given department. The problem is to find an optimum workforce schedule that would meet personnel requirements at any given time and also be economical. Some of the factors affecting personnel assignment are listed here: 1. By corporate policy, part-time personnel hours are limited to a maximum of 40% of the day’s total requirement. 2. Full-time employees work for 8 hours (1 hour for lunch included) per day. Thus, a full-timer’s productive time is 35 hours per week. 3. Part-timers work for at least 4 hours per day but less than 8 hours and are not allowed a lunch break. 4. Fifty percent of the full-timers go to lunch between 11 A.M. and noon, and the remaining 50% go between noon and 1 P.M. 5. The shift starts at 9 A.M. and ends at 7 P.M. (i.e., overtime is limited to 2 hours). Any work left over at 7 P.M. is considered holdover for the next day. 6. A full-time employee is not allowed to work more than 5 hours overtime per week. He or she is paid at the normal rate for overtime hours—not at one-and-a-half times the normal rate applicable to hours in excess of 40 per week. Fringe benefits are not applied to overtime hours. In addition, the following costs are pertinent: 1. The average cost per full-time personnel hour (fringe benefits included) is $10.11. 2. The average cost per overtime personnel hour for full-timers (straight rate excluding fringe benefits) is $8.08. 3. The average cost per part-time personnel hour is $7.82. The personnel hours required, by hour of day, are given in the following Table. TABLE: Workforce Requirements NUMBER OF PERSONNEL TIME PERIOD REQUIRED 9–10 A.M. 14 10–11 25 11–12 26 12–1 P.M. 38 1–2 55 2–3 60 3–4 51 4-5 29 5-6 14 6-7 9 The bank’s goal is to achieve the minimum possible personnel cost subject to meeting or exceeding the hourly workforce requirements as well as the constraints on the workers listed earlier.

Discussion Questions:

1. What is the minimum-cost schedule for the bank?

Solutions

Expert Solution

Given data

Workforce requirements

NUMBER OF PERSONNEL TIME PERIOD REQUIRED
9–10 A.M. 14
10–11 25
11–12 26
12–1 P.M. 38
1–2 55
2–3 60
3–4 51
4-5 29
5-6 14
6-7 9

1)

Initially  Develop a grid in Excel with the time periods ( 9:00 to 10:00, 10:00 to 11.00, etc.) down the left side of the grid and all possible full-time and part-time shifts that can be worked across the top. put an "X" in the grid to indicate the times that each of the possible shifts works. all full-time employees start at 9:00. for the full-time employees, half of the employees take lunch from 11"00 A.M to noon and the remainder of them takes lunch from noon to 1:00 P.M. ( hint: there 3 possible full-time shifts and 22 possible part-time shifts.)
   2)

Using the grid from (1), formulate the 10 constraints corresponding to the time periods.

  • If that shift works in a given time period, make the coefficient equal to 1.0
  • If the shift doesn't work in a given time period, make the coefficient equal to 0.0
  • For the lunch periods of full-time employees, make the coefficients equal to 0.5
  • The number of employees needed for each time period is given in the problem in the case.

  3)

The final (11th) constraint states that the total number of hours worked by the part-time employees is limited to 40 % of the total hours worked by both full-time and part-time employees. as stated in the problem, each full-time employee works 7 hours out of an 8 hour day.

4)

Disregard the 6th factor(constraint) listed in the case.

5)

The coefficients in the objective function is the hourly wage multiplied by hours worked. assume that full-time employees are paid for lunch ( they are paid for 8 hours but only work 7 hours).

6)

Using the linear programming module in QM software, input the problems (25 decision variables and 11 constraints) and solve the problem.

7)

Copy the formulation from the linear programming module and paste it into the integer programming module. verify that all of the constraints copy over correctly! solve the problem. if your answer for the integer program has no full-time employees, reverse the sign in the 11th constraint.

Requirements:
Grid from (1)
solution output from a linear programming module
  solution output from linear programming module solution and the integer program solution.
                                           
Employee Type  Shift Worked   Linear Program Solution  Integer Program solution
  Full time          9:00am to 5:00pm  
  Full time          9:00am to 6:00pm
  Full time           9:00am to 7:00pm
  part time          9:00am to 1:00pm
  part time          9:00am to 2:00pm
  part time          9:00am to 3:00pm
  part time          9:00am to 4:00pm
  part time          10:00am to 2:00pm
  part time          10:00am to 3:00pm
  part time          10:00am to 4:00pm
  part time          10:00am to 5:00pm
  part time          11:00am to 3:00pm
  part time          11:00am to 4:00pm
  part time          11:00am to 5:00pm
  part time          11:00am to 6:00pm
  part time          Noon to 4:00 pm
  part time          Noon to 5:00 pm
  part time          Noon to 6:00 pm
  part time          Noon to 7:00 pm
  part time          1:00pm to 5:00pm
  part time          1:00pm to 6:00pm
  part time          1:00pm to 7:00pm
  part time          2:00pm to 6:00pm
  part time          2:00pm to 7:00pm
  part time          3:00pm to 7:00pm
  Total Cost  

1. What is the minimum-cost schedule for the bank?

Objective Function:Minimize total personnel cost: $80.88F + $31.28(P1+P2+P3+P4+P5+P6+P7) + $16.16FO

Let:

Ffull-time tellers where F≤35FO

full-time tellers working OT where FO ≤ 5P1

part-timers (PT) start 9am, leave between 1pmP2

PT start at 10am, leave between 2pmP3

PT start at 11am, leave between 3pmP4

PT start at 12pm, leave between 4pmP5

PT start at 1pm, leave between 5pmP6

PT start at 2pm, leave at 6pm

Limitations:Part time workers cannot exceed 40% of total hours required each day,

which is the sum of the tellers needed each hour

4 (P1 + P2 + P3 + P4 + P5 + P6 + P7) ≥ 0.40 (14 + 25 + 26 + 38 + 55 + 60 + 51 + 29 + 14 + 19)

4P1+4P2+4P3+4P4+4P5+4P6+4P7 ≤ .40 (331)

Variables FP1P2P3P4P5P6P7FO

Values 29.270.000.0011.3721.730.000.000.000.00

Cost$ 80.88 $ 31.28 $ 31.28 $ 31.28 $ 31.28 $ 31.28 $ 31.28 $ 31.28 $ 16.16

Shift Covers Time Period (1=yes, 0=no         

Constraints                                                                                                                                                                                                  LHS

9am-10am

1

1

1

29.27

10am-11a

1

1

1

29.27

11am-12p

0.5

1

1

1

26.00

12pm-1pm

0.5

1

1

1

1

47.73

1pm-2pm

1

1

1

1

1

62.37

2pm-3pm

1

1

1

1

1

62.37

3pm-4pm

1

1

1

1

1

51.00

4pm-5pm

1

1

1

1

29.27

5pm-6pm

1

1

1

29.27

6pm-7pm

1

1

29.27

Max full

1

29.27

Total PT hour

4

4

4

4

4

4

4

132.40

Total Cost of Labor$ 3,402.46

If you have any doubts please comment and please don't dislike.

PLEASE GIVE ME A LIKE. ITS VERY IMPORTANT FOR ME.


Related Solutions

The workload in many areas of bank operations has the characteristics of a nonuniform distribution with...
The workload in many areas of bank operations has the characteristics of a nonuniform distribution with respect to time of day. For example, at Chase Manhattan Bank in New York, the number of domestic money transfer requests received from customers, if plotted against time of day, would appear to have the shape of an inverted U curve with the peak around 1 P.M. For efficient use of resources, the personnel available should, therefore, vary correspondingly. A variable capacity can be...
Read and review chapter 31 Analyze the following case study and answer the question bellow CASE...
Read and review chapter 31 Analyze the following case study and answer the question bellow CASE STUDY Mrs. Angstrom is an 83-year-old patient who was admitted to the hospital after she fell outside her home and broke her hip. She has been living alone in her apartment since her husband died 4 years ago. Mrs. Angstrom has no long-term history of mental illness, but she has recently shown signs of cognitive impairment and dementia, according to her neighbor Jeanine Finch,...
CASE STUDY #1 Review the case below and answer the following questions. This should be original...
CASE STUDY #1 Review the case below and answer the following questions. This should be original work, no references or information from online. Please be detailed. 38-year-old female with excessive thirst, frequent urination, and weight loss. History: Cindy Mallon, an 38 year old Caucasian female in previously good health, she has noticed that in the past month, she is increasingly thirsty. She gets up several times a night to urinate, and finds herself gulping down glassfuls of water. At the...
Write a review for the article below Minimum Wages and Employment: A Case Study of the...
Write a review for the article below Minimum Wages and Employment: A Case Study of the Fast-Food Industry in New Jersey and Pennsylvania (CarD and Krueger)
Review the case study and complete the questions to increase your knowledge of Fundamentals content. Copy...
Review the case study and complete the questions to increase your knowledge of Fundamentals content. Copy and paste the questions into a document to type your answers. Copy and paste the questions and answers back into messaging to your coach. You coach will provide you with feedback on your answers. A 70-year-old female has been admitted to the hospital. The client has had nausea and vomiting for the past three days. Upon admission the client is slightly confused and weak....
Case Study: The subway is expected to run the whole length of Manhattan. It will eventually...
Case Study: The subway is expected to run the whole length of Manhattan. It will eventually connect with the already existing subway, East Side subway. The second avenue subway will also connect with the railroad at the 125th street in the north and run to the southern side to reach the financial district. However, phase one of the project was opened for the public in January 2017. There is a plan to include 16 new underground stations in the subway....
In a 2-3 page paper, complete the case below and submit to instructor. Review the income...
In a 2-3 page paper, complete the case below and submit to instructor. Review the income statement for Uden Supply Company and answer the following: Describe the purpose of analytical procedures performed in the planning stage of the audit. Uden Supply has projected its 2004 gross profit at 31% of sales despite expectation for some shrinkage in margins. On the basis of Uden's operating performance in years 2001 - 2003 project your best guess for 2004. Project 2004 based on...
complete a brief case analysis based on the article posted below. analyze the external environment as...
complete a brief case analysis based on the article posted below. analyze the external environment as well as the internal environment. http://fortune.com/2018/02/20/kfc-still-shut-uk/
To complete this assignment, review the following Web resource: A Critical Access Hospital Case Study: Idaho...
To complete this assignment, review the following Web resource: A Critical Access Hospital Case Study: Idaho Flex Program: Evaluation 2010 Where not all pertinent information is given in the case itself, search for that information through the South University Online Library or perform a Web search for the required information. Note: Do not search for information beyond the date of the case. For the situational analysis, you are encouraged to provide a visual presentation of data in your situational analysis...
Bank of America and JPMorgan Chase are major competitors to Wells Fargo. Please (1)analyze their strategies,...
Bank of America and JPMorgan Chase are major competitors to Wells Fargo. Please (1)analyze their strategies, (2)core competencies, and (3)competitive response for both Bank of America and JPMorgan Chase.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT