Question

In: Finance

A company is evaluating two possible projects with the following cash flows. Suppose that the projects...

A company is evaluating two possible projects with the following cash flows. Suppose that the projects are contingent. Which answer describes the correct decision if the firm's required rate of return is 15%?

Year

0

1

2

3

4

Project 1

-$50

$10

$15

$10

$20

Project 2

-$30

$20

$15

$30

$10

Question 16 options:

Accept both projects.

Accept project 1 and reject project 2.

Accept project 2 and reject project 1.

Reject both projects.

Solutions

Expert Solution

NPV of Project 1
Year Cash Flow PV Factor PV Of Cash Flow
a b c=1/1.15^a d=b*c
0 $              -50 1 $                 -50.00
1 $                10 0.8695652 $                     8.70
2 $                15 0.7561437 $                   11.34
3 $                10 0.6575162 $                     6.58
4 $                20 0.5717532 $                   11.44
Net Present Value $                 -11.95
NPV of Project 2
Year Cash Flow PV Factor PV Of Cash Flow
a b c=1/1.15^a d=b*c
0 $              -30 1 $                 -30.00
1 $                20 0.8695652 $                   17.39
2 $                15 0.7561437 $                   11.34
3 $                30 0.6575162 $                   19.73
4 $                10 0.5717532 $                     5.72
Net Present Value $                   24.18
Correct Answer = Accept project 2 and reject project 1.
Reason : Proect 1 has negative NPV whereas project 2 has postive NPV.

Related Solutions

A company is evaluating two possible projects with the following cash flows. Suppose that the projects...
A company is evaluating two possible projects with the following cash flows. Suppose that the projects are contingent. Which answer describes the correct decision if the firm's required rate of return is 12%? Year 0 1 2 3 4 Project 1 -$50 $15 $15 $5 $5 Project 2 -$30 $20 $10 $10 $10
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
Suppose you are given the following two projects A and B with the cash flows below,...
Suppose you are given the following two projects A and B with the cash flows below, if the cost of capital is 10%, what is the Profitability Index (PI) of projects A and B? Year Project A Project B 0 -5000 -6000 1 1500 1500 2 2000 2500 3 3000 4000 4 3500 4000
Matterhorn Mountain Gear is evaluating two projects with the following cash flows: year project x project...
Matterhorn Mountain Gear is evaluating two projects with the following cash flows: year project x project y 0 -319,400 -299,050 1 146,100 137,300 2 163,600 154,500 3 128,700 120,250 What interest rate will make the NPV for the projects equal? a)14.22% b)18.31% c)12.64% d).26% e)18.05%
You are evaluating two projects with the following cash flows: Year Project X Project Y 0...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0 −$552,600 −$521,000 1 217,700 207,400 2 227,600 217,200 3 234,800 225,100 4 194,500 185,900 What is the crossover rate for these two projects?
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows are given in the following table. The appropriate discount rate is 11.5% per annum. Years Project X Project Y 0 -$300,000 -$350,000 1 $150,000 $150,000 2 $150,000 $150,000 3 $250,000 $200,000 4 $80,000 $200,000 5 $80,000 $200,000 IRR 42.2% 39.3% Calculate the crossover rate/incremental IRR, at which the NPV profiles for Projects A and B intersect. 2.Which project should be accepted based on your...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows...
The manager of FIRN is evaluating two mutually exclusive projects. The costs and expected cash flows are given in the following table. The appropriate discount rate is 11.5% per annum. Years Project X Project Y 0 -$300,000 -$350,000 1 $150,000 $150,000 2 $150,000 $150,000 3 $250,000 $200,000 4 $80,000 $200,000 5 $80,000 $200,000 IRR 42.2% 39.3% 1. Calculate the projects’ net present value (NPV). Identify which project should be accepted under the rule of NPV. Explain your answer.       2. What...
MC algo 5-12 Calculating Crossover Rate You are evaluating two projects with the following cash flows:...
MC algo 5-12 Calculating Crossover Rate You are evaluating two projects with the following cash flows: Year Project X Project Y 0 −$547,200 −$516,500 1 218,600 208,300 2 228,500 218,100 3 235,700 226,000 4 195,400 186,800 What is the crossover rate for these two projects? Multiple Choice .66% 22.35% 11.72% 23.01% 10.65%
choosing between two projects. The cash flows for the projects are given in the following table​...
choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A negative $ 48 −$48 $ 24 $24 $ 21 $21 $ 19 $19 $ 15 $15 B negative $ 102 −$102 $ 20 $20 $ 41 $41 $ 48 $48 $ 58 $58 a. What are the IRRs of the two​ projects? b. If your discount rate is 4.7 %...
Brian Cliff is evaluating two mutually exclusive projects                    (expected cash flows shown below). The...
Brian Cliff is evaluating two mutually exclusive projects                    (expected cash flows shown below). The firm's cost of capital is 12.25 percent.                                                                               Year                Project A             Project B                                                    0                       (600)                                      (600)                                                    1                           200                                        400                                                    2                           310                                        260                                                      3                           400                                        100                                                                 NPV?                     _____                                   _____                                                                 IRR?                       _____                                   _____                 Calculate the NPVs and IRRs for Projects A and B. Project A's NPV is $107.02, and Project B's...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT