Question

In: Accounting

Baker enterprises, Inc., has a job-order costing system. The company uses predetermined overhead rates in applying...

Baker enterprises, Inc., has a job-order costing system. The company uses predetermined overhead rates in applying manufacturing overhead cost to individual jobs. The predetermined overhead rate in Department A is based on machine-hours, and the rate in Department B is based on direct labor hours. At the beginning of the most recent year, the company’s management made the following estimates for the year:

Department A

Department B

Machine-hours.............

70,000

19,000

Direct labor-hours.........

30,000

60,000

Direct materials............

$195,000

$282,000

Direct labor..................

$260,000

$520,000

Manufacturing overhead.................................

$420,000

$705,000

Job 423 entered into production an April 1 and was completed on May 12. The company’s cost records show the following information about the job:

Department A

Department B

Machine-hours.....

250

60

Direct labor-hours.

70

120

Direct materials....

$840

$1,100

Direct labor..........

$610

$880

Required:

a. Compute the predetermined overhead rates for Department A and Department B.

b. Compute the total overhead cost applied to Job 423.

c. Compute the total job cost of Job 423

d. Compute the unit cost of Job 423 if the job produces 300 units.

Solutions

Expert Solution

Answer a.

Department A:

Predetermined Overhead Rate = Budgeted Manufacturing Overhead / Budgeted machine-hours
Predetermined Overhead Rate = $420,000 / 70,000
Predetermined Overhead Rate = $6.00 per machine-hour

Department B:

Predetermined Overhead Rate = Budgeted Manufacturing Overhead / Budgeted direct labor-hours
Predetermined Overhead Rate = $705,000 / 60,000
Predetermined Overhead Rate = $11.75 per direct labor-hour

Answer b.

Department A:

Overhead Cost applied = Predetermined Overhead Rate * Actual machine-hours
Overhead Cost applied = $6.00 * 250
Overhead Cost applied = $1,500

Department B:

Overhead Cost applied = Predetermined Overhead Rate * Actual direct labor-hours
Overhead Cost applied = $11.75 * 120
Overhead Cost applied = $1,410

Job 423:

Total Overhead Cost applied = $1,500 + $1,410
Total Overhead Cost applied = $2,910

Answer c.

Department A:

Total Cost = Direct Materials + Direct Labor + Overhead Cost applied
Total Cost = $840 + $610 + $1,500
Total Cost = $2,950

Department b:

Total Cost = Direct Materials + Direct Labor + Overhead Cost applied
Total Cost = $1,100 + $880 + $1,410
Total Cost = $3,390

Job 423:

Total Job Cost = $2,950 + $3,390
Total Job Cost = $6,340

Answer d.

Unit Cost = Total Job Cost / Number of units produced
Unit Cost = $6,340 / 300
Unit Cost = $21.13


Related Solutions

Dotsero Technology, Inc., has a job-order costing system. The company uses predetermined overhead rates in applying...
Dotsero Technology, Inc., has a job-order costing system. The company uses predetermined overhead rates in applying manufacturing overhead cost to individual jobs. The predetermined overhead rate in Department A is based on machine-hours, and the rate in Department B is based on direct labor hours. At the beginning of the most recent year, the company's management made the following estimates for the year. Dept. A Dept. B Machine-hours. . . . . . . . . . . . ....
ABC Manufacturing Company uses a job-order costing system. The company uses predetermined overhead rates in applying...
ABC Manufacturing Company uses a job-order costing system. The company uses predetermined overhead rates in applying manufacturing overhead to individual jobs. The predetermined overhead rate in the Chair Department is based on direct labour hours, the rate in the Table Department is based on machine hours, and the rate in the Desk Department is based on direct labour cost. At the beginning of the most recent year, members of the management team made the following estimates for the year: (Estimated)                                                                          ...
Basic Job Costing Project Reed Incorporated uses a job-order costing system and a predetermined overhead rate...
Basic Job Costing Project Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours. At the beginning of the year, the company estimated manufacturing overhead for the year would be $240,000 and machine hours would be 8,000. The following information pertains to December of the current year: Job 10 Job 11 Job 12 Total Work-in-process, Dec. 1 $16,000 $26,000 $38,000 $80,000 The following transactions took place during the month of December: 1. Purchased raw...
The Maverick company uses a job-order costing system with a single plantwide predetermined overhead rate based...
The Maverick company uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor hours. the company based its predetermined overhead rate for the current year on the following data. Estimated total direct labor hours :        $2,800 Estimated total fixed MOH cost :         $35,000 Estimated variable MOH per direct labor hour : $2.34 Recently, Job D3 was completed with the following characteristics : # of units in the job :       14 total direct labor hours:  ...
The Savage Garden Company uses normal costing in its job-order cost system. The predetermined overhead rate...
The Savage Garden Company uses normal costing in its job-order cost system. The predetermined overhead rate is 3 times the direct labor cost. Job 70 was completed during 2019. This job was charged $4,000 for direct materials, $2,000 for direct labor, and $6,000 for allocated overhead. The job consisted of 10 units. After the job was completed, but before it was sent to Finished Goods, it was determined that 2 of these units were spoiled. If the 2 bad units...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently,...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $80,000 $78,000 Normal activity (machine hours) 14,500 10,800 Required: 1. Compute a predetermined...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently,...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $80,000 $83,000 Normal activity (machine hours) 16,000 2,800 Required: 1. Compute a predetermined...
Problem #4 Predetermined Overhead Rate Broadway Corporation uses job order costing with a predetermined overhead rate...
Problem #4 Predetermined Overhead Rate Broadway Corporation uses job order costing with a predetermined overhead rate based on machine hours to apply overhead. The following costs were provided after Job 500 & 510 were complete. Given Estimated Annual Data: Machine Hours 55,000 DL rate/hour $8 Unit Overhead 345,000 Support labor (4,000 hours) 17,000 Facility Overhead 150,000 Supervisor Salaries 36,000 Total Overhead 495,000 Beginning Inventory Raw Materials and Supplies $10,500 Work in Process (Job 500 only) 54,000 Finished Goods 112,500 Purchases...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,700 Total fixed manufacturing overhead cost $294,300 Variable manufacturing overhead per machine-hour $ 2.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 20 Direct materials $ 545 Direct labor cost $1,090 If the company marks up...
Gerstein Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Gerstein Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $90,000, variable manufacturing overhead of $3.70 per direct labor-hour, and 50,000 direct labor-hours. The company recently completed Job M800 which required 150 direct labor-hours. The estimated total manufacturing overhead is closest to: Multiple Choice $90,000 $275,000 $185,000 $90,004
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT