Describe the measurements of discharge at weirs and its potential errors associated with indirect methods weir...

Describe the measurements of discharge at weirs and its potential errors associated with indirect methods weir in real-world application setting

Solutions

Expert Solution

The common sources of errors for weir installations can be broken down into four categories:

1) approach channel

2) weir installation

3) crest condition

4) downstream conditions

1 ) Approach channel

Flow approaching a weir installation should be no more than 0.5 fps and the upstream channel (weir pool) should be straight and of uniform cross-section for 20 times the maximum anticipated head (Hmax).  

Additionally, the channel must be at least as wide as 2Hmax on either side of the crest level at Hmax.

Conditions that differ from the above will result in a poor approach velocity profile, which will degrade a weir's accuracy.

2) weir Installation

For a weir to work correctly it must be mounted so that the crest is centered in the channel, level from side to side, and vertically plumb.  Deviation in any respect will impact the flow accuracy of the installation.

3 ) Crest Condition

Precise flow measurement with a weir requires that the crest of the weir be:

  • Good condition (without nicks or abrasions)
  • Sharp (but not knife edged due to the difficulties in maintaining the edge) (no rounding of the crest)
  • Free of rust, debris, growth, or trash accumulation

4) Downstream Conditions

Downstream conditions typically refer to the water level after the weir - and if it is high enough to submerge the  nappe (body of water flowing over the weir crest).  

When the downstream water level is high enough it will impede the flow of water over the weir.  Weir submergence dramatically affects the actual flow rate (versus the higher indicated flow rate).


Related Solutions

describe the action potential associated with the sinoatrial node.
describe the action potential associated with the sinoatrial node.
1) Describe how you can use measurements of stream height (stage) to estimate discharge and what...
1) Describe how you can use measurements of stream height (stage) to estimate discharge and what pieces you need to do so. (I’m looking for you to describe both the curve and one method for making discharge measurements) 2) If a flood occurs and erodes the channel where we are measuring stage, can we still use the same relationship between stage and discharge? Why or why not?
Define and describe the difference between the direct and indirect methods for calculating the cash flow...
Define and describe the difference between the direct and indirect methods for calculating the cash flow from operating activities. What are the other major sections of the cash flow statement? Describe the main functions of these components.
Describe the potential social, economic, and cultural implications associated with the Baby-Friendly Hospital Initiative. Describe how...
Describe the potential social, economic, and cultural implications associated with the Baby-Friendly Hospital Initiative. Describe how the registered nurse can overcome the obstacles to make the Baby-Friendly Initiative a success. 250 words or more please The Baby-Friendly Hospital Initiative (BFHI) is a program developed by the World Health Organization (WHO) and the United Nations Children's Fund (UNICEF) to promote breastfeeding in hospitals and birthing facilities worldwide. Since the program was launched in 1991, breastfeeding initiation, duration, and exclusivity have increased...
Describe laboratory and geophysical methods to measure intact rock strength. Explain why measurements of rock strength...
Describe laboratory and geophysical methods to measure intact rock strength. Explain why measurements of rock strength alone are insufficient to assess the difficulty of excavation and the likely stability of the rock mass during and after construction.
Describe how to calculate cash flows from operating activities under both the direct and indirect methods.
Describe how to calculate cash flows from operating activities under both the direct and indirect methods.
In your own words (Easy words, not difficult one), describe potential errors when performing multiple regression....
In your own words (Easy words, not difficult one), describe potential errors when performing multiple regression. What are some ways to respond to such pitfalls? In addition, describe ways to prevent such pitfalls during data collection. ( Please answer the questions asked, I already asked this question before, but the expert answered something else).
Discuss potential methods to linearize body source terms in search for a stable solution and Describe:...
Discuss potential methods to linearize body source terms in search for a stable solution and Describe: -Relations that could be used to couple pressure and density with heat addition -The role or meaning of characteristic curves in a flow field -Shock-capturing techniques in flow fields
Discuss potential methods to linearize body source terms in search for a stable solution and Describe:...
Discuss potential methods to linearize body source terms in search for a stable solution and Describe: -Relations that could be used to couple pressure and density with heat addition -The role or meaning of characteristic curves in a flow field -Shock-capturing techniques in flow fields
Who are three I/O theorists or psychologists and describe the potential impact of their research methods
Who are three I/O theorists or psychologists and describe the potential impact of their research methods
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT