Calculate the MRR in a drilling process that is done with a 2 1 4 -...

Calculate the MRR in a drilling process that is done with a 2 1 4 - inches radius drill bit, in one piece whose drilling depth is H = 5 3 8 inches and it takes 1/2 hr. Keep in mind that the perforation is not through the workpiece and that the conical tip of the hole has a height of ½ inch.

Solutions

Expert Solution

Data:

Hole depth, Lh = 5 3/8 = 5.375 in , Drill dia / hole dia, D = 2.25in,                                                

Cutting time = 0.5 hr = 30 min    

Soln:

Length of cut, Lc = 5 3/8 + 1/2 = 5.875 in

Cycle time, Tc = Lc / (f * N)

i.e., (f*N) = Lc / Tc = 5.875 / 30 = 0.196 in /min

Now, The material removal rate is MRR = (?D2 / 4) (f*N)

MRR =   (?*2.252 / 4) (0.196) =0.78 in3/min

MRR = 0.78 in3/min OR 0.013 in3/s


Related Solutions

4). (a). Calculate an expression for the work done during an isothermal, reversible expansion for a...
4). (a). Calculate an expression for the work done during an isothermal, reversible expansion for a gas which is described using the van der Waals equation of state. (b). The van der Waals constants for a gas are a = 506.5 kPa L2 mol2 and b = 6.0x10−2 L mol−1. Determine the work done by 2.0 moles of a gas that expands from 1.5 L to 10 L at 325 K. (c). The a constant is attributed to attractive forces...
Calculate the entropy of the process of freezing of benzene under 1 atm pressure in 2...
Calculate the entropy of the process of freezing of benzene under 1 atm pressure in 2 cases a. Reversible solidification at 50C knowing the freezing temperature of benzene is -2370 cal/mol. b. Non-reversible freezing condensation at -50C. Knowing the heat capacity of solid and liquid benzene is 30,3 and 29,3 cal/mol.K espectively.)
Which role does Gel Strength play in the drilling process?
Which role does Gel Strength play in the drilling process?
SE-FamilySize 1 1 4 3 2 4 2 3 4 2 4 1 4 2 2...
SE-FamilySize 1 1 4 3 2 4 2 3 4 2 4 1 4 2 2 4 5 4 5 4 4 2 4 3 1 2 3 5 5 5 Make a confidence interval. Be sure you show all the steps you took. Include a screen shot of any applet you used in your calculations. 2. Choose a confidence level (1 – α). 3. What is xbar? 4. What is s? 5. What is t? (Show a screen shot...
4. The CPI in year 1 = 120, the CPI in Year 2 = 144. Calculate...
4. The CPI in year 1 = 120, the CPI in Year 2 = 144. Calculate the amount of inflation or deflation. Why is this important?
12. Calculate the maximum work to be done in the cell: Al (s) + Ni^2+ (ac)...
12. Calculate the maximum work to be done in the cell: Al (s) + Ni^2+ (ac) --> Al^3+ (ac) + Ni (s), if 15.8g of Al (26.98g) are used / mol) (F = 96,485 C / mol)
After drilling generally casing is done. Assume in one well the casing failure has taken place...
After drilling generally casing is done. Assume in one well the casing failure has taken place due which the operator has faced a problem in the well. Based on understanding how the selection of different types of casing is done (4marks). Support your answer with a neat diagram (1mark).
After drilling generally casing is done. Assume in one well the casing failure has taken place...
After drilling generally casing is done. Assume in one well the casing failure has taken place due which the operator has faced a problem in the well. Based on understanding how the selection of different types of casing is done (4marks). Support your answer with a neat diagram (1mark).
Question 1 A company is considering drilling a development well. Wellsite preparation, drilling and testing of...
Question 1 A company is considering drilling a development well. Wellsite preparation, drilling and testing of the well is expected to cost $2.2 million. Completion of the well and the field equipment necessary to get the well ready for production (wellhead, tubing, flowline, etc.) would cost $1.4 million. Company geologists have suggested that there is a 20% probability that the well will be dry. If that is the case, abandonment and reclamation costs would be $150,000. In the event the...
Question 1 A company is considering drilling a development well. Wellsite preparation, drilling and testing of...
Question 1 A company is considering drilling a development well. Wellsite preparation, drilling and testing of the well is expected to cost $2.2 million. Completion of the well and the field equipment necessary to get the well ready for production (wellhead, tubing, flowline, etc.) would cost $1.4 million. Company geologists have suggested that there is a 20% probability that the well will be dry. If that is the case, abandonment and reclamation costs would be $150,000. In the event the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT