Question

In: Finance

The cash flows for four projects are shown below, along with the cost of capital for...

  1. The cash flows for four projects are shown below, along with the cost of capital for these projects. If these projects are mutually exclusive, which one should be taken?

    A.

    Year:                         0                1            2              3            4                  5

    Cash flow:                     -$12,000    $4000    $4000      $4000    $4000          $4000

    Cost of Capital: 5.0%

    B.

    Year:                              0                1            2              3            4                  5

    Cash flow:                     -$15,000    $4000    $4000      $4000    $4000          $4000

    Cost of Capital: 7.0%

    C.

    Year:                              0                1            2              3            4                  5

    Cash flow:                     -$20,000    $6000    $6000      $6000    $6000          $6000

    Cost of Capital: 8.2%

    D.

    Year:                              0                1            2              3            4                  5

    Cash flow:                     -$18,000    $5000    $5000      $5000    $5000          $5000

    Cost of Capital: 7.6%

Solutions

Expert Solution

Answer: (A) As NPV is higher for Project A, it should be accepted.

Computation of NPV Computation of NPV Computation of NPV Computation of NPV
A B C D
Year Cashflows PVF@ 5 % PV Year Cashflows PVF@ 7 % PV Year Cashflows PVF@ 8.2 % PV Year Cashflows PVF@ 7.6 % PV
A 0 $ (12,000) 1.0000 $        (12,000) 0 $       (15,000) 1.0000 $        (15,000) 0 $             (20,000) 1.0000 $           (20,000) 0 $ (18,000) 1.0000 $(18,000)
PV of Cash Outflows $        (12,000) PV of Cash Outflows $        (15,000) PV of Cash Outflows $           (20,000) PV of Cash Outflows $(18,000)
B 1 $     4,000 0.9524 $             3,810 1 $            4,000 0.9346 $            3,738 1 $                 6,000 0.9242 $                5,545 1 $      5,000 0.9294 $    4,647
2 $     4,000 0.9070 $             3,628 2 $            4,000 0.8734 $            3,494 2 $                 6,000 0.8542 $                5,125 2 $      5,000 0.8637 $    4,319
3 $     4,000 0.8638 $             3,455 3 $            4,000 0.8163 $            3,265 3 $                 6,000 0.7894 $                4,737 3 $      5,000 0.8027 $    4,014
4 $     4,000 0.8227 $             3,291 4 $            4,000 0.7629 $            3,052 4 $                 6,000 0.7296 $                4,378 4 $      5,000 0.7460 $    3,730
5 $     4,000 0.7835 $             3,134 5 $            4,000 0.7130 $            2,852 5 $                 6,000 0.6743 $                4,046 5 $      5,000 0.6933 $    3,467
PV of Cash Inflows $          17,318 PV of Cash Inflows $          16,401 PV of Cash Inflows $              23,831 PV of Cash Inflows $ 20,176
NPV = B-A $          5,318 NPV = B-A $ 1,401 NPV = B-A $ 3,831 NPV = B-A $ 2,176

All the Projects have Positive NPV, So all the projects can be accepted if they are independent.

However, as the projects are mutually exclusive, i.e., selection of one project, excludes other projects. So, Project with higher NPV should be NPV should be Selected, So, Project A

Computation of NPV Computation of NPV Year Cashflows PVF@ 5% PV Year Cashflows PVF@ 7% PV 0 $(12,000) 1.0000 $ (12,000) 0 $ (15,000)| 1.0000 $ (15,000) PV of Cash Outflows $ (12,000) PV of Cash Outflows $ (15,000) 1 $ 4,000 0.9524 $ 21 $ 4,000 0.9070$ 3 $ 4,000 0.8638 $ 4 $ 4,000 0.8227 $ 5 $ 4,000 0.7835 $ PV of Cash Inflows $ 3,810 3,628 3,455 3,291 3,134 17,318 1 $ 4,000 0.9346 $ 21 $ 4,000 0.8734 $ 31 $ 4,000 0.8163 $ 4 $ 4,000 0.7629 $ 5 $ 4,000 0.7130 $ PV of Cash Inflows $ 3,738 3,494 3,265 3,052 2,852 16,401 NPV =B-A $ 29,318 NPV =B-A $ 31,401

Computation of NPV Computation of NPV Year Cashflows PVF@ 8.2% PV Year Cashflows PVF@ 7.6% PV AL0 $ (20,000) 1.0000 $ (20,000) 0 $(18,000) 1.0000 $ (18,000) PV of Cash Outflows $ (20,000) PV of Cash Outflows $ (18,000) 1 $ 6,000 2 $ 6,000 3 $ 6,000 4 $ 6,000 5 $ 6,000 PV of Cash Inflows 0.9242 $ 0.8542 $ 0.7894 $ 0.7296 $ 0.6743 $ 5,545 5,125 4,737 4,378 4,046 23,831 1 $ 5,000 0.9294 $ 4,647 2 $ 5,000 0.86371 $ 4,319 3 $ 5,000 0.8027 $ 4,014 4 $ 5,000 0.7460 $ 3,730 5 $ 5,000 0.6933 $ 3,467 PV of Cash Inflows $ 20,176 NPV =B-A $ 43,831 NPV =B-A $ 38,176


Related Solutions

) The cash flows for four projects are shown below, along with the cost of capital...
) The cash flows for four projects are shown below, along with the cost of capital for these projects. If these projects are mutually exclusive, which one should be taken? 28) A) Year: 0 1 2 3 4 5 Cash flow: -$20,000 $6000 $6000 $6000 $6000 $6000 Cost of Capital: 8.2% B) Year: 0 1 2 3 4 5 Cash flow: -$15,000 $4000 $4000 $4000 $4000 $4000 Cost of Capital: 7.0% C) Year: 0 1 2 3 4 5 Cash...
a) Four investment projects have the following net cash flows. The cost of capital is 15%....
a) Four investment projects have the following net cash flows. The cost of capital is 15%. Decide which of them should be accepted using the net present value method. Find the discounted payback period. YEAR PROJECT A PROJECT B PROJECT C PROJECT D 0 (10,000) (15,000) (20,000) (30,000) 1 5,000 5,000 10,000 0 2 5000 5,000 10,000 0 3 20,000 5,000 4,000 100,000 4 1,000 10,000 2,000 120,000 5 - 5,000 - 60,000
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 7.75% 0 1 2 3 4 CF S -$1,025 $380 $380 $380 $380 CF...
A company is considering Projects S and L, whose cash flows are shown below. These projects...
A company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates other methods. If the decision is made by choosing the project with the higher IRR, how much, if any, value will be forgone, i.e., what's the: NPV and IRR of the chosen project(s). What is the Payback period, discounted payback period, and...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? Interest rate: 10.00% Year 0 1 2 3 4 CFS -$1,000 $380 $380 $380 $380...
The cash flows for two projects, A and B, are shown in the table, below. Notice...
The cash flows for two projects, A and B, are shown in the table, below. Notice that Project A has a life of 5 years and Project B has a 3 year life. Calculate the NPV of each project and calculate which should be adopted using the replacement chain approach. Assume that the cost of capital is 10%. Project CFs Project CFs Time A B 0 -100 -150 1 20 75 2 25 60 3 30 50 4 30 5...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 0 1 2 3 4 CFS -$1,100...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects...
Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. WACC: 7.75 CFs Y0: $-1050 Y1 $675 $650 CFl Y0 $-1050 Y1 $360 Y2 360 Y3$360...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT