Question

In: Accounting

Suppose that you are the estimator who is assigning costs to a major project to be...

Suppose that you are the estimator who is assigning costs to a major project to be undertaken this year by your firm, Acme Software Developers. One particular software development process involves many labor-hours, but the work is highly redundant. You anticipate a total of 100,000 labor-hours to complete the first iteration of the software development process and a learning curve rate of 80%. Assume you are going to use the cumulative average time in your calculations to determine the time it takes for each iteration.

You are attempting to estimate the cost of the tenth iteration of this repetitive process. Based on this information and a $60 per hour labor rate, what would you expect to budget as

A. The cost of the tenth iteration?

B. The cost of the twentieth iteration?

Solutions

Expert Solution

Cummulative average time = Y = aXb

Where Y =cumulative average time per unit or batch

a = time taken to produce initial quantity

X = the cumulative units of production or, if in batches, the cumulative number of batches.

b = the learning index or coefficient, which is calculated as: log learning curve percentage ÷ log 2. So b for an 80 per cent curve would be log 0.8 ÷ log 2 = – 0.322

Cumulative average time for 10 iterations

Y = 100000*10-0.322

= 47643.10

TOTAL TIME TO PRODUCE 10 ITERATIONS = 47643.10*10 = 476431 hours.

Cumulative average time for 9 iterations

Y = 100000*9-0.322

= 49287.17

TOTAL TIME TO PRODUCE 9 ITERATIONS = 49287.17*9 = 443584.53 hours.

time taken for 10th iteration = 476431 hours - 443584.53 hours. = 32846.47

Cost of 10th iteration = 32846.47*60 = $1970788.2

Cumulative average time for 20 iterations

Y = 100000*20-0.322

= 38112.58

TOTAL TIME TO PRODUCE 20 ITERATIONS = 38112.58*20 = 762251.59 hours.

Cumulative average time for 19 iterations

Y = 100000*19-0.322

= 38747.29

TOTAL TIME TO PRODUCE 19 ITERATIONS = 38747.29*19 = 736198.52 hours.

time taken for 20th iteration = 762251.59 hours - 736198.52 hours = 26053.07

Cost of 10th iteration = 26053.07*60 = $1563184.06


Related Solutions

FIFO method assigning costs.
FIFO method assigning costs. Do Exercise 17-24 using the FIFO method. Note that you first need to calculate the equivalent units of work done in the current period (for direct materials and conversion costs) to complete beginning work in process, to start and complete new units, and to produce ending work in process 
FIFO method, assigning costs
FIFO method, assigning costs (continuation of 11-21). For the data in Exercise 17-19, use the FIFO method to summarize total costs to account for, calculate cost per equivalent unit for direct materials and conversion costs, and assign total costs to units completed (and transferred out) and to units in ending work in process. 
Suppose that you are the auditor of a major retail client who has reported the following...
Suppose that you are the auditor of a major retail client who has reported the following income before taxes (IBT) for the first two quarters of the year: 1st quarter = $1,200,000 2nd quarter = $1,500,000 You are in the process of establishing overall materiality for the client. Based on prior years, the client has a 10% decline in IBT from the 2nd quarter to the 3rd quarter. You also know IBT in the 4th quarter historically increases by 25%...
1. Suppose you have an investment that costs $80,000 at the beginning of the project, and...
1. Suppose you have an investment that costs $80,000 at the beginning of the project, and it generates $30,000 a year for four years in positive cash flows. The cost of capital is 12%. The IRR of the project is 18.45% and the NPV is about $11,120. The IRR model assumes that at the end of the first year you can invest the $30,000 at ________. a. 12.00% b. a rate greater than the IRR c.  rate less than the cost...
Suppose you run a bakery, briefly summarize what your major fixed costs, marginal costs, and implicit...
Suppose you run a bakery, briefly summarize what your major fixed costs, marginal costs, and implicit costs would be given by. Suppose the marginal costs associated with a loaf of bread equal $0.50. You're considering whether to charge a price of $2.00 or $3.00 for each loaf. What are the major factors that you should consider in making this decision?
In an activity-based costing system, the first step in assigning costs is to a. accumulate costs...
In an activity-based costing system, the first step in assigning costs is to a. accumulate costs for each activity. b. identify the appropriate activities for each function. c. separate nonvalue-adding activities from value-adding activities. d. analyze all nonvalue-adding activities to determine if they are necessary support areas. Harrah Company provided the following information for the month of August:                Beginning cash balance                         $ 70,000                Cash receipts                                            460,000                Cash disbursements                                 525,000 Harrah’s policy is to keep a minimum end of the month cash balance of...
You are the Project Manager for a major software development project.
a.You are the Project Manager for a major software development project. You are concerned that one of the project constraints is going unbalanced, but the project sponsor is unable to understand your concern since he is not familiar with the concept of project constraints. How would you explain this concept and its significance in project success, to the project sponsor? You can use the Iron Triangle to illustrate the concept.b. Saudi Railways has announced a project to add a new...
What does it mean to assign overhead costs? There are several options for assigning overhead costs,...
What does it mean to assign overhead costs? There are several options for assigning overhead costs, what are the common allocation bases? What others could be used? Which is the best?
What does it mean to assign overhead costs? There are several options for assigning overhead costs,...
What does it mean to assign overhead costs? There are several options for assigning overhead costs, what are the common allocation bases? What others could be used? Which is the best?
Imagine that you are a project manager who was just assigned to a new project. You...
Imagine that you are a project manager who was just assigned to a new project. You received no additional information except that your primary constraint is time and the initial cost estimates should be based on previously completed projects. Assume that you were able to find ways to gather the information you needed, and that you have already created a project plan and schedule. Now imagine that your team discovers discrepancies in the material and resource costs. Since you used...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT