The construction of a house is developed and in the table you will find all the activities described and the information that corresponds to predecessors and the duration of each activity. Adjust your analysis to the information in the table without modifying the baseline information. Analyze the project execution time following the PERT Diagram methodology. Establish Critical Path of the project. Set the duration of the work. Complete the table.
ACTIVITY | DESCRIPTION | PREDECESSOR | DURATION (WEEKS) | Earliest Time | Latest Time |
A | PRELIMINARY JOBS | - | 2 | ||
B | STRUCTURE | A | 3 | ||
C | FOUNDATIONS AND WALLS | B | 4 | ||
D | SPECIAL SYSTEMS | A | 2.5 | ||
E | ROOF AND COVERINGS | C | 2 | ||
F | TOUCH-UPS | E | 5 | ||
G | COATINGS | E | 3 | ||
H | PAINTING | F,G | 2 | ||
I | DELIVERY | H | 1 |