In: Accounting
Question 2
Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2020, 10,100 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 14,000 direct labor hours. All materials purchased were used.
Cost Element |
Standard (per unit) |
Actual |
||
Direct materials | 7 yards at $4.70 per yard | $322,200 for 71,600 yards ($4.50 per yard) | ||
Direct labor | 1.20 hours at $13.00 per hour | $173,166 for 13,020 hours ($13.30 per hour) | ||
Overhead | 1.20 hours at $6.40 per hour (fixed $3.90; variable $2.50) | $49,400 fixed overhead $37,500 variable overhead |
Overhead is applied on the basis of direct labor hours. At normal
capacity, budgeted fixed overhead costs were $54,600, and budgeted
variable overhead was $35,000.
(a)
Compute the total, price, and quantity variances for (1) materials
and (2) labor. (Round per unit values to 2 decimal
places, e.g. 52.75 and final answers to 0 decimal places, e.g.
52.)
(1) | Total materials variance | $ |
Neither favorable nor unfavorableFavorableUnfavorable |
|||
Materials price variance | $ |
Neither favorable nor unfavorableFavorableUnfavorable |
||||
Materials quantity variance | $ |
Neither favorable nor unfavorableFavorableUnfavorable |
||||
(2) | Total labor variance | $ |
FavorableNeither favorable nor unfavorableUnfavorable |
|||
Labor price variance | $ |
FavorableNeither favorable nor unfavorableUnfavorable |
||||
Labor quantity variance | $ |
FavorableUnfavorableNeither favorable nor unfavorable |
(b)
Compute the total overhead variance.
Total overhead variance | $ |
Neither favorable nor unfavorableFavorableUnfavorable |
Part (a) :
(1) Material Variances:
(i) Total materials variance
Total Materials variance = Standard cost - actual cost |
Standard cost = 10100 suits * 7 yards * $4.70 per yard = $332290
Actual cost = $322200
Total Material Variance = $332290 - $322200 = $10090 Favorable |
(ii) Material Price variance
Material Price variance = (Actual quantity * Standard Price) - (Actual quantity * actual price) |
Actual Quantity = 71600 Yards
Standard Price = $4.70 per Yard
Material Price Variance = (71600 yards * $4.70 per yard) - (71600 Yards * $4.50 per Yard) = $14320 Favorable |
(iii) Material Quantity variance
Material Quantity variance = (Standard quantity * Standard Price) - (Actual quantity * standard price) |
Standard Quantity = 10100 suits * 7 yards = 70700 Yards
Actual Quantity = 71600 yards
Standard Price = $4.70 per Yard
Material Quantity Variance = (70700 yards * $4.70 per yard) - (71600 Yards * $4.70 per Yard) = $4230 Unfavorable |
Part (a) :
(2) Labor Variances:
(i) Total Labor variance
Total Labor variance = Standard cost - actual cost |
Standard cost = 1.20 hours * 10100 suits * $13 per hour = $157560
Actual cost = $173166
Total labor Variance = $157560 - $173166 = $15606 Unfavorable |
(ii) Labor Price variance
Labor Price variance = (Actual Hours * Standard Rate) - (Actual Hours * actual rate) |
Actual Hours = 13020 hours
Standard rate = $13 per hour
Labor Price Variance = (13020 hours * $13 per hour) - (13020 hours * $13.30 per hour) = $3906 Unfavorable |
(iii) Labor Quantity variance
Labor Quantity variance = (Standard quantity * Standard Rate) - (Actual quantity * standard rate) |
Standard Quantity = 10100 suits * 1.20 hours = 12120 Hours
Actual Quantity = 13020 hours
Standard Rate = $13 per hour
Labor Quantity Variance = (12120 hours * $13 per hour) - (13020 hours * $13 per hour) = $11700 Unfavorable |
Part (b) :
Total overhead Variances:
Total Overhead variances = Standard cost - actual cost |
Standard cost = 1.20 hours * 10100 suits * $6.40 per hour = $77568
Actual cost = $49400 + $37500 = $86900
Total Overhead Variance = $77568 - $86900 = $9332 Unfavorable |
All the best...