Question

In: Accounting

Splish Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard...

Splish Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2020, 10,400 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 15,080 direct labor hours. All materials purchased were used.

Cost Element

Standard (per unit)

Actual

Direct materials 6 yards at $4.50 per yard $276,760 for 62,900 yards ($4.40 per yard)
Direct labor 1.55 hours at $13.80 per hour $240,264 for 16,920 hours ($14.20 per hour)
Overhead 1.55 hours at $7.40 per hour (fixed $4.90; variable $2.50) $48,800 fixed overhead $36,500 variable overhead


Overhead is applied on the basis of direct labor hours. At normal capacity, budgeted fixed overhead costs were $73,892, and budgeted variable overhead was $37,700.

Compute the overhead controllable variance and the overhead volume variance.

Overhead controllable variance $

Neither favorable nor unfavorable/Favorable/Unfavorable

Overhead volume variance $

Neither favorable nor unfavorable/Favorable/Unfavorable

Solutions

Expert Solution

overhead controllable variance

A

Actual Expenses

PARTICULARS

NO OF YARD

RATE

AMOUNT ( $ )

DIRECT MATERIALS

62900

4.4

              276,760

DIRECT LABOUR

16920

14.2

              240,264

OVERHEAD- FIXED

                 48,800

OVERHEAD- VARIABLE

                 36,500

TOTAL

              602,324

B

BUDGETED

DIRECT MATERIALS

62900

4.5

              283,050

DIRECT LABOUR

16920

13.8

              233,496

OVERHEAD- FIXED

                 73,892

OVERHEAD- VARIABLE

                 37,700

TOTAL

              628,138

DIFFERENCE ( A- B)

              (25,814)

Overhead Controllable Variance is define as difference between

actual expenses and budgeted expenses based on the standard hours

allowed.

If the actual factory overhead is more that the budgeted overhead based

on the standard hours allowed the particular work performed the

variance is called un-favorable Controllable Variance.

On the other hand If the actual factory overhead is less than the budgeted overhead based

on the standard hours allowed the particular work performed the

Variance is called favorable Controllable Variance.

Conclusion : Actual overhead is less than the budgeted overhead & it’s a

favorable controllable variance.

OVERHEAD VOLUMN VARIENCE

The is calculated difference between the amount of Fixed Overhead actually

applied to the good manufactured and the amount that was budgeted to the

applied to the good manufactured .

In our above worked sheet Actual Fixed Overhead is $ 48800 against budget

Fixed Overhead is $ 73892.

Conclusion : Actual Fixed Overhead is less than the Budgeted Fixed Overhead.

It’s a favorable Overhead Volume Variance

Generally unfavorable variable used to highlighted problem that may negative impact of profit..

Thus, it is necessary to review the underlying reasons for a unfavorable variance before concluding that

there is actually a problem.

When actual overhead is equal to the budgeted overhead than called neither favourable nor unfavourable .Its applicale both the overhead conctolled varience & Overhead Volume Varience.


Related Solutions

Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard...
Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2017, 10,400 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 17,000 direct labor hours. All materials purchased were used. Cost Element Standard (per unit) Actual Direct materials 9 yards at $5.00 per yard $458,325 for 94,500 yards ($4.85 per yard) Direct labor 1.70 hours at $13.50 per...
Question 2 Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used...
Question 2 Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2020, 10,100 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 14,000 direct labor hours. All materials purchased were used. Cost Element Standard (per unit) Actual Direct materials 7 yards at $4.70 per yard $322,200 for 71,600 yards ($4.50 per yard) Direct labor 1.20 hours at...
Question 2 Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used...
Question 2 Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2020, 10,100 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 14,000 direct labor hours. All materials purchased were used. Cost Element Standard (per unit) Actual Direct materials 7 yards at $4.70 per yard $322,200 for 71,600 yards ($4.50 per yard) Direct labor 1.20 hours at...
Problem 24-09A Blossom Clothiers is a small company that manufactures tall-men’s suits. The company has used...
Problem 24-09A Blossom Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2020, 10,300 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 17,510 direct labor hours. All materials purchased were used. Cost Element Standard (per unit) Actual Direct materials 9 yards at $5.00 per yard $457,660 for 93,400 yards ($4.90 per yard) Direct labor 1.80 hours at...
Problem 24-03A a-b Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has...
Problem 24-03A a-b Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2020, 10,100 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 14,000 direct labor hours. All materials purchased were used. Cost Element Standard (per unit) Actual Direct materials 7 yards at $4.70 per yard $322,200 for 71,600 yards ($4.50 per yard) Direct labor 1.20 hours...
Problem 24-03A a-b (Video) Concord Clothiers is a small company that manufactures tall-men’s suits. The company...
Problem 24-03A a-b (Video) Concord Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2020, 10,400 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 16,000 direct labor hours. All materials purchased were used. Cost Element Standard (per unit) Actual Direct materials 10 yards at $4.20 per yard $419,600 for 104,900 yards ($4.00 per yard) Direct labor 1.10...
The Rinadale Company manufactures and sells very high-quality men’s business suits to major department store chains....
The Rinadale Company manufactures and sells very high-quality men’s business suits to major department store chains. To stimulate sales, Rinadale Company offered all new first-time customers a special deal. New customers could purchase up to $100,000 of suits using an open credit line. If the purchaser continues to make timely payments on any subsequent purchases, Rinadale Company defers the original purchase payment due date. If the purchaser fails to make additional purchases within sixty days or timely payments, the amount...
Standard Costing Answer Approach Required (steps) Mayfield Ltd manufactures a small part used in the automotive...
Standard Costing Answer Approach Required (steps) Mayfield Ltd manufactures a small part used in the automotive industry. You are the Management Accountant of the company and have been presented with the following information to allow you to prepare a performance report for the year ended 31st March 2020. The budgeted level of production and sales for the year was 265,000 units and the standard manufacturing cost per unit was as follows;                                                                                                 €          Direct materials 2.2 kg @ €11.50 each                                  ...
Haliburton Mills Inc. is a large producer of men’s and women’s clothing. The company uses standard...
Haliburton Mills Inc. is a large producer of men’s and women’s clothing. The company uses standard costs for all of its products. The standard costs and actual costs for a recent period are given below for one of the company’s product lines (per unit of product): Standard Cost Actual Cost   Direct materials:      Standard: 2.0 metres at $3.90 per metre $ 7.80      Actual: 2.4 metres at $3.65 per metre $ 8.76   Direct labour:     Standard: 1.5 hours at $2.50 per hour 3.75...
Stark Industries is considering adding a vibranium shield to the Iron Man Suits the company manufactures...
Stark Industries is considering adding a vibranium shield to the Iron Man Suits the company manufactures for the U.S. Armed Forces. The equipment to build the shields has a purchase price of $1,100,000, and the company will spend $100,000 to ship the equipment to its plant and install it on the production floor. Stark Industries engineers expect the machine to have a $50,000 salvage value at the end of its 10-year life and a practical capacity of 1,200 shields per...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT