CPM or the critical path method is used in the project planning and scheduling stage of a any project. Its' widely used in construction project as a detailing tool.
The CPM for the above mentioned project is given below. As the detailed project with quantities and time duration is not give, the below CPM is formed based on the list of activities that forms the above project. The common activities such as the construction of load bearing columns, exteriors, interiors and clubbed together and mentioned in the CPM drawing. The activity duration are assumed for a construction project and is shown in the drawing. Some of the activities may overlap or carried out side by side and such activities are given in the schedule with overlapping time schedules.
The CPM constructed for the middle school building project is given below: