Gerstein Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $90,000, variable manufacturing overhead of $3.70 per direct labor-hour, and 50,000 direct labor-hours. The company recently completed Job M800 which required 150 direct labor-hours.

The estimated total manufacturing overhead is closest to:

Multiple Choice

  • $90,000

  • $275,000

  • $185,000

  • $90,004

Solutions

Expert Solution

The estimated total manufacturing overhead can be calculated as follows-
Particulars Amount
Estimated fixed manufacturing overhead cost $90,000
Add: Estimated variable manufacturing overhead cost ($3.70 per direct labor-hour x 50,000 estimated direct labor-hours) $185,000
Estimated total manufacturing overhead $275,000
Hence, the second option is the correct answer.

Related Solutions

Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,700 Total fixed manufacturing overhead cost $294,300 Variable manufacturing overhead per machine-hour $ 2.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 20 Direct materials $ 545 Direct labor cost $1,090 If the company marks up...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,300 Total fixed manufacturing overhead cost $ 581,400 Variable manufacturing overhead per machine-hour $ 2.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 630 Direct labor cost $ 1,260 If the company...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 78,000 Total fixed manufacturing overhead cost $ 460,200 Variable manufacturing overhead per direct labor-hour $ 5.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 50 Total direct labor-hours 100 Direct materials $ 710 Direct labor cost $...
Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 80,000 Total fixed manufacturing overhead cost $ 312,000 Variable manufacturing overhead per machine-hour $ 2.10 Recently, Job T629 was completed with the following characteristics: Number of units in the job 50 Total machine-hours 200 The estimated total manufacturing overhead is closest to what?
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,000 Total fixed manufacturing overhead cost $ 352,000 Variable manufacturing overhead per machine-hour $ 3.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 675 Direct labor cost $ 1,350 If the company...
Brown Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Brown Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $234,000, variable manufacturing overhead of $2.60 per machine-hour, and 30,000 machine-hours. The company has provided the following data concerning Job Z500 which was recently completed: Number of units in the job 20 Total machine-hours 80 Direct materials $790 Direct labor cost $1,580 If the company...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,800 Total fixed manufacturing overhead cost $ 164,000 Variable manufacturing overhead per machine-hour $ 5 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 745 Direct labor cost $ 1,490 The amount of...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,400 Total fixed manufacturing overhead cost $ 425,600 Variable manufacturing overhead per machine-hour $ 5.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 20 Direct materials $ 590 Direct labor cost $ 1,180 If the company...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 31,200 Total fixed manufacturing overhead cost $ 156,000 Variable manufacturing overhead per machine-hour $ 3.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 665 Direct labor cost $ 1,330 If the company...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,700 Total fixed manufacturing overhead cost $ 337,700 Variable manufacturing overhead per machine-hour $ 4 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 20 Direct materials $ 575 Direct labor cost $ 1,150 The unit product...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT