In: Finance
A three-year project will cost $150,000 to construct. This will be depreciated straight-line to zero over the three-year life. The project is expected to generate sales of $450,000 per year. It has annual variables costs of $200,000 and annual fixed costs of $100,000 per year. The appropriate tax rate is 25 percent and the required rate of return on the project is 16 percent. Assume that a salvage company will pay $60,000 (before taxes) for the assets at the end of year 3. The project also has an initial net working capital requirement of $40,000, which is fully recoverable when the project ends. Note that the project only depreciates the $150,000 initial cost. The salvage value is excluded from depreciation. What is the project’s net present value (NPV)?
Calculation of NPV of the Project | ||||
Particulars | 0 | 1 | 2 | 3 |
Initial Investment | ||||
Cost of Project | -150000 | |||
Investment in net working capital | -40000 | |||
Net Investment (A) | -190000 | |||
Operating Cash Flows | ||||
Annual Sales (B) | 450000 | 450000 | 450000 | |
Variable Costs (C ) | 200000 | 200000 | 200000 | |
Fixed Costs (D) | 100000 | 100000 | 100000 | |
Depreciation (E ) ($150,000 / 3 years) |
50000 | 50000 | 50000 | |
Profit Before Tax (F = B-C-D-E) | 100000 | 100000 | 100000 | |
Tax @ 25% (G = F*25%) | 25000 | 25000 | 25000 | |
Profit After Tax (H = F-G) | 75000 | 75000 | 75000 | |
Add back depreciation (I) | 50000 | 50000 | 50000 | |
Net Operating Cash Flows (J = H+I) | 125000 | 125000 | 125000 | |
Terminal Value | ||||
Salvage Value (K) | 60000 | |||
Tax @25% (L = K*25%) | 15000 | |||
After tax Salvage Value (M = K-L) | 45000 | |||
Recovery of net working capital (N) | 40000 | |||
Net Terminal Value (O = M+N) | 85000 | |||
Total Cash Flows (P = A+J+O) | -190000 | 125000 | 125000 | 210000 |
Discount Factor @16% (Q) 1/(1+16%)^n n=0,1,2,3 |
1 | 0.862068966 | 0.743162901 | 0.640657674 |
Discounted Cash Flows (R = P*Q) | -190000 | 107758.6207 | 92895.36266 | 134538.1114 |
NPV of the Project | 145192.0948 | |||
Therefore, NPV of the project is $145,192.09 |