Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $674,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:

Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity
Machining Machine-hours $ 216,700 11,000 MHs
Machine setups Number of setups $ 79,900 170 setups
Product design Number of products $ 81,000 2 products
General factory Direct labor-hours $ 296,400 13,200 DLHs
Activity Measure Product Y Product Z
Machine-hours 6,700 4,300
Number of setups 60 110
Number of products 1 1
Direct labor-hours 7,700 5,500

1. What is the company’s plantwide overhead rate?

2. Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z?

3. What is the activity rate for the Machining activity cost pool?

4. What is the activity rate for the Machine Setups activity cost pool?

5. What is the activity rate for the Product Design activity cost pool?

6. What is the activity rate for the General Factory activity cost pool?

7. Which of the four activities is a batch-level activity?

Product design activity

Machining activity

General factory activity

Machine setups activity

8. Which of the four activities is a product-level activity?

Machining activity

Product design activity

Machine setups activity

General factory activity

9. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y?

10. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z?

11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z?

12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z?

13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z?

14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z?

15. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z?

Thank you

Solutions

Expert Solution

Note: In case of any clarification, please do feel free to comment. Thank You


Related Solutions

Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $674,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 216,700 11,000...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 213,400 11,000...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $597,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 213,400 11,000...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $696,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 224,400 11,000...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $729,600 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 227,700 11,000...
Required information Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product...
Required information Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labour-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Measure Estimated Overhead Cost Expected Activity   Machining Machine-hours $ 227,700   11,000 MHs   Machine...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Using the ABC system, what percentage of the Machine Setups is assigned to Product Y and...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Using the ABC system, what percentage of the General Factory cost is assigned to Product Y...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:    Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity   Machining Machine-hours $ 231,000   ...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Greenwood Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:    Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity   Machining Machine-hours $ 224,400   ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT