In: Finance
A three-year project will cost $150,000 to construct. This will be depreciated straight line to zero over the three-year life. The project is expected to generate sales of $450,000 per year. It has annual variables costs of $200,000 and annual fixed costs of $100,000 per year. The appropriate tax rate is 25 percent and the required rate of return on the project is 16 percent. Assume that a salvage company will pay $60,000 (before taxes) for the assets at the end of year 3. The project also has an initial net working capital requirement of $40,000, which is fully recoverable when the project ends. Note that the project only depreciates the $150,000 initial cost. The salvage value is excluded from depreciation. What is the project’s net present value (NPV)?
> Formula
NPV = Present Value of Cash inflow (PVCI) - Present Value of Cash outflow (PVCO)
> Calculation
PVCO = Construction Cost + Working capital requirement
= 150000 + 40000
= 190000
PVCI
Particulars | Year 1 | Year 2 | Year 3 |
Sales | 450000 | 450000 | 450000 |
Less: Variable Cost | ( 200000 ) | ( 200000 ) | ( 200000 ) |
Less: Fixed Cost | ( 100000 ) | ( 100000 ) | ( 100000 ) |
Less: Depreciation [150000 / 3 years ] |
( 50000 ) | ( 50000 ) | ( 50000 ) |
Profit before tax | 100000 | 100000 | 100000 |
Less: Tax @ 25% | (25000) | (25000) | (25000) |
Profit After Tax | 75000 | 75000 | 75000 |
Add: Depreciation | 50000 | 50000 | 50000 |
Cashflow after tax | 125000 | 125000 | 125000 |
Add: Salvage ( 1 - Tax rate) |
60000 * ( 1 - 0.25) = 45000 |
||
Add: Working capital | 40000 | ||
Cash Inflow | 125000 | 125000 | 210000 |
PV Factor @ 16% | 0.8621 | 0.7432 | 0.6407 |
Present Value of Cash inflow | 107762.5 | 92900 | 134547 |
PVCI = Sum of Present Value of Cash inflow
= 335210
NPV = 335210 - 190000
= $ 145210 Answer
Hope you understand the solution.