In: Accounting
Question 2
Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2020, 10,100 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 14,000 direct labor hours. All materials purchased were used.
Cost Element |
Standard (per unit) |
Actual |
||
Direct materials | 7 yards at $4.70 per yard | $322,200 for 71,600 yards ($4.50 per yard) | ||
Direct labor | 1.20 hours at $13.00 per hour | $173,166 for 13,020 hours ($13.30 per hour) | ||
Overhead | 1.20 hours at $6.40 per hour (fixed $3.90; variable $2.50) | $49,400 fixed overhead $37,500 variable overhead |
Overhead is applied on the basis of direct labor hours. At normal
capacity, budgeted fixed overhead costs were $54,600, and budgeted
variable overhead was $35,000.
(a)
Compute the total, price, and quantity variances for (1) materials
and (2) labor. (Round per unit values to 2 decimal
places, e.g. 52.75 and final answers to 0 decimal places, e.g.
52.)
(1) | Total materials variance | $
|
FavorableNeither favorable nor unfavorableUnfavorable |
|||
Materials price variance | $ |
FavorableNeither favorable nor unfavorableUnfavorable |
||||
Materials quantity variance | $ |
FavorableNeither favorable nor unfavorableUnfavorable |
||||
(2) | Total labor variance | $ |
Neither favorable nor unfavorableUnfavorableFavorable |
|||
Labor price variance | $ |
FavorableUnfavorableNeither favorable nor unfavorable |
||||
Labor quantity variance | $ |
Neither favorable nor unfavorableUnfavorableFavorable |
(b)
Compute the total overhead variance.
Total overhead variance | $
|
FavorableNeither favorable nor unfavorableUnfavorable |
(a)
Compute the total, price, and quantity variances for (1) materials
and (2) labor. (Round per unit values to 2 decimal
places, e.g. 52.75 and final answers to 0 decimal places, e.g.
52.)
(1) | Total materials variance | (10100*7*4.70)-322200 = 10090
|
Favorable | |||
Materials price variance | (4.70-4.50)*71600 = 14320 | Favorable | ||||
Materials quantity variance | (10100*7-71600)*4.7 = 4230 | Unfavorable | ||||
(2) | Total labor variance | (10100*1.2*13)-173166 = 15606 | Unfavorable | |||
Labor price variance | (13*13020-173166) = 3906 | Unfavorable | ||||
Labor quantity variance | (10100*1.2-13020)*13 = 11700 | Unfavorable |
(b)
Compute the total overhead variance.
Total overhead variance | (10100*1.2*6.4-86900) = 9332 | Unfavorable |