Question

In: Accounting

Ron’s Data Corp.? (RDC) entered into a contract that provides RDC with the? right-of-use of a...

Ron’s Data Corp.? (RDC) entered into a contract that provides RDC with the? right-of-use of a vehicle for one year at which time the asset is returned to the lessor. The fair value of the car is? $40,000. Terms of the contract require RDC to make payments of? $1,000 per month with the first payment due on March? 31, 2018, the commencement date of the lease. RDC knows that the implicit rate in the lease is? 0.5% per month. Assume that RDC elects to expense leases of a? short-term nature. Determine the cost of the? right-of-use asset at the commencement date of the lease

Solutions

Expert Solution

Monthly payment = $1,000

Lease period = 12 months.

Implicit rate of interest = 0.5% per month.

To calculate the cost of lease at the commencement date of the lease i.e 03/31/2018, all we have to do is to calculate the present value (as on 03/31/2018) of monthly lease payment using monthly implicit rate of interest.

Present value (PV) of annuity = P [(1-(1+r)-n) / r]

Where p = Monthly payments = $1,000

r = Implicit rate of interest = 0.5% per month

n = Number of installments = 11 (in months)

*Note - The reason why we are adding "1st installment" in the above formula is that PDC is paying the first installment on the day of the commencement of the lease i.e 03/31/2018. We don't have to bring that first installment amount to the present value since that amount itself represents present value.

Therefore pv of annuity = 1000 + 1000[(1-0.67)11) / 0.5]

= $2975

Cost of leased payments as on the day commencement of lease = $2975


Related Solutions

In the law of contract, once the contracting parties agree and the contract is entered into,...
In the law of contract, once the contracting parties agree and the contract is entered into, nothing can spoil, impair or destroy the contract.Discuss
In the law of contract, once the contracting parties agree and the contract is entered into,...
In the law of contract, once the contracting parties agree and the contract is entered into, nothing can spoil, impair or destroy the contract.Discuss
JCPenny entered into a contract with Emma. The contract begins on May 1 and ends on...
JCPenny entered into a contract with Emma. The contract begins on May 1 and ends on November 31, 2020. JCpenny will exchange 100 of their most popular watches at a discount as well as 100 glasses for brand-specific marketing. The regular wholesale price of the shirts is $65. JcPenny expects the cost to produce each mask will be $6. All goods that they sell have a profit margin of about 54%. Being able to carry these exclusive products is important...
On 31 January 2019, Ben Chan (Ben) entered into a contract of a 6-month 5G Data...
On 31 January 2019, Ben Chan (Ben) entered into a contract of a 6-month 5G Data and Wifi Plan with the Entity A, the largest local telecom service supplier in Hong Kong. The contract terms are listed as below: The fixed monthly fee is $800 per month; and At the inception stage of the plan, a free X-Phone is given to Ben for inviting him to join the service plan. The 5G Data Service and the Wifi Service will start...
Customer Ltd enters into a 10-year contract with Supplier Ltd for the right to use two...
Customer Ltd enters into a 10-year contract with Supplier Ltd for the right to use two specified physically distinct dark fibres within a larger cable connecting Hong Kong to Tokyo. Customer Ltd makes the decisions about the use of the fibres by connecting each end of the fibres to its electronic equipment (i.e., Customer ‘light’ the fibres and decides what data and how much data to transfer). If the fibres are damaged, Supplier Ltd is responsible for the repairs and...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract provided for progress payments. RCL’s accounting year ends December 31. Work began under the contract on August 1, 2019, and was completed on October 31, 2021. RCL uses the percentage-of-completion method to account for this long-term contract. Construction activities are summarized below: 2019 2020 2021 Construction costs incurred to date 180,000 630,000 825,000 Estimated remaining costs to complete 630,000 190,000 0 Progress Billings during...
Turner Construction entered into a contract to provide general construction of Granby Towers. Turner then entered...
Turner Construction entered into a contract to provide general construction of Granby Towers. Turner then entered into a subcontract with Universal to install precast concrete floors in the Granby Towers construction project. The general construction contract was incorporated by reference into the subcontract. The contract between Turner and Universal contained a “pay-when-paid provision” that conditioned any payments to Universal on Turner’s first receiving payment from Universal. Due to the economic downturn, financing for the project fell through. Universal had substantially...
Contract law?Use IRAC to analysis the problem. Laura is an artist. She creates sculptures. She entered...
Contract law?Use IRAC to analysis the problem. Laura is an artist. She creates sculptures. She entered into a contract with the ‘Master Art’ a business who sells artworks in Hahndorf. A term of the contract requires that Laura creates 3 sculptures every year for Master Art. At the end of the first year, Laura has created only 2 sculptures. Master Art wants to terminate the contract and Laura is not happy with this. Advise Laura and Master Arts.
The following table provides data for a project. Use the data to answer the following questions...
The following table provides data for a project. Use the data to answer the following questions Activity Immediate Predecessor Time Estimates (weeks) Optimistic Most Likely Pessimistic Expected Variance A - 6 7 14 B - 8 10 12 C A 2 3 4 D A 6 7 8 E B,C 5 5.5 9 F B,C 5 7 9 G D,E 4 6 8 H F 2.5 3 3.5 Draw a network to represent the above project. What is the critical...
You have entered a short position in an oil futures contract. The contract size is 1,000...
You have entered a short position in an oil futures contract. The contract size is 1,000 barrels for each contract. The initial margin required is $20,000 per contract. The maintenance margin is $16,000. The contract is entered at market close on January 7 at a price of $100/barrel. Fill in the table below. If a margin call occurs, indicate in the margin call column the amount that has been added to the margin account as a result of the margin...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT