Question

In: Operations Management

Turner Construction entered into a contract to provide general construction of Granby Towers. Turner then entered...

Turner Construction entered into a contract to provide general construction of Granby Towers. Turner then entered into a subcontract with Universal to install precast concrete floors in the Granby Towers construction project. The general construction contract was incorporated by reference into the subcontract. The contract between Turner and Universal contained a “pay-when-paid provision” that conditioned any payments to Universal on Turner’s first receiving payment from Universal. Due to the economic downturn, financing for the project fell through. Universal had substantially completed all its work by that time, and it sought payment of $885,507 from Turner, which refused to pay because it had not received any payment from the owner of the project. Turner asked the court for summary judgment on Universal’s breach-of-contract claim. Should the court’s grant of summary judgment be upheld? Why or why not? [Universal Concrete Products v. Turner Construction Co., 4th Cir. Case No. 09- 1569 (2010).]

Solutions

Expert Solution

As per scenario mentioned above, the agreement has clearly stated “pay-when-paid provision” which means unless Turner would not receive the payment from the owner of the project they cannot make the payment to the subcontractor which is Universal.
Although the work has been completed by Universal, they cannot claim the payment as they are in agreement with Turner about the payment clause. Judgements are always done on the basis of documents/ contracts/ valid proofs in court of law. If turner asks for summary of judgement presenting all the documentation of the contracts/sub-contracts & prove that payment has still not made to them by the owner, then yes court can validate the case & verify the findings & provide the judgement. All the documents related to payment & valid communication about the payments along with copies of contracts/sub-contracts needs to be presented in court of law so that the judgement can be upheld.


Related Solutions

Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract provided for progress payments. RCL’s accounting year ends December 31. Work began under the contract on August 1, 2019, and was completed on October 31, 2021. RCL uses the percentage-of-completion method to account for this long-term contract. Construction activities are summarized below: 2019 2020 2021 Construction costs incurred to date 180,000 630,000 825,000 Estimated remaining costs to complete 630,000 190,000 0 Progress Billings during...
Action Steel entered into a contract with Systems Builders for the construction of an addition to...
Action Steel entered into a contract with Systems Builders for the construction of an addition to a commercial building. Systems Builders was the general contractor and agreed to erect a building designed and manufactured by Varco-Pruden. Part of Systems Builders’ contract with Action Steel included an agreement for the parties not to sue each other or any subcontractors or agents if another insurance plan was taken out on neighboring properties or the finished project. During the first winter after construction...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 50 $ 150 $ 45 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018   Costs incurred during the year $ 50 Estimated costs to complete as of December 31 $200 2019  Costs incurred during...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 40 $ 80 $ 50 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 70 $ 60 $ 30 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $340 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 40 $ 120 $ 50 Estimated costs to complete as of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 70 $ 60 $ 30 Estimated costs to complete as of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT