In: Accounting
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $696,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Expected Activity | ||
Machining | Machine-hours | $ | 224,400 | 11,000 | MHs |
Machine setups | Number of setups | $ | 129,600 | 240 | setups |
Product design | Number of products | $ | 88,000 | 2 | products |
General factory | Direct labor-hours | $ | 254,000 | 13,200 | DLHs |
Activity Measure | Product Y | Product Z |
Machine-hours | 7,400 | 3,600 |
Number of setups | 60 | 180 |
Number of products | 1 | 1 |
Direct labor-hours | 8,400 | 4,800 |
1. What is the company’s plantwide overhead rate? (Round your answer to 2 decimal places.)
2.Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places and your final answers to the nearest whole dollar amount.)
3. What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.)
4. What is the activity rate for the Machine Setups activity cost pool?
5. What is the activity rate for the Product Design activity cost pool?
6.What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.)
7. Which of the four activities is a batch-level activity?
Product design activity
Machining activity
General factory activity
Machine setups activity
8.Which of the four activities is a product-level activity?
Machining activity
Product design activity
Machine setups activity
General factory activity
9.Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Round all intermediate calculations to 2 decimal places.)
10. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z?
1 | |||
Plantwide overhead rate | 52.73 | per DLH | =696000/13200 |
2 | |||
Manufacturing overhead cost: | |||
Product Y | 442932 | =8400*52.73 | |
Product Z | 253104 | =4800*52.73 | |
3 | |||
Machining Activity rate | 20.40 | per MH | =224400/11000 |
4 | |||
Machine Setups Activity rate | 540 | per setup | =129600/240 |
5 | |||
Product Design Activity rate | 44000 | per product | =88000/2 |
6 | |||
General Factory Activity rate | 19.24 | per DLH | =254000/13200 |
7 | |||
Machine setups activity is a batch-level activity | |||
8 | |||
Product design activity is a product-level activity | |||
9 | |||
Total manufacturing overhead cost Product Y | 388976 | ||
10 | |||
Total manufacturing overhead cost Product Z | 306992 | ||
Workings: | |||
Product Y: | |||
Machining | 150960 | =7400*20.4 | |
Machine setups | 32400 | =60*540 | |
Production design | 44000 | ||
General factory | 161616 | =8400*19.24 | |
Total manufacturing overhead cost | 388976 | ||
Product Z: | |||
Machining | 73440 | =3600*20.4 | |
Machine setups | 97200 | =180*540 | |
Production design | 44000 | ||
General factory | 92352 | =4800*19.24 | |
Total manufacturing overhead cost | 306992 |