Question

In: Accounting

Do an order of magnitude estimate for building a new catalytic cracking plant in the Middle...

Do an order of magnitude estimate for building a new catalytic cracking plant in the Middle East with a capacity of 5000 metric tons/year in 2016.

Solutions

Expert Solution

A Rough Order of Magnitude Estimate (ROM estimate) is an estimation of a project’s level of effort and cost to complete. A ROM estimate takes place very early in a project’s life cycle — during the project selection and approval period and prior to project initiation in most cases. The main purpose of the ROM estimate is to provide decision-makers with the information necessary to make a decision on whether it makes sense to move forward with the project based on the estimated level of effort, in terms of completion time and cost.

Developing a ROM estimate is as much a skill as it is an art. First and foremost, subject matter experts should be involved in level of effort estimations. Second, when developing a ROM, it is important to understand that the estimate is a “Rough Order of Magnitude” estimate that will have an accuracy of about plus or minus 50%. Depending on the source, the variance can be as much as 100%.  A variance of -25% to +75% is also common for ROM estimates. The point is to provide a “ballpark” estimate using the information available at the time.

A ROM estimate’s variance is rather large, but it should not disuade you from making an attempt. Remember that some information is better than no information. Also remember that the estimate is based on the information available at the time of developing the ROM estimate.  As the project moves forward, expect to further improve the estimate, when more information is obtained and requirements are further refined during the initiation and planning phases of the project (PMBOK students, do you recall the term progressive elaboration?)

The following information provides a comparison of the three general kinds of estimates as the project makes its way through the life cycle.

  1. ROM Estimate (Variance of -50% to +50%, or -25% to +75% depending on preference)
    • A “ballpark” estimate used to provide a starting estimate to move forward
    • A top-down estimation approach
    • Use of previous expert knowledge and experience
    • Not a great deal of time is spent to develop the ROM estimate
  2. Budget Estimate (Variance of -10% to +25%)
    • Also a top down estimation approach
    • Use of analogous estimation techniques helps provide a slightly more accurate estimate than the ROM estimate (e.g., referencing previous similar types of projects for effort)
  3. Definitive Estimate (Variance of -5% to +10%)
    • A bottom-up estimation technique that requires a decomposition of work and its level of effort that is summed up to develop a more accurate estimate
    • Generally performed during the planning phase and matained through the remainder of the project
    • This is the most time consuming estimation effort of the three listed

When developing a ROM estimate, it is best to try estimating in buckets of time and cost. Providing categories may help estimators who otherwise would not be able to provide one number due to the limited amount of information available at the onset of a project. The example below provides categories of “Low”, “Medium”, and “High” levels of effort. Using such a scale may be easier than trying to pull a number out of a hat. It also sets the expectation on both sides — project team and client — that the ROM estimate has a large variance and should be recognized as just an initial ROM.

  1. Low Effort
    • Hours: 40 to 80 hours to complete
    • Cost: $1000 to $5000 dollars
    • Duration: 1 to 4 weeks
    • Number of Resources: 1 to 3 Resources
  2. Medium Effort
    • Hours: 80 to 480 hours to complete
    • Cost: $10,000 to $50,000 dollars
    • Duration: 2 to 6 months
    • Number of Resources: 4 to 10 Resources
  3. High Effort
    • Hours: 480 to 2080 hours to complete
    • Cost: $100,000 to $500,000 dollars
    • Duration: 6 to 12 months
    • Number of Resources: 11 to 20 Resources

Using buckets, or categories like the ones listed above, decompose the work from top down to a level of detail that makes sense given the amount of information available. Assuming that the project is in the very early stages, and stakeholder needs and requirements are at a high level, it is safe to assume that the breakdown of work will not be significantly detailed. The point is not to develop a full blown WBS here. The point is simply to compartmentalize the work into a set of activities that make sense and that can be measured. For example, developing a web application, the work list might only be a few items like so:

  1. Develop Requirements
  2. Develop the Database Schema
  3. Develop the Application
  4. Test and Deploy the Application
  5. Project Management Activities (Don’t forget to include PM activities. The take time and resources)

Apply a category of effort to each piece of work to come to a ROM estimate. That’s it in a nutshell!

There is a great deal more to know about cost estimating and cost estimating techniques (e.g., Applying learning curves, complexity factors and risk factors; PERT time estimation; Software estimation techniques such as function point analysis technique and COCOMO — http://cost.jsc.nasa.gov/COCOMO.html). But this is a good primer, at least, on ROM estimation. The related links, below, offer additional tips on cost estimating. Also, refer to the Society of Cost Estimating and Analysis (http://www.sceaonline.org/), which is a thought leader in this arena. Expect lots more to come on cost estimation!


Related Solutions

Scenario : Middle School Building Project: The new middle school building includes classrooms, offices and administrative...
Scenario : Middle School Building Project: The new middle school building includes classrooms, offices and administrative spaces, dining commons with kitchen, and media center. Additional spaces that may be part of the final design include auditorium, gymnasium and athletic fields. Building construction may consist of a multi-story masonry and steel load bearing building with elevated slabs, poured in-place concrete retaining walls and associated underground waterproofing. Exterior finish materials may include brick veneer, aluminum storefront and curtain wall, and aluminum composite...
Sunset Sarsaparilla is building a new bottling plant. This plant will cost $140M to construct, and...
Sunset Sarsaparilla is building a new bottling plant. This plant will cost $140M to construct, and will produce EBIT of $19M per year for the next 12 years. Sunset has a tax rate of 40%. Another firm in the same industry, Vim Pop, has an equity beta of 1.2 and a debt to equity ratio of 0.9. Sunset’s debt to equity ratio is 1.5, the risk free rate is 4%, and the excess return on the market is 8%. Assume...
Aberdeen Outboard Motors is contemplating building a new plant. The company anticipates that the plant will...
Aberdeen Outboard Motors is contemplating building a new plant. The company anticipates that the plant will require an initial investment of $2.06 million in net working capital today. The plant will last 11 ​years, at which point the full investment in net working capital will be recovered. Given an annual discount rate of 6.4%​, what is the net present value of this working capital​ investment? The NPV is ​$_____ ​(Round to the nearest​ dollar.)
Artie's Wrestling Stuff is considering building a new plant. This plant would require an initial cash...
Artie's Wrestling Stuff is considering building a new plant. This plant would require an initial cash outlay of ​$ 8 million and would generate annual free cash inflows of ​$ 1 million per year for 8 years. Calculate the​ project's MIRR ​given: a. A required rate of return of 9 percent b. A required rate of return of 12 percent c. A required rate of return of 15 percent
In order to evaluate the effectiveness of a new type of plant food that was developed...
In order to evaluate the effectiveness of a new type of plant food that was developed for tomatoes, a study was conducted in which a random sample of n = 68 plants received a certain amount of this new type of plant food each week for 14 weeks. The variable of interest is the number of tomatoes produced by each plant in the sample. The table below reports the descriptive statistics for this study: Descriptive statistics for the tomato food...
GMFC is planning to expand its U.S. operations by building a new plant. They will employ...
GMFC is planning to expand its U.S. operations by building a new plant. They will employ about 500 production workers. This new plant will manufacture motorized recreational equipment including all-terrain vehicles, personal watercraft, and snowmobiles. The equipment will assemble mechanical components produced in other GMFC operations or purchased from suppliers. The new plant will fabricate fiberglass body parts and complete the final assembly process. GMFC would like to operate the new plant union-free. It's likely that the Untied Automobile Workers...
In order to estimate the number of calls to expect at a new suicide hotline, volunteers...
In order to estimate the number of calls to expect at a new suicide hotline, volunteers contact a random sample of 50 similar hotlines across the nation and find that the sample mean is 32.0 calls per month. Construct a 99% confidence interval for the mean number of calls per month. Assume that the population standard deviation is known to be 9.5 call per month. (Please show all work)
A new entrepreneur wants to estimate the costs of an offsite team-building event for her 14...
A new entrepreneur wants to estimate the costs of an offsite team-building event for her 14 employees. She was able to gather the following information on a 3-day program in which she is interested. Use the unit technique to estimate the cost per employee of this event. Assume there will 100% participation in all activities. Cost Elements Cost Rate Transportation Costs (the site is 60 miles away.) Van rental of $109 pay day per 14 people. The van gets 16...
You’re trying to determine whether to expand your business by building a new manufacturing plant. The...
You’re trying to determine whether to expand your business by building a new manufacturing plant. The plant has an installation cost of $12.6 million, which will be depreciated straight-line to zero over its four-year life. If the plant has projected net income of $1,914,300, $1,967,600, $1,936,000, and $1,389,500 over these four years, respectively, what is the project’s average accounting return (AAR)?
Hawke Skateboards is considering building a new plant. Bob Skerritt, the company's marketing manager, is an...
Hawke Skateboards is considering building a new plant. Bob Skerritt, the company's marketing manager, is an enthusiastic supporter of the new plant. Lucy Liu, the company's chief financial officer, is not so sure that the plant is a good idea. Currently, the company purchases its skateboards from foreign manufacturers. The following figures were estimated regarding the construction of a new plant. Cost of plant                                         $4,000,000    Estimated useful life                               15 years Annual cash inflows                                   4,000,000 Salvage value...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT